United States v. Skidmore, Owings & Merrill

505 F. Supp. 1101, 28 Cont. Cas. Fed. 81,272, 1981 U.S. Dist. LEXIS 9394
CourtDistrict Court, S.D. New York
DecidedJanuary 29, 1981
Docket80 Civil 3060
StatusPublished
Cited by14 cases

This text of 505 F. Supp. 1101 (United States v. Skidmore, Owings & Merrill) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Skidmore, Owings & Merrill, 505 F. Supp. 1101, 28 Cont. Cas. Fed. 81,272, 1981 U.S. Dist. LEXIS 9394 (S.D.N.Y. 1981).

Opinion

OPINION

EDWARD WEINFELD, District Judge.

In this suit brought by the United States against the architectural firm Skidmore, Owings & Merrill (“Skidmore”) on claims based on indemnification, breach of contract and breach of warranty arising out of a contract for the design and construction of the Joseph H. Hirshhorn Museum and Sculpture Garden in Washington, D. C., defendant Skidmore moves pursuant to Rule 12(b)(6) of the Federal Rules of Civil Procedure to dismiss the complaint on the grounds that all claims are barred by the applicable statute of limitations and that defendant as an architectural firm cannot be held liable for breach of warranty. The Government, in resisting the motion, has submitted an affidavit and certain evidentiary material; the Court thus treats the motion as one for summary judgment under Rule 56. For the reasons set forth below, defendant’s motion is granted in part and denied in part.

The facts alleged in the complaint and contained in the Government’s supporting material, which for purposes of this motion are accepted as true, are rather simple. The United States, acting through the General Services Administration (“GSA”), entered into a contract for architectural and engineering services with Skidmore in August 1967 in connection with the construction of the museum. Among other things, the contract required Skidmore to prepare specifications to be included in the contract for the construction of the museum, and also to review and approve architectural and structural shop drawings. In February 1970, the United States entered into a contract for the construction of the museum with Piracci Construction Company (“Piracci”).

Pursuant to the construction contract, Piracci was required to prepare a scale model of the museum’s “Core No. 1 support from Plaza Level to and including Second Floor framing, complete with ring girders, and one typical axial rib each side; to extent shown on drawings.” Piracci submitted this model to GSA in August 1970, and Skidmore reviewed it. The complaint alleges that GSA rejected the model as not acceptable upon Skidmore’s representation that it was inaccurate and out of scale. Piracci submitted a second model, which was accepted, in April 1971.

The complaint further alleges that Skid-more, contrary to its contractual obligation, refused to approve shop drawings for the column supports until the second model was approved, despite its knowledge that such drawings were not required by the subcontractor which was fabricating the columns; *1103 and that it persisted in such refusal although it knew the subcontractor would not proceed without such approval and its refusal would delay the fabrication of the form and delay construction of the museum as a whole. As a result, according to the Government, the formwork was not delivered until June 1971, six months behind schedule, causing both the Government and Piracci to incur substantial additional costs.

In addition to the above allegations in the complaint, other facts are set forth in the affidavit of Walter Huber, the Contracting Officer in charge of the GSA-Piracci construction contract.

On November 29, 1970, Piracci notified the GSA that its performance of work under the construction contract had been unreasonably delayed “because of the failure of the government and its architect to furnish [it] with the design information and related calculations required to produce the shop drawings for steel form fabrication for the main support columns and to fabricate a scale model as specified,” and that it intended to submit a claim for the increased cost resulting from the delay. Thereafter Piracci submitted the second model which, based upon the architect’s approval, was accepted by GSA in April 1971.

