United States v. Newport News Shipbuilding, Inc.

276 F. Supp. 2d 539, 2003 U.S. Dist. LEXIS 14149, 2003 WL 21955886
CourtDistrict Court, E.D. Virginia
DecidedAugust 14, 2003
DocketCIV.A. 03-142-A
StatusPublished
Cited by13 cases

This text of 276 F. Supp. 2d 539 (United States v. Newport News Shipbuilding, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Newport News Shipbuilding, Inc., 276 F. Supp. 2d 539, 2003 U.S. Dist. LEXIS 14149, 2003 WL 21955886 (E.D. Va. 2003).

Opinion

MEMORANDUM OPINION

ELLIS, District Judge.

At issue on summary judgment in this False Claims Act (FCA) case 1 is whether Newport News Shipbuilding, Inc. (NNS) violated the Federal Acquisition Regulation (FAR) by misclassifying as Independent Research and Development (IR & D) approximately $74 million that was allegedly spent in connection "with the design and construction of double-hulled tankers for commercial customers. Resolution of this question requires the interpretation and application of a long-questioned aspect of the FAR’s definition of IR & D, specifically the exclusion from IR & D of efforts “required in the performance of a contract.” 48 C.F.R. § 31.205-18(a).

Also at issue on summary judgment is whether the FCA claims must be dismissed on the ground that the undisputed evidence establishes that NNS did not “knowingly” submit false claims, as required by the FCA. 31 U.S.C. § 3729(a).

Following an initial hearing on these motions on Friday, July 18, 2003, supplemental briefing was requested and the hearing continued on Monday, July 21, 2003, at which time the motions were decided from the bench and an order issued. 2 This memorandum opinion elucidates the bases for those bench rulings.

*542 I.

Defendant NNS is a major defense contractor whose chief business is the design, construction, repair, overhaul and re-fueling of nuclear-powered aircraft carriers and submarines for the United States Navy. During the time period relevant to this action, most of NNS’s yearly revenues, between 85% and 99%, came from its contracts with the Navy. Most the contracts are flexibly-priced contracts, under which NNS charges the government on an ongoing basis based on its reasonable, allo-cable, and allowable costs, as determined according to the FAR 48 C.F.R. §§ 1.000 et seq. These costs include (i) direct costs that are directly identified with and charged to a specific contract, such as material and labor costs, and (ii) indirect costs that are allocable to more than one contract, including overhead and general administrative costs, which must be allocated to the various applicable contracts. IR & D costs, the subject of this dispute, are indirect costs.

For the period between 1994 and 1999, NNS submitted invoices for progress payments on a bi-weekly or monthly basis. At the end of each year, NNS submitted a final indirect cost proposal, which certified that the submitted indirect costs were allowable in accordance with the FAR. The central question at issue here is whether NNS’s claims for progress payments and year-end certifications submitted from 1994 and 1999 were false, because they contained IR & D charges for efforts related to NNS’s Double Eagle commercial tanker program that were not allowable as IR & D under the FAR.

Although both parties agree on some of the essential facts in this dispute, and although there is a voluminous factual record accompanying the summary judgment motions, there remain disputed factual issues material to certain aspects of the case. As the following summary indicates, substantial factual questions remain regarding such central facts as (i) the nature and intent of NNS’s Double Eagle class design efforts, (ii) the content of the advice NNS received regarding the regulation and its charging practices, (iii) whether NNS followed that advice, and (iv) when and to what extent NNS disclosed its IR & D charging practices regarding the Double Eagle IR & D to the government.

A. NNS’s Double Eagle tanker program

The genesis of this dispute is NNS’s ultimately unsuccessful attempt to re-enter the commercial shipbuilding market. Although it had earlier withdrawn from the commercial shipbuilding market, NNS, in the early 1990’s, decided to return to commercial shipbuilding, specifically to build double hulled oil tankers to be known as Double Eagle tankers. NNS asserts that this decision to design, market, and sell the Double Eagle tankers was part of a larger effort undertaken by NNS to transform itself into a world-class shipbuilder capable of competing with shipbuilding yards in Asia and Europe. NNS argues that the intent, from the outset, was to invest significantly to create a “class design” for the Double Eagle tankers and to transform its shipbuilding operations to become more competitive and efficient. Thus, NNS paints a picture of a tanker class design effort that was independent from the efforts undertaken to fulfill the specific Double Eagle contracts, which contracts materialized after the commencement of the class design effort.

The government’s view is quite different; it disputes the existence of a truly independent class design effort, contending that NNS simply created “contract-level” plans for a “proposed class” of ships which it intended to market to potential customers, and that it chose to pursue a class design in order to shift design costs *543 from money-losing commercial contracts into general IR & D chargeable to government contracts. Thus, the government does not agree that NNS worked to develop a generic class design separate and independent from the specific commercial contracts received by NNS to build the Double Eagle tankers.

By March 1994, NNS had completed some market research and preliminary design work on the Double Eagle tanker, and, at that time, began to seek funding for the project and to market the new tankers to potential customers. On March 15, NNS issued a press release publicly announcing its Double Eagle tanker program. On March 18, 1994, NNS submitted a proposal for funding under the United States Advanced Research Projects Agency (ARPA)’s Maritech Program, setting out its plan to enter the commercial shipbuilding market with the a “42,000 dwt product tanker” as the “initial target market ship,” and stating that “NNS has already developed a concept design for such a ship, the Double Eagle 338.” And, on March 21 and 22, 1994, NNS presented a model of the Double Eagle tanker at an industry trade show, and quickly thereafter became involved in discussions with various potential commercial customers for its new tankers.

Beginning on January 4, 1993, NNS charged the costs of its preliminary design efforts for what became the Double Eagle tanker project to various IR & D accounts. On May 12, 1994 NNS issued IR & D Job Order 2858, the first IR & D job order to contain charges disputed in this matter. Job Order 2858, entitled “Develop Product Carrier Design Process,” was intended to capture the costs of NNS’s efforts to “complete the preliminary design of the Newport News Standard Products Carrier and to establish the process for transferring from preliminary design to detail design.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Ex Rel. Drakeford v. Tuomey
792 F.3d 364 (Fourth Circuit, 2015)
Abusamhadaneh v. Taylor
873 F. Supp. 2d 682 (E.D. Virginia, 2012)
United States Ex Rel. Westmoreland v. Amgen, Inc.
812 F. Supp. 2d 39 (D. Massachusetts, 2011)
ATK Thiokol, Inc. v. United States
598 F.3d 1329 (Federal Circuit, 2010)
Massachusetts v. Mylan Laboratories
608 F. Supp. 2d 127 (D. Massachusetts, 2008)
United States Ex Rel. Burlbaw v. Orenduff
548 F.3d 931 (Tenth Circuit, 2008)
United States v. Degayner
622 F. Supp. 2d 1258 (M.D. Florida, 2008)
ATK Thiokol, Inc. v. United States
68 Fed. Cl. 612 (Federal Claims, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
276 F. Supp. 2d 539, 2003 U.S. Dist. LEXIS 14149, 2003 WL 21955886, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-newport-news-shipbuilding-inc-vaed-2003.