Burlington Northern Railroad v. Southwestern Electric Power Co.

925 S.W.2d 92, 1996 WL 207269
CourtCourt of Appeals of Texas
DecidedJuly 16, 1996
Docket06-95-00024-CV
StatusPublished
Cited by76 cases

This text of 925 S.W.2d 92 (Burlington Northern Railroad v. Southwestern Electric Power Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Burlington Northern Railroad v. Southwestern Electric Power Co., 925 S.W.2d 92, 1996 WL 207269 (Tex. Ct. App. 1996).

Opinions

OPINION

BLEIL, Justice.

Burlington Northern Railroad Company (Burlington) appeals a judgment entered in favor of Southwestern Electric Power Company (SWEPCO) following a jury trial. Burlington challenges the trial court’s submission of certain jury questions, entry of a declaratory judgment, and award of attorney’s fees. SWEPCO raises two conditional cross-points of error challenging certain evi-dentiary rulings made by the trial court for our consideration only in the event we decide to reverse the judgment. We sustain each of Burlington’s points of error, overrule SWEP-CO’s cross-points, and render judgment that SWEPCO take nothing.

In 1974, Burlington and SWEPCO entered into a long-term contract1 for the hauling of coal from Wyoming to two SWEPCO power plants in Texas and Arkansas.2 The contract called for shipments to the Welsh plant to commence on October 1, 1976, and continue for twenty-five years. Shipments to the Flint Creek plant were to commence in 1977, and also continue for twenty-five years.

Initial shipping rates to be charged by the railroads were listed in the contract. In an appendix to the contract, a clause entitled “Escalation Formula” provided that the rates would be adjusted once each year according to the AAR Western Index of Railroad Material Prices, Wage Rates and Supplements Combined, published annually by the Interstate Commerce Commission. Immediately following the escalation formula provision was this clause entitled “Formula Intent”:

It is the intent of [the parties] that the formula described above will compensate [the railroads] for any changes in the cost of transporting SWEPCO’s coal tonnages above or below the 1971 base cost level. If any one of the parties should suffer a gross inequity as a result of unusual economic conditions, which result in the formula failing to fairly cover cost changes, such inequities will be resolved by mutual agreement among [the parties]. Pending such agreement, no party shall be relieved of its [96]*96obligations as outlined in the effective tariff.

In 1984, the parties entered into a second contract which superseded the original contract as to the Welsh plant only. The terms of this contract were similar to those of the first, including the escalation formula and formula intent clauses, except that the rates were to be adjusted quarterly based on the Interstate Commerce Commission Interim Mid-Quarter Forecast Index. The first contract continued in force as to the Flint Creek plant. Both contracts specified minimum and maximum quantities of coal to be shipped each year.

Each year since the effective dates of the contracts, Burlington has delivered and SWEPCO has received quantities of coal within the annual contractual ranges. Rates have been computed according to the formulas and indexes specified in each contract.

In thé late 1980s, SWEPCO began to suspect that Burlington’s costs of transporting coal were not increasing at the same rate at which the industry indexes were causing shipping charges to rise under the contract. Following unsuccessful negotiations with Burlington, SWEPCO filed this suit, claiming that under the contracts’ formula intent clauses, it had suffered gross inequities as a result of unusual economic conditions which caused the formulas to fail to fairly cover changes in the cost of transporting the coal. SWEPCO sought damages for alleged overcharges caused by discrepancies between Burlington’s actual shipping costs and the rates charged from 1987 to 1994.

The jury found that SWEPCO had not suffered a gross inequity under either contract as a result of the escalation formulas failing to fairly cover changes in Burlington’s cost of transporting SWEPCO’s coal.3 In response to additional questions, however, the jury found that Burlington had received an unjust enrichment of $100 million from SWEPCO’s payments under both contracts ($25 million for Flint Creek and $75 million for Welsh).4 The trial court later reduced this total to $71,668,258.00 pursuant to a pretrial litigation agreement between the parties to grant Burlington credit for a portion of SWEPCO’s settlement with the other original defendants. The jury also found that SWEPCO was entitled to attorney’s fees of $2 million. The court entered judgment on these findings. In addition, the court entered a declaratory judgment governing the shipping rates to be charged for the remainder of the life of each contract. The judgment declared that the rates calculated by the escalation formulas were interim rates and ordered that the correct and final rate for each futuré period under the contract be set at that amount necessary to compensate Burlington for changes in its costs of transporting SWEPCO’s coal above or below the base costs specified in the original contracts.

Burlington contends that the trial court erred in submitting to the jury the questions regarding unjust enrichment. Burlington argues that recovery by SWEP-CO of alleged overcharges under principles of unjust enrichment is barred because the issue of the rates to be charged for the coal shipments was fully addressed by the contracts themselves. Burlington asserts that the jury’s finding that SWEPCO suffered no gross inequity, as defined in the contracts’ formula intent clauses, prohibits SWEPCO from challenging the rates it paid under the express terms of the contract.

The doctrine of unjust enrichment belongs to the measure of damages known as quasi-contract or restitution. LaChance v. [97]*97Hollenbeck, 695 S.W.2d 618, 620 (Tex.App.—Austin 1985, writ ref'd n.r.e.); see also 1 ARTHUR L. Corbin, Corbin on Contracts § 1.20 (rev. ed. 1993); 5 Arthur L. Corbin, Corbin on Contracts §§ 1102, 1104 (1964); 42 C.J.S. Implied and Constructive Contracts §§ 4-6 (1991); cf. Ferrous Prods. Co. v. Gulf States Trading Co., 323 S.W.2d 292, 296-97 (Tex.Civ.App. — Houston 1959), aff'd, 160 Tex. 399, 332 S.W.2d 310 (1960). The purpose of restitution is to place an aggrieved plaintiff in the position he occupied prior to his dealings with the defendant. 42 C.J.S. Implied and Constructive Contracts § 6; 5 Corbin § 1102. This purpose is accomplished by requiring the defendant to return to the plaintiff any rendered performance to which the defendant is not entitled. 5 Corbin § 1102.

The unjust enrichment doctrine applies the principles of restitution to disputes which for one reason or another are not governed by a contract between the contending parties. See Lone Star Steel Co. v. Scott, 759 S.W.2d 144, 154 (Tex.App. — Texarkana 1988, writ denied). When a defendant has been unjustly enriched by the receipt of benefits in a manner not governed by contract, the law implies a contractual obligation upon the defendant to restore the benefits to the plaintiff. Barrett v. Ferrell, 550 S.W.2d 138, 143 (Tex.Civ.App. — Tyler 1977, writ refd n.r.e.); 42 C.J.S. Implied and Constructive Contracts § 5. Unjust enrichment is typically found under circumstances in which one person has obtained a benefit from another by fraud, duress, or the taking of an undue advantage. Heldenfels Bros. v. City of Corpus Christi

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Norman v. FCA US, LLC
E.D. Michigan, 2023
Derick Ortiz, v. Sig Sauer, Inc.
2023 DNH 015 (D. New Hampshire, 2023)
King v. Baylor University
46 F.4th 344 (Fifth Circuit, 2022)
Elbar Invs., Inc. v. Okedokun (In re Okedokun)
593 B.R. 469 (S.D. Texas, 2018)
Freeman v. Harleton Oil & Gas, Inc.
528 S.W.3d 708 (Court of Appeals of Texas, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
925 S.W.2d 92, 1996 WL 207269, Counsel Stack Legal Research, https://law.counselstack.com/opinion/burlington-northern-railroad-v-southwestern-electric-power-co-texapp-1996.