On May 12, 1971, Piracci filed a detailed statement for its additional costs claimed to have been incurred as a result of changes ordered and of delays occasioned by the rejection of the first model. On August 25, 1971 the Contracting Officer rejected Piracci’s claim, upon the ground that any delays were the result of Piracci’s failure to execute the work as required. Piracci appealed this decision to the General Services Board of Contract Appeals (“Board”) and also filed an additional claim with the Contracting Officer on February 18, 1972. The Board reversed the decision of the Contracting Officer on May 30, 1974 and found that GSA wrongfully rejected the model and delayed approval of the shop drawings, and that Piracci had thus sustained compensable additional costs as a result thereof. The Board’s opinion contained language critical of Skidmore’s basis for recommending to GSA rejection of the first model, but made no finding that Skidmore was negligent since it was not a party to the administrative appeal. In sum, the Board rejected GSA’s contention that the first model failed to meet specification requirements.

GSA and Piracci effected a settlement in the amount of $1,043,393 on September 30, 1977, three-and-a-half years after the Board’s decision; a stipulation of settlement was filed in the Court of Claims on May 12, 1978, 1 and payment was made by August 3, 1978 to Piracci which executed a general release in favor of the Government. The GSA notified Skidmore on August 12, 1977 that it would assess damages against it based on Skidmore’s professional negligence regarding the scale-model issue; on December 19, 1977, GSA informed Skidmore that the damages amounted to $1,043,393, the amount paid to Piracci. Skidmore denied responsibility and notified GSA of its refusal to make any payment. The Government commenced this action on May 29, 1980.

The rather inartistically and repetitively worded complaint states four causes of action. The first alleges that Skidmore’s rejection of the first model, its insistence on a submission of a second model, and its refusal to consider the drawings until the model was approved were both unjustified and constituted breach of contract. The second alleges that these actions constituted negligence by Skidmore in the performance of its professional services in breach of Article XVI(B) of the contract, which provides in pertinent part:

the Professional Services Contractor [Skidmore] shall be and remain liable to the Government for all costs of any kind which were incurred by the Government as a result of [Skidmore’s] negligent performance of any of the services furnished under this contract.

*1104 The third alleges that Skidmore breached its agreement to indemnify the Government as provided by Article XVI(B) of the contract. Finally, the fourth alleges that Skid-more failed to provide all necessary information for the model maker to fabricate a scale model to the degree of accuracy insisted upon by Skidmore and that such failure constituted a breach of its warranties and undertakings under the contract and delayed the construction of the museum. The Government seeks the same damages— $1,043,393 paid to Piracci pursuant to the settlement — on each cause of action.

However variously stated and fragmentized under allegations of negligence, breach of contract and breach of warranty, the Government, under its four separately pleaded causes of action, essentially seeks indemnification of the $1,043,393 paid to Piracci.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M.E.S., Inc. v. United States
104 Fed. Cl. 620 (Federal Claims, 2012)
Gail Frances, Inc. v. Alaska Diesel Electric, Inc.
62 F. Supp. 2d 511 (D. Rhode Island, 1999)
Atlantic Richfield Co. v. Lujan
811 F. Supp. 1520 (N.D. Oklahoma, 1992)
United States v. Government Development Bank
725 F. Supp. 96 (D. Puerto Rico, 1989)
Federal Sav. and Loan Ins. Corp. v. Burdette
696 F. Supp. 1196 (E.D. Tennessee, 1988)
Marathon Enterprises, Inc. v. Feinberg
595 F. Supp. 368 (S.D. New York, 1984)
United States v. Lincoln Engineers, Inc.
586 F. Supp. 684 (D. Rhode Island, 1984)
Zenobi v. Exxon Co., USA
577 F. Supp. 514 (D. Connecticut, 1983)
United States v. Whitesell
563 F. Supp. 1355 (D. South Dakota, 1983)
United States v. McFerran
568 F. Supp. 804 (S.D. Texas, 1983)
Sven Salen AB v. Jacq. Pierot, Jr., & Sons, Inc.
559 F. Supp. 503 (S.D. New York, 1983)
United States v. Gonzales
541 F. Supp. 783 (D. Kansas, 1982)
United States v. Glens Falls Insurance
546 F. Supp. 643 (N.D. New York, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
505 F. Supp. 1101, 28 Cont. Cas. Fed. 81,272, 1981 U.S. Dist. LEXIS 9394, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-skidmore-owings-merrill-nysd-1981.