The Boeing Company v. The United States

862 F.2d 290, 1988 WL 125852
CourtCourt of Appeals for the Federal Circuit
DecidedFebruary 24, 1989
DocketAppeal 88-1298
StatusPublished
Cited by10 cases

This text of 862 F.2d 290 (The Boeing Company v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Boeing Company v. The United States, 862 F.2d 290, 1988 WL 125852 (Fed. Cir. 1989).

Opinion

BISSELL, Circuit Judge.

The Boeing Company (Boeing) appeals the decision of the Armed Services Board of Contract Appeals (Board), Boeing Co.— Boeing Military Airplane Div., ASBCA No. 29793, 88-1 BCA ¶ 20,380 (1987) [available on WESTLAW, 1987 WL 46116], holding that all of Boeing’s bid and proposal (B & P) costs incurred to enhance its ability to receive a Phase 2 contract must be recorded as direct costs of the Phase 1 contract, Contract No. F33657-77-C-0175, under the consistency requirements of General Accounting Office Cost Accounting Standard (CAS) 402, 4 C.F.R. §§ 402.10-.80 (1988). Because the Board erred in interpreting CAS 402, we reverse.

BACKGROUND

In April 1976, the Air Force issued a request for proposals (RFP) specifically soliciting two proposals for the competitive design, production and demonstration of a B-52G and a KC-135 weapon systems trainer. The winner of a Phase 1 initial production contract competition would receive the Phase 2 contract for the balance of the equipment.

The RFP, at Line Item 0010 of the proposed contract, required each offeror to prepare a proposal for the Phase 2 contract and to specify a target cost for the proposal preparation. The RFP further provided that (1) the contents of the Phase 2 proposal would be specified at a later date, (2) the proposal instruction package (PIP) would be issued 23 months after award of the Phase 1 contract, and (3) the proposal would be due 2 months later. In October 1976, Boeing submitted its bid for the Phase 1 contract, including a target cost of $1,010,380 for the Phase 2 proposal effort.

Shortly thereafter, Boeing described its interpretation of CAS 402’s Interpretation No. 1, 4 C.F.R. Part 402, Appendix (1988) (Interpretation No. 1), in an internal memorandum to its contracts directors and finance directors. Consistent with the foregoing memorandum, Boeing issued an internal directive specifying that all Phase 2 proposal preparation costs incurred during the two months between receipt of the PIP and submission of the proposal were to be allocated as direct costs of the Phase 1 contract, and all other costs for proposal activity generated to obtain the Phase 2 contract — those incurred prior to receipt of the PIP or after submission of the proposal —were to be allocated to Boeing’s indirect B & P cost account.

In January 1977, Boeing submitted its best and final offer for the Phase 1 contract. The offer set forth a price of $486,-310 for Line Item 0010 — the Phase 2 proposal activity — and stated that this price covered only the costs incurred in preparing the Phase 2 proposal. In April 1977, the Air Force awarded one of the Phase 1 contracts to Boeing and the other to Singer Company.

On April 20, 1979, the Air Force issued a PIP for only the B-52 trainer and cancelled the procurement of the KC-135 trainer. Although Boeing made a best and final offer for the Phase 2 production contract, the Air Force awarded the Phase 2 contract to Singer Company in May 1980.

From 1974 through 1979, Boeing had performed several independent research and development (IR & D) and B & P projects to enhance its capability to design and produce the weapon systems trainers and simulators for the B-52, KC-135 and other military aircraft. In accordance with defense contracting regulations, Boeing regularly reported its costs in these endeavors to the Department of Defense Tri-Service Office, the office responsible for negotiating ceilings on indirect cost allowances for IR & D/B & P projects undertaken by defense contractors. Boeing allocated all B & P costs incurred in performing the weapon systems trainer B & P efforts to its indirect IR & D/B & P cost accounts except for those costs incurred between receipt of the Phase 2 PIP and submission of the Phase 2 proposal. These latter costs, amounting to $444,235, were allocated directly to the Phase 1 contract.

The contracting officer in his final decision directed Boeing to adjust its accounts *292 to remove all B & P costs recorded as indirect costs for the years 1977 through 1980 and record these costs as direct costs of the Phase 1 contract. The issue of direct or indirect cost allocation for all years except 1979 was resolved during negotiation of final overhead rates.

Before the Board, the parties agreed that Boeing had properly allocated directly to the Phase 1 contract the costs incurred in actually preparing the Phase 2 proposal, i.e., the costs incurred between Phase 2 PIP receipt and Phase 2 proposal submission. Thus, the only remaining dispute was whether CAS 402 allowed Boeing to treat all other 1979 B & P costs related to the weapon systems trainers as indirect costs. The Board resolved the dispute adversely to Boeing.

ISSUE

Whether the Board erred in interpreting CAS 402 to require Boeing to allocate all B & P costs incurred to enhance its ability to receive the Phase 2 contract as direct costs of the Phase 1 contract.

OPINION

CAS 402, promulgated by the Cost Accounting Standards Board (CASB) pursuant to the Defense Production Act Amendments of 1970, Pub.L. 91-379, 84 Stat. 796 (1970), enjoys the “full force and effect of law.” 50 U.S.C.App. § 21680(A) (1982). CAS 402 requires in pertinent part that

[a]ll costs incurred for the same purpose, in like circumstances, are either direct costs only or indirect costs only with respect to final cost objectives.

4 C.F.R. § 402.40.

The CASB published an interpretation of Interpretation No. 1 because a number of questions had been raised as to 'how the standard was to be applied to account for B & P costs and, particularly, as to whether all costs incurred in preparing proposals are incurred for the same purpose, in like circumstances and therefore must all be allocated alike. Preamble C, 4 C.F.R. Part 402 (1988). Interpretation No. 1 “deals with the way Part 402 applies to the treatment of costs incurred in preparing, submitting, and supporting proposals.” Interpretation No. 1.

Under Part 402, costs incurred in preparing, submitting, and supporting proposals pursuant to a specific requirement of an existing contract are considered to have been incurred in different circumstances from the circumstances under which costs are incurred in preparing proposals which do not result from such specific requirement. The circumstances are different because the costs of preparing proposals specifically required by the provisions of an existing contract relate only to that contract while other proposals costs relate to all work of the contractor.
This interpretation does not preclude the allocation, as indirect costs, of costs incurred in preparing all proposals.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ATK Thiokol, Inc. v. United States
598 F.3d 1329 (Federal Circuit, 2010)
AT & T Corp. v. United States
76 Fed. Cl. 297 (Federal Claims, 2007)
ATK Thiokol, Inc. v. United States
68 Fed. Cl. 612 (Federal Claims, 2005)
United States v. Newport News Shipbuilding, Inc.
276 F. Supp. 2d 539 (E.D. Virginia, 2003)
Greenbush School Committee v. Mr. and Mrs. K
949 F. Supp. 934 (D. Maine, 1996)
United States Ex Rel. Mayman v. Martin Marietta Corp.
894 F. Supp. 218 (D. Maryland, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
862 F.2d 290, 1988 WL 125852, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-boeing-company-v-the-united-states-cafc-1989.