United States v. Newport News Shipbuilding and Dry Dock Company, and Tenneco, Inc.

571 F.2d 1283, 24 Cont. Cas. Fed. 82,155, 1978 U.S. App. LEXIS 12419
CourtCourt of Appeals for the Fourth Circuit
DecidedFebruary 27, 1978
Docket77-1748
StatusPublished
Cited by38 cases

This text of 571 F.2d 1283 (United States v. Newport News Shipbuilding and Dry Dock Company, and Tenneco, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Newport News Shipbuilding and Dry Dock Company, and Tenneco, Inc., 571 F.2d 1283, 24 Cont. Cas. Fed. 82,155, 1978 U.S. App. LEXIS 12419 (4th Cir. 1978).

Opinion

BUTZNER, Circuit Judge:

The United States appeals from an order of the district court enforcing an oral settlement purportedly reached between the Department of the Navy and the Newport News Shipbuilding and Drydock Co., and dismissing as moot the government’s suit for specific performance of a contract for construction of a vessel. We vacate this order because we conclude that the parties’ negotiators did not settle the case orally and because the Attorney General, whose approval was essential, rejected the terms that were ultimately reduced to writing.

I

This litigation arises from the Navy’s attempt to exercise an option for construction of the DLGN-41, the fourth ship in a class of nuclear powered guided missile frigates. As part of an agreement to negotiate a number of disputed matters, the final date for exercising this option was extended to February 1, 1975. In the meantime, the Navy authorized the shipyard to start preconstruction work. In August 1974, however, the shipyard notified the Navy that for a variety of reasons it considered the option invalid. The Navy disagreed, and on January 31, 1975, it formally undertook to exercise the option. The parties then signed a memorandum of understanding obligating the shipyard to continue its preconstruction work while they negotiated. In August 1975, the shipyard exercised its right to cancel the memorandum of understanding because it was dissatisfied with the progress of the negotiations.

As a result of the cancellation, the Navy filed this suit seeking specific performance of the contract and a temporary restraining order directing the shipyard to resume work on the vessel. At a hearing on August 29, 1975, the district court adopted as its order a stipulation by the parties providing for continued work on the ship, for continued payment for work performed, and for negotiations “in good faith to reach an agreement as rapidly as possible to modify those contract provisions requiring amendment or to take other appropriate action.”

The shipyard, again dissatisfied with the Navy’s negotiating tactics, filed a motion on July 13, 1976, for enforcement of the court’s order to negotiate in good faith. It also sought to have its obligation to continue work suspended until the Navy complied. The Navy countered by designating as its negotiator Gordon W. Rule, an experienced *1285 civilian official in the procurement office. In view of this development, the shipyard requested the court to reserve ruling on its motion.

Rule began negotiating with the shipyard on July 15, 1976, and subsequently the Navy issued him a contracting officer’s warrant granting him “unlimited authority with respect to negotiations.” On August 20, 1976, the parties reached what Rule and the shipyard’s negotiators considered to be an oral agreement in principle which the Navy later estimated would increase the cost of the ship by about 22.7 million dollars.

The shipyard prepared a written first draft of the oral agreement which Rule received on August 30, 1976. The negotiators then met on several occasions to discuss revisions. A second draft was circulated on September 27, 1976, and further discussions concerning revisions were held. On October 7, 1976, the shipyard executed a third draft of the agreement and sent it to Rule. Although Rule signed the draft as presented by the shipyard, he conditioned his execution of the document by the following provisions set forth in his letter returning it to the shipyard:

(i) That ultimate approval must be received from Deputy Secretary of Defense Clements, and
(ii) That escalation under thi's Mod [i. e., modification of the contract] will be paid by the Government on the basis of the contractor’s actual experience or the BLS Indices times 1.25, whichever is less.

On October 15, 1976, Deputy Secretary Clements forwarded a copy of the compromise to the Attorney General with the recommendation that it be approved. The Attorney General, however, disapproved it on November 24, 1976.

During the negotiations dissension had arisen concerning the scope of Rule’s duties. Rule thought he possessed plenary authority both to negotiate and to bind the government to any agreement he reached. Immediately after his appointment, he told the shipyard that this was the extent of his power. The Navy agreed that Rule possessed unlimited authority to negotiate, but it denied granting him unreviewable authority to bind the government to a settlement. Alerted by a news report that the shipyard considered the law suit to have been settled on August 20, Rule’s superiors explicitly cautioned him several times that any agreement he reached would require approval by higher authorities. The Navy also informed representatives of the shipyard about the necessity for review and approval.

Rule himself appears to have recognized that his authority was not as unrestricted as he first supposed. In a memorandum dated October 5, 1976, he submitted the proposed agreement to the Chief of Naval Material for approval and referred to obtaining “final review and approval” from the Office of General Counsel of the Navy. Finally, the letter addressed to the shipyard accompanying Rule’s executed copy of the agreement expressly conditioned his execution of the document on approval by Deputy Secretary Clements.

Shortly after Rule executed the agreement, and even before the Deputy Secretary transmitted his recommendation to the Attorney General, the shipyard moved the district court to enforce the compromise and dismiss the government’s action for specific performance. In the alternative, it moved to dismiss the action on the ground that the Navy had failed to negotiate in good faith.

The court considered the shipyard’s motion to enforce the settlement without conducting an evidentiary hearing. Relying on affidavits and discovery depositions, it found that Rule had authority to bind the government to the settlement he negotiated; that agreement was reached orally on August 20, 1976, and subsequently memorialized; that Deputy Secretary Clements approved the agreement; and that the Attorney General “is estopped to deny the settlement.”

II

We find no reversible error in the Navy’s complaint that the district court *1286 should have held an evidentiary hearing on the motion to enforce the settlement. When there is no real dispute about the facts, a court has inherent power to enforce summarily a compromise terminating pending litigation. