United States v. D. H. Dave, Inc.

424 F. Supp. 424, 23 Cont. Cas. Fed. 81,283, 1976 U.S. Dist. LEXIS 11638
CourtDistrict Court, D. Maryland
DecidedDecember 28, 1976
DocketCiv. K-75-1805
StatusPublished
Cited by3 cases

This text of 424 F. Supp. 424 (United States v. D. H. Dave, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. D. H. Dave, Inc., 424 F. Supp. 424, 23 Cont. Cas. Fed. 81,283, 1976 U.S. Dist. LEXIS 11638 (D. Md. 1976).

Opinion

FRANK A. KAUFMAN, District Judge.

On June 30, 1952, the United States entered into a contract with defendants D. H. Dave, Inc. and Gerben Contracting Company (hereinafter “contractors”) for the construction by contractors of school shop buildings, roads, and utilities at the United States Army installation in Aberdeen, Maryland. Contractors purchased a performance bond naming defendant Fidelity and Casualty Company of New York (hereinafter “Fidelity”) as surety. That bond is still in effect. On April 3, 1954, the United States, asserting default by contractors because of failure timely to complete performance as required by the contract, terminated the contract. Thereafter, the work was assigned by the Government to another contractor who completed it on February 8, 1955. Under the terms of the June 30,1952 contract including the standard disputes clause set forth therein, 1 defendants are *426 liable to the Government for any excess costs incurred as a result of any default by contractors. The federal contracting officer determined that contractors were in default as of April 3, 1954 and that contractors would be required to pay to the Government certain excess costs.

After an extended series of administrative appeals and remands, which culminated in a decision by the Armed Services Board of Contract Appeals entered on June 7, 1973, finding contractors liable to the United States in the net amount of $16,-739.47, the Government made demand upon Fidelity on November 7, 1974 for payment in full of $16,739.47. That demand has not been met. On December 12, 1975, more than two years after the final administrative action was completed on June 7, 1973, the Government instituted this collection case. All defendants have moved to dismiss, on the grounds that the within action is barred by limitations. 2 In so doing, defendants rely upon 28 U.S.C. § 2415(a), which provides, in part:

[E]very action for money damages brought by the United States or an officer or agency thereof which is founded upon any contract express or implied in law or fact, shall be barred unless the complaint is filed within six years after the right of action accrues or within one year after final decisions have been rendered in applicable administrative proceedings required by contract or by law, whichever is later * * *. [Emphases added.]

The Government argues that the right of action accrues on the date of the final administrative action. Defendants contend that it accrues at the time of the breach of the contract, that is, in this case, on April 3, 1954. However, in this case, the earliest legally effective date upon which the accrual could have occurred is July 18, 1966, the date upon which the statute, of which 28 U.S.C. § 2415(a) is part, was enacted. See 28 U.S.C. § 2415(g) which provides:

Any right of action subject to the provisions of this section which accrued prior to the date of enactment of this Act shall, for purposes of this section, be deemed to have accrued on the date of enactment of this Act.

In United States v. Birmingham Fire Ins. Co., 370 F.Supp. 501 (W.D.Pa.1974), Judge Teitelbaum held that the right of action accrued, under section 2415(a), upon the final administrative determination. In so doing, he relied upon Crown Coat Front Co. v. United States, 386 U.S 503, 87 S.Ct. 1177, 18 L.Ed.2d 256 (1967). That case did not involve section 2415(a). Rather it was concerned with the construction of 28 U.S.C. § 2401(a), which provides:

Every civil action commenced against the United States shall be barred unless the complaint is filed within six years after the right of action first accrues. The action of any person under legal disability or beyond the seas at the time the claim accrues may be commenced within three years after the disability ceases.

In Crown Coat, the contractor, after unsuccessfully pursuing and exhausting its rights under the standard dispute clause in its contract with the Government, 3 brought suit in federal district court claiming entitlement to an equitable adjustment. That suit was instituted more than six years after the contractor had completed performance of the contract, but a bit more than five months (and well within a year) after final government administrative action adverse to the contractor, pursuant to the standard disputes clause. The Government contended that the “right of action first accrue[d]” when the Government failed to meet its obligations with respect to the contract — a date concededly more than six *427 years before the commencement date of the federal district court case. In rejecting the Government’s argument, Mr. Justice White wrote (at 519-22, 87 S.Ct. at 1186):

Finally, the Government relies on Public Law 89-505, 80 Stat. 304, 28 U.S.C. § 2415 (1964 ed., Supp. II), enacted on July 18, 1966, which for the first time established a general statute of limitations on government tort claims and on suits by the Government for money damages founded on any contract, express or implied. Such suits must now be brought within “six years after the right of action accrues or within one year after final decisions have been rendered in applicable administrative proceedings required by contract or by law.” As an example of such administrative proceedings, the relevant committee reports and hearings mentioned the administrative proceedings required under the standard disputes clause contained in government contracts. H.R.Rep.No.1534, 89th Cong., 2d Sess., at 4; S.Rep.No.1328, 89th Cong., 2d Sess., at 3; Hearing on H.R. 13652 before Subcommittee No. 2 of the House Committee on the Judiciary, 89th Cong., 2d Sess., 7 (1966). Based on this new provision, the Government argues that Congress necessarily assumed that the right of action of the United States in disputes clause situations first accrues and the limitations period begins to run prior to the completion of administrative proceedings. Otherwise there would have been no need for the one-year period following final administrative decision in order to save actions which might otherwise be barred by the six-year limitation. What this amounts to, the Government says, is a congressional construction of the similar “first accrual” language of the older limitations on private actions contained in § 2401(a) and § 2501. Likewise, it argues, this construction precludes holdings such as that of the Third Circuit in Northern Metal Co. v. United States, 3 Cir., 350 F.2d 833, to the effect that the statute is tolled during the pendency of administrative proceedings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Lincoln Engineers, Inc.
586 F. Supp. 684 (D. Rhode Island, 1984)
United States v. General Electronics, Inc.
556 F. Supp. 801 (D. New Jersey, 1983)
United States v. Skidmore, Owings & Merrill
505 F. Supp. 1101 (S.D. New York, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
424 F. Supp. 424, 23 Cont. Cas. Fed. 81,283, 1976 U.S. Dist. LEXIS 11638, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-d-h-dave-inc-mdd-1976.