United States v. Tandem Roofing, LLC

CourtDistrict Court, E.D. Louisiana
DecidedMarch 26, 2025
Docket2:23-cv-02293
StatusUnknown

This text of United States v. Tandem Roofing, LLC (United States v. Tandem Roofing, LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Tandem Roofing, LLC, (E.D. La. 2025).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF LOUISIANA UNITED STATES OF AMERICA CIVIL ACTION FOR THE USE AND BENEFIT OF EXPOSED ROOF DESIGN, LLC VERSUS NO. 23-2293 TANDEM ROOFING, LLC, ET AL. SECTION “O” ORDER AND REASONS Before the Court is the Federal Rule of Civil Procedure 12(b)(6) motion1 of Miller-Act Plaintiff United States of America, for the Use and Benefit of Exposed Roof Design, LLC (“Exposed”), to dismiss the unjust enrichment counterclaim of Defendant Tandem Roofing, LLC (“Tandem”). Tandem opposes2 the motion. For the reasons that follow, Exposed’s 12(b)(6) motion to dismiss Tandem’s unjust enrichment counterclaim is GRANTED.

I. BACKGROUND This case arises from a dispute over a project to repair and replace the roof at the Naval Air Station Joint Reserve Base New Orleans in Belle Chasse, Louisiana.3 The Department of Navy selected E&F Construction (“E&F) as the prime contractor on the project.4 In turn, E&F contracted with Tandem, a commercial and industrial roofing company, to provide roofing materials and perform limited roofing work.5

1 ECF No. 25. 2 ECF No. 27. 3 See generally ECF No. 19. 4 Id. ¶¶ 1, 14. 5 Id. ¶¶ 14–17. Tandem then entered into a subcontract (“Subcontract”) with Exposed whereby Tandem agreed to pay Exposed $215,625 to supply labor for the project.6 In its First Amended Complaint, Exposed alleges that Tandem mismanaged

the project.7 Exposed claims that, after less than a month of work, it realized that payment of $215,625 was insufficient to cover its labor and costs.8 So Exposed and Tandem executed a change order requiring Tandem to pay Exposed an additional $215,625 for additional labor.9 Soon after, according to Exposed, Tandem informed Exposed that it lacked the funds to keep Exposed on the project.10 Exposed claims that, over the next several

months, Tandem repeatedly promised to pay the amount owed.11 But Tandem eventually changed its position and informed the company that it would make no further payments.12 Exposed now brings this action against Tandem and E&F, along with Markel Insurance Company and SureTec Insurance Company (collectively, the “Sureties”), to recover the unpaid balance owed by Tandem and additional damages.13 Specifically, Exposed brings claims against Tandem for breach of contract, a violation of the Texas Prompt Payment Act, and quantum meruit; and it brings a claim against

E&F, Markel, and SureTec under the Miller Act.14

6 Id. ¶ 19; ECF No. 19-1. This was the first project to use Tandem’s newly developed roofing system. ECF No. 19 ¶ 1. 7 Id. ¶ 22. 8 Id. ¶¶ 23–24. 9 Id. ¶¶ 24–25; ECF No. 19-2. 10 ECF No. 19 ¶ 26. 11 Id. ¶ 28. 12 Id. ¶¶ 26, 28–34. 13 ECF Nos. 1, 19. 14 ECF No. 19. Exposed’s First Amended Complaint withdrew both its Miller Act claim against Tandem and its Federal Prompt Payment claim against all Defendants. Tandem asserts counterclaims against Exposed.15 In its First Amended Answer to Plaintiff’s First Amended Complaint and Original Counterclaim, Tandem acknowledges that, under the terms of the Subcontract, Tandem initially agreed to

pay Exposed $215,625 for labor.16 Tandem claims to have made the first payment of $53,906.25 in accordance with the Subcontract’s terms.17 Approximately one month later, according to Tandem, Exposed “demanded” that Tandem agree to a change order that doubled the cost of the project, and “threaten[ed]” to withhold Exposed workers from the project if Tandem didn’t comply.18 Tandem alleges that, “[u]nder this duress,” it agreed to the change order and additional payment of $215,625.19

Tandem subsequently made a second payment to Exposed in the amount of $59,000.20 The following month, according to Tandem, Exposed “demanded a second change order” in the amount of “$400,000 more.”21 At that point, Tandem gave notice to Exposed that it was exercising Section 12.10 of the Subcontract, the “termination for convenience” provision.22 Under that provision, Tandem was permitted to terminate the Subcontract with seven-days’ notice “for any reason and without any default under the agreement.”23 Triggering this provision meant that Tandem would

be required to pay Exposed, “as its entire and sole compensation,” the “actual necessary and reasonable costs of performing the work to the date of termination . . .

