Atlantic Richfield Co. v. Lujan

811 F. Supp. 1520, 1992 U.S. Dist. LEXIS 21759, 1992 WL 415419
CourtDistrict Court, N.D. Oklahoma
DecidedDecember 22, 1992
Docket89-C-892-B
StatusPublished
Cited by2 cases

This text of 811 F. Supp. 1520 (Atlantic Richfield Co. v. Lujan) is published on Counsel Stack Legal Research, covering District Court, N.D. Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atlantic Richfield Co. v. Lujan, 811 F. Supp. 1520, 1992 U.S. Dist. LEXIS 21759, 1992 WL 415419 (N.D. Okla. 1992).

Opinion

ORDER

BRETT, District Judge.

This matter comes on for consideration of Plaintiffs Motion for Summary Judgment and Defendants’ Cross-Motion for Summary Judgment. These motions were originally filed January 21, 1992, 1 along with supporting memorandums that addressed a plethora of issues. Reply memorandums were filed April 6, 1992, by both parties. The Court heard oral arguments on the pending motions on June 19, 1992. At that hearing, the Court determined that it should first address the statute of limitations issue, in order to allow the parties to file an interlocutory appeal along with Phillips Petroleum Co. v. Lujan, No. 89-C-914-B (N.D.Okla. October 28, 1991), if they desired.

The Court provided the parties with another opportunity to specifically address the statute of limitations issue. The parties were given until July 6 to file an agreed statement of facts 2 , with briefs due July 16 and responses due July 27. The parties failed to submit an agreed statement of facts. Instead, the Defendants submitted their own statement of facts 3 , which the Plaintiff moved to strike. 4 The briefs and responses were timely filed. Due to the parties inability to agree on a statement of facts, the Plaintiff’s Motion to Strike the Defendants’ Statement of Facts will be granted. The Court will address the statute of limitations question based on the uncontroverted facts appearing in the remaining record that are relevant to this issue.

I. Background

Plaintiff, Atlantic Richfield Company (“ARCO”), is the lessee of an Indian lease which produces natural gas upon which ARCO pays a royalty. The Defendants, Secretary of the Department of Interior Manuel Lujan, Director of the Minerals Management Service (“MMS”) Barry Williamson and Area Manager of the MMS Dallas Area compliance office Nick Kelly, are sued by ARCO as a result of an Administrative Order (the “Order”) issued by the Defendants, 5 dated September 25, 1989.

This Order 6 notified ARCO that it had deducted an incorrect manufacturing allow *1522 anee 7 from past royalty payments on the audited lease. Based on this information, the MMS concluded that a systemic failure existed in ARCO’s royalty calculation method. Thus, it ordered ARCO to recalculate royalties on gas produced from all its Indian and Federal onshore oil and gas leases using a cost-based manufacturing allowance for the period October 1, 1980, through February 29, 1988, and pay any resulting deficiencies.

II. Statute of Limitations

ARCO filed this action October 24, 1989, seeking judicial review of the Defendants’ Order. 8 ARCO argues that the Order is barred in part by the statute of limitations, which provides:

Subject to the provisions of section 2416 of this title, and except as otherwise provided by Congress, every action for money damages brought by the United States or an officer or agency thereof which is founded upon any contract express or implied in law or fact, shall be barred unless the complaint is filed within six years after the right of action accrues or within one year after final decisions have been rendered in applicable administrative proceedings required by contract or by law, whichever is later____ (emphasis added).

28 U.S.C. § 2415(a).

ARCO reasons that the portion of the MMS Order that requires the payment of additional royalties for the period October 1980, through September 25, 1983, should be vacated as untimely (Supplemental Memorandum of Atlantic Richfield Company Addressing the Statute of Limitations, p. 1) (hereinafter “Plaintiff’s Brief”). ARCO argues that § 2415 bars these claims because the royalty payments were due more than six years before the MMS order was issued. 9

According to ARCO, there are only two material facts relating to the statute of limitations issue and they are both undisputed (Plaintiff’s Brief, p. 3). The first fact is the date on which the royalties were due, October 1980 through September 25, 1983. The second fact is the date the MMS Order was issued, September 25, 1989. ARCO contends these two facts provide sufficient grounds for granting summary judgment as to the pre-September 25, 1983, claims (“disputed claims”) 10 .

III. Accrual of Claim

The Defendants assert two basis for finding that the disputed claims are not time-barred. First, Defendants argue that their claim for royalties did not accrue, and thus the statute of limitations did not begin running, until after the audit was completed (Defendants’ Supplemental Brief on the Statute of Limitations, p. 24) (hereinafter “Defendants’ Brief”).

The Defendants direct the Court’s attention to Medicare Part A payment cases. Under the Medicare Part A program, a provider of services receives payment in the form of interim reimbursements from organizations which serve as fiscal intermediaries between the government agency and the provider. The interim payments are determined on the basis of estimated costs for a given accounting period. The provider later submits reports of the actual costs incurred. The fiscal intermediary must then audit the reports and compare estimated payments to the amounts *1523 due on the basis of actual costs, with a final adjustment made based on the audit results. If the provider has been overpaid, the Government has a claim for reimbursement (Defendants’ Brief, p. 25).

Some courts have concluded that in such Medicare Part A cases, the statute of limitations did not begin to run until “the rights and liabilities of the parties were determined in the audit.” United States v. Withrow, 593 F.2d 802, 805 (7th Cir.1979); United States v. Gravette Manor Homes, 642 F.2d 231 (8th Cir.1981). The Defendants contend the same approach should be used in royalty payment cases by arguing that the correct amount owed to the Government is unknown in both cases until an audit is completed.

This Court addressed this same argument in Phillips Petroleum Co. v. Lujan, No. 89-C-914-B, (N.D.Okla. Oct. 24, 1991) (“Phillips III”), and rejected the analogy to Medicare cases.

Cases interpreting payments made under Part A of the Medicare Act relate to estimated payments made to medical providers without delay.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Exxon Mobil Corp. v. ALA. DEPT. OF CONSERVATION AND NATURAL RESOURCES
986 So. 2d 1093 (Supreme Court of Alabama, 2007)
Weatherly v. Universal Music Publishing Group
23 Cal. Rptr. 3d 157 (California Court of Appeal, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
811 F. Supp. 1520, 1992 U.S. Dist. LEXIS 21759, 1992 WL 415419, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atlantic-richfield-co-v-lujan-oknd-1992.