United States v. Lincoln Engineers, Inc.

586 F. Supp. 684, 1984 U.S. Dist. LEXIS 16819
CourtDistrict Court, D. Rhode Island
DecidedMay 10, 1984
DocketCiv. A. No. 830104 S
StatusPublished

This text of 586 F. Supp. 684 (United States v. Lincoln Engineers, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Lincoln Engineers, Inc., 586 F. Supp. 684, 1984 U.S. Dist. LEXIS 16819 (D.R.I. 1984).

Opinion

OPINION AND ORDER

SELYA, District Judge.

The United States brought this contract action to recapture unliquidated progress payments and inventory recovery costs from the defendant Lincoln Engineers, Inc. (Lincoln). Suit was filed on February 4, 1983. Lincoln answered, then moved for judgment on the pleadings, Fed.R.Civ.P. 12(c). In July of 1983, while that motion was pending, the First Circuit rendered its decision in United States v. Hughes House Nursing Home, 710 F.2d 891 (1st Cir.1983). This court promptly denied Lincoln’s motion without prejudice, subject to renewal as a motion for summary judgment under Fed.R.Civ.P. 56, and instructed the parties to develop the factual record to address questions arguably raised by Hughes House.

Over the succeeding months, that directive has been honored. An agreed statement of facts has been filed, along with cross motions for summary judgment. At a hearing held on April 18, 1984, the parties agreed to submit the cause on the record (in lieu of trial) for decision by the court on the merits. In addition to the pleadings, the statement of facts, and the cross motions, the record comprises, by agreement, all of the material proffered in connection with the motions for brevis disposition, including the relevant contract clauses and correspondence between the parties, as well as the decision of the Armed Services Board of Contract Appeals (Board) anent Lincoln’s administrative appeal. In that appeal, the Board on July 11, 1978 upheld the government’s termination of the contract on the ground of default and sustained the government’s counterclaim for recovery against Lincoln.

The matter has been briefed, and oral arguments have been waived. This re-script, therefore, constitutes the court’s findings of fact and conclusions of law required by Fed.R.Civ.P. 52(a).

I.

On April 21, 1972, the Department of the Army awarded Lincoln a fixed price contract to manufacture one hundred fifty-five missile mounting kits for delivery during the period April, 1973 through May, 1974. By modification thereto, the government, on October 30, 1973, exercised its option to procure from Lincoln an additional thirty-six mounting kits at roughly the same price. The stipulated consideration for these items, in the aggregate, exceeded half a million dollars.

Three clauses of the contract are at issue here.1 The default clause, which allowed [686]*686the United States to terminate the contract by written notice of default, required Lincoln, upon the government’s exercise of this prerogative, to transfer to the Army all inventory and materials produced or acquired in the course of performance of the contract. The progress payments clause entitled Lincoln to periodic step payments, but only up to eighty percent of costs reasonably incurred under the contract as determined in accordance with “sound and generally accepted accounting principles and practices.” If at any time unliquidated progress payments exceeded a specific amount, the government was entitled to a refund on demand. And, in the event of termination for default, the government had a right to be paid all unliquidated progress payments, likewise on demand. Finally, the disputes clause required that controversies arising under the contract, and not consensually resolved, be decided by a contracting officer. There was reserved a further right of appeal to, in this case, the Board.

Although the Army granted several extensions of time for performance, the defendant was unable to meet the contract delivery schedules. By letter dated April 6, 1976, the government demanded that Lincoln show cause why the contract should not be terminated pursuant to the default clause. No meaningful response ensued. In the absence of a satisfactory showing, the Army, by letter dated May 12, 1976, invoked the default clause and terminated the contract due to Lincoln’s failure to effect timely delivery. On or about June 1, 1976, the defendant protested the government’s action to the Board.

