United States v. Tandem Roofing, LLC

CourtDistrict Court, E.D. Louisiana
DecidedNovember 15, 2023
Docket2:23-cv-02293
StatusUnknown

This text of United States v. Tandem Roofing, LLC (United States v. Tandem Roofing, LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Tandem Roofing, LLC, (E.D. La. 2023).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF LOUISIANA

UNITED STATES OF AMERICA CIVIL ACTION FOR THE USE AND BENEFIT OF EXPOSED ROOF DESIGN, LLC

VERSUS CASE NO. 23-2293 TANDEM ROOFING, LLC et al. SECTION: “G”(5) ORDER AND REASONS

Before the Court is Defendant Tandem Roofing, LLC’s (“Tandem”) Motion to Dismiss, Sever, and Transfer Venue.1 In this litigation, Plaintiff Exposed Roof Design LLC (“Exposed”) seeks to recover payments for work it performed but which Tandem and other Defendants did not tender.2 Tandem moves to dismiss Exposed’s Miller Act and Federal Prompt Payment Act claims under Rule 12(b)(6).3 Tandem also moves to sever the state common law claims Exposed asserted against it and transfer those claims to the Northern District of Texas because of a forum selection clause in the contract between Exposed and Tandem.4 In response, Exposed filed an Amended Complaint, which withdraws the Miller Act and Federal Prompt Payment Act claims against Tandem mooting the Rule 12(b)(6) arguments.5 Exposed also argues that the inconvenience non- signatory Defendants to the contract containing the forum selection clause would face if the case is severed and transferred, as well as judicial economy concerns, favor keeping the case in this

1 Rec. Doc. 16. 2 Rec. Doc. 1. 3 Rec. Doc. 16. 4 Id. 5 Rec. Doc. 19. Court.6 Having considered the motions, the memoranda in support and in opposition, the record, and the applicable law, the Court finds the motion to dismiss moot and denies the motion to sever and transfer. I. Background

On June 30, 2023 Exposed filed a Complaint against Defendants Tandem, E&F Construction (“E&F”), Markel Insurance Company (“Markel”), and SureTec Insurance Company (“Suretec”) in this Court.7 Exposed seeks to recover damages for work it allegedly performed but was not paid for as a subcontractor on a construction project (“Project”) related to the repair of two buildings at the Naval Air Station Joint Reserve Base New Orleans in Belle Chasse, Louisiana.8 Exposed is a construction company that among its services, provides roofing materials and performs roofing work.9 Tandem is a commercial and industrial roofing company that was a subcontractor to E&F, the prime contractor that contracted with the Department of the Navy to work on the Project.10 Exposed alleges that on or around August 29, 2022, it entered into a $215,635 subcontract with Tandem to “provide labor and install the roofing system” for the Project.11 Exposed alleges

that it priced its labor according to Tandem’s estimate that the Project would be completed in four weeks.12 Exposed alleges that it then performed work from September 12, 2022 to October 7,

6 Rec. Doc. 20. 7 Rec. Doc. 1. 8 Id. at 1. 9 Id. 10 Id. at 1–2. 11 Id. at 5. 12 Id. 2022, but Tandem caused significant delays to the Project.13 Specifically, Exposed alleges that “Tandem failed to (1) properly prepare the Project site for installation; (2) estimate the proper amount of roofing material to supply the Project; (3) estimate the time that it would take for installation; and (4) ensure that a sufficient amount of roofing material was onsite.”14 Exposed

alleges that as a result of the delay, Tandem signed Change Order #1 (“Change Order” and collectively with the Subcontract, the “Agreement”) to pay Exposed another $215,625 for four weeks of labor and costs for the Project.15 Exposed alleges, however, Tandem later notified Exposed “it no longer had the funds to keep [Exposed] on the Project.”16 Exposed alleges that as a result of this news and to preserve its rights under the Miller Act, Exposed “timely sent its notice of intent to … E&F on or around November 15, 2023.”17 Exposed further alleges that from November 2022 through mid-May 2023, Tandem “repeatedly represented ” to Exposed that it would be paid the additional $215,625 under the Change Order, but ultimately, Tandem did not pay Exposed.18 Exposed alleges that it finally sent Tandem a formal demand letter for payment on March 24, 2023, to which Tandem responded that it would send payment of the $215,625 in two checks.19 Exposed alleges that it received the

first check from Tandem on April 17, 2022, but the check could not be cashed because there were