15 ECF No. 22. 16 Id. at 8. 17 Id. 18 Id. 19 Id. at 9 20 Id. 21 Id. 22 Id.; ECF No. 19-1 at 16. 23 Id. plus a reasonable mark-up for overhead and profit as to such work only.”24 This amount would be determined “by an audit of [Exposed’s] records.”25 In turn, Exposed was required to make its records “available at reasonable times and places for

[Tandem’s] audit.”26 According to Tandem, Exposed did not fulfill its obligation under Section 12.10 to make its records reasonably available.27 Unable to perform the audit, and “out of an abundance of caution, on the demand of [Exposed],” Tandem nevertheless paid Exposed an additional $102,718.75.28 Tandem claims to have paid Exposed $215,625 over the course of the project—

which is 50% of the agreed-upon payment under the Subcontract and the change order.29 After terminating the contract, Tandem “worked with E&F” to determine how much of the project Exposed completed.30 They concluded that Exposed completed 30% of the total project.31 Thus, according to Tandem, Exposed owes Tandem $86,250, which represents the amount Tandem paid Exposed, less 30% the total contract value.32

Tandem now brings two counterclaims against Exposed: (1) breach of contract, based on Exposed’s refusal to allow Tandem to audit its records and Tandem’s

24 ECF No. 22 at 9–10; ECF No. 19-1 at 16. 25 Id. 26 Id. 27 ECF No. 22 at 10. 28 Id. 29 Id. 30 Id. 31 Id. 32 Id. subsequent overpayment on the contract, and (2) unjust enrichment, based on the same overpayment. Exposed moves to dismiss Tandem’s unjust enrichment counterclaim under

Rule 12(b)(6).33 Because the case comes to the Court on Exposed’s Rule 12(b)(6) motion to dismiss Tandem’s counterclaim, the Court accepts as true all well-pleaded facts in the counterclaim and construes the allegations in the light most favorable to Tandem. See Lewis v. Danos, 83 F.4th 948, 953 (5th Cir. 2023) (citing Heinze v. Tesco Corp., 971 F.3d 475, 479 (5th Cir. 2020)). II. LEGAL STANDARD

“To survive a motion to dismiss, a complaint must contain sufficient factual matter, accepted as true, to ‘state a claim to relief that is plausible on its face.’” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (quoting Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007)). “A claim has facial plausibility when the plaintiff pleads factual content that allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged.” Id. (citing Twombly, 550 U.S. at 556). In its Rule 12(b)(6) review, the Court “accept[s] all well-pleaded facts as true and construe[s] the

allegations in the light most favorable to the plaintiff.” Lewis, 83 F.4th at 953. The Court also “may consider ‘any documents attached to the motion to dismiss that are central to the claim and referenced in the complaint.’” PHI Grp., Inc. v. Zurich Am. Ins. Co., 58 F.4th 838, 841 (5th Cir. 2023) (quoting Lone Star Fund V (U.S.), L.P. v. Barclays Bank PLC, 594 F.3d 383, 387 (5th Cir. 2010)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coghlan v. Wellcraft Marine Corp.
240 F.3d 449 (Fifth Circuit, 2001)
Lone Star Fund v (U.S.), L.P. v. Barclays Bank PLC
594 F.3d 383 (Fifth Circuit, 2010)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Fortune Production Co. v. Conoco, Inc.
52 S.W.3d 671 (Texas Supreme Court, 2000)
Burlington Northern Railroad v. Southwestern Electric Power Co.
925 S.W.2d 92 (Court of Appeals of Texas, 1996)
First Union National Bank v. Richmont Capital Partners I, L.P.
168 S.W.3d 917 (Court of Appeals of Texas, 2005)
Leonard Panella v. Tesco Corporation
971 F.3d 475 (Fifth Circuit, 2020)
King v. Baylor University
46 F.4th 344 (Fifth Circuit, 2022)
Janvey v. Alguire
846 F. Supp. 2d 662 (N.D. Texas, 2011)
PHI Group v. Zurich American Insurance
58 F.4th 838 (Fifth Circuit, 2023)
Lewis v. Danos
83 F.4th 948 (Fifth Circuit, 2023)
Hodge v. Engleman
90 F.4th 840 (Fifth Circuit, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
United States v. Tandem Roofing, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-tandem-roofing-llc-laed-2025.