While the appeal to the Board was pending, the United States, under date of June 10, 1976, ordered that Lincoln relinquish to it all inventory attributable to the contract and purchased by use of the progress payments. Lincoln complied within the month. Therefore, by the end of June, 1976, the government had in its possession all of the information necessary to calculate the amount forthcoming as a consequence of the termination. But, true to the most exasperating of bureaucratic traditions, the Army proceeded at a leisurely pace. Not until March 30, 1977 did the government arrive at the conclusion that it was owed $47,127.21 in unliquidated progress payments and $3,699.00 in inventory recovery costs. And, on June 13, 1977, the government filed its counterclaim for those amounts with the Board. The Board, as noted previously, found in favor of the Army both on Lincoln’s appeal and on the counterclaim.

The parties concur that the controlling statute of limitations is that set out in 28 U.S.C. § 2415(a). There is, likewise, general agreement that the decision of the Board is a “final decision ... rendered in applicable administrative proceedings required by contract or by law” for purposes of the aforementioned statute. Id. And, both parties are bound by the Board’s findings of fact. The sole issue before the court relates to the government’s claim for recompense. Lincoln does not now protest the Board’s determination that the Army properly abrogated the contract; nor does it challenge the government’s claim that the disputes clause of the contract precludes judicial review of the Board’s decision beyond the substantial evidence test. See, e.g., Silverman Brothers v. United States, 324 F.2d 287, 288-90 (1st Cir.1963). Indeed, Lincoln foreclosed the possibility of de novo review of the Board’s decision by agreeing to be bound by the Board’s findings of fact.

The plaintiff commenced this action more than six years after the government terminated the contract for default; more than six years after the government demanded disgorgement of the inventory; and more than one year — indeed more than four years — after the Board rendered its final decision. The defendant urges that the suit is, therefore, stale and time barred. The government, while forced to concede that the action is a trifle moldy, asseverates that it is sufficiently fresh to withstand a limitations defense.

II.

Lincoln’s resistance rests on one simple contention: the government’s action is [687]*687barred by 28 U.S.C. § 2415(a). That statute, in relevant part, requires the government to sue on a contract claim “within six years after the right of action accrues or within one year after final decisions have been rendered in applicable administrative proceedings required by contract or by law, whichever is later.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Green v. Biddle
21 U.S. 1 (Supreme Court, 1823)
Crown Coat Front Co. v. United States
386 U.S. 503 (Supreme Court, 1967)
Silverman Brothers, Inc. v. United States
324 F.2d 287 (First Circuit, 1963)
United States v. Hughes House Nursing Home, Inc.
710 F.2d 891 (First Circuit, 1983)
Irving M. Levin, Etc. v. David R. Berley
728 F.2d 551 (First Circuit, 1984)
Fischer v. McGowan
585 F. Supp. 978 (D. Rhode Island, 1984)
United States v. D. H. Dave, Inc.
424 F. Supp. 424 (D. Maryland, 1976)
United States v. Birmingham Fire Insurance Co. of Pennsylvania
370 F. Supp. 501 (W.D. Pennsylvania, 1974)
United States v. Skidmore, Owings & Merrill
505 F. Supp. 1101 (S.D. New York, 1981)
City of New Bedford v. Lloyd Investment Associates, Inc.
292 N.E.2d 688 (Massachusetts Supreme Judicial Court, 1973)
Olsen v. BELL TELEPHONE LABORATORIES, W. ELECTRIC CO.
445 N.E.2d 609 (Massachusetts Supreme Judicial Court, 1983)
Jonklaas v. Silverman
370 A.2d 1277 (Supreme Court of Rhode Island, 1977)
United States v. Cardinal
452 F. Supp. 542 (D. Vermont, 1978)
United States v. General Electronics, Inc.
556 F. Supp. 801 (D. New Jersey, 1983)
Baddock v. American Benefit Life Insurance
431 U.S. 904 (Supreme Court, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
586 F. Supp. 684, 1984 U.S. Dist. LEXIS 16819, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-lincoln-engineers-inc-rid-1984.