13 Id. 14 Id. 15 Id. at 5–6. 16 Id. at 6. 17 Id. 18 Id. 19 Id. insufficient funds.20 Exposed alleges that although Tandem initially responded that it would re- issue the bounced check, it ultimately did not and thereafter did not make further payments.21 Exposed alleges that E&F secured a payment bond, Bond No. 4415766 (“Payment Bond”), issued by Markel and Suretec on or about June 10, 2020, as part of its obligations under the Miller Act.22 Exposed alleges that it sent a letter to E&F notifying them of a claim for $327,238.28

(“Miller Act Notice”).23 Exposed alleges that after it provided Miller Act Notice, Tandem paid it $102,718.75.24 Exposed further alleges that Defendants are jointly and severally liable for the $215,625 left on the balance of its claim.25 In the original Complaint, Exposed brought several causes of action against Defendants. First, Exposed brought a breach of contract cause of action against Tandem, alleging that Tandem failed to make payment under the Agreement despite Exposed performing the work it was required to under the Contract.26 In addition to recovering payment owed from the Agreement, Exposed sought “interest, reasonable attorney’s fees under Texas Civil Practice & Remedies Code Chapter 38, and costs incurred in the prosecution of this lawsuit …”27 Second, Exposed brought a Miller

Act claim against all Defendants, asserting that when Suretec and Markel issued the Payment Bond, they “undertook a direct obligation with the United States of America to act as the surety

20 Id. at 7. 21 Id. 22 Id. 23 Id. at 8. 24 Id. 25 Id. 26 Id. 27 Id. at 9. with respect to E&F and Tandem’s obligations to make payments to subcontractors and suppliers for labor and materials furnished to the Project.”28 Exposed asserted that it met the requirements for bringing a Miller Act claim because it provided labor for the Project, was not paid in full within 90 days after the day on which it last worked on the Project, was a second-tier subcontractor who

contracted directly with a first-tier subcontractor, Tandem, timely sent its notice of intent to E&F as the prime contractor on the Project, and filed this instant lawsuit less than a year after it last provided labor and services to the Project.29 Third, Exposed brought a Federal Prompt Payment claim against all Defendants, alleging that the payments Defendants owed are accruing statutory interest.30 Finally, Plaintiff brought a quantum meruit claim against Tandem for “recovery of the reasonable value of the services and materials, interest …, [and] attorneys’ fees and costs.”31 On August 29, 2023, Tandem moved to dismiss the Miller Act and Federal Prompt Pay Act claims against it, sever the breach of contract and quantum meruit claims against it from the claims asserted against E&F, Markel, and Suretec, and transfer those claims to the Northern District of Texas.32 On August 29, 2023, Exposed file a response opposing Tandem’s motion.33

On the same day, Exposed also filed a First Amended Complaint to withdraw its Miller Act claim against Tandem and the Federal Prompt Payment claim against all Defendants.34 Exposed also added a Texas Prompt Payment Act against Tandem, alleging that Tandem received payment for

28 Id. 29 Id. at 9–10. 30 Id. at 10 (citing to 31 U.S.C. § 3901 et. seq.). 31 Id. 32 Rec. Doc. 16. 33 Rec. Doc. 20. 34 Rec. Doc. 19.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brunet v. United Gas Pipeline Co.
15 F.3d 500 (Fifth Circuit, 1994)
Applewhite v. Reichhold Chemicals, Inc.
67 F.3d 571 (Fifth Circuit, 1995)
DTEX, LLC v. BBVA Bancomer, S.A.
508 F.3d 785 (Fifth Circuit, 2007)
Acevedo v. Allsup's Convenience Stores, Inc.
600 F.3d 516 (Fifth Circuit, 2010)
Piper Aircraft Co. v. Reyno
454 U.S. 235 (Supreme Court, 1982)
Phillips v. Audio Active Ltd.
494 F.3d 378 (Second Circuit, 2007)
Morris v. Northrop Grumman Corp.
37 F. Supp. 2d 556 (E.D. New York, 1999)
In Re: Rolls Royce Corporation
775 F.3d 671 (Fifth Circuit, 2014)
Peter Weber v. Pact XPP Technologies, AG
811 F.3d 758 (Fifth Circuit, 2016)
Jonathan Barnett v. Dyncorp International, L.L.C.
831 F.3d 296 (Fifth Circuit, 2016)
Defense Distributed v. Bruck
30 F.4th 414 (Fifth Circuit, 2022)
Jolley v. Welch
904 F.2d 988 (Fifth Circuit, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
United States v. Tandem Roofing, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-tandem-roofing-llc-laed-2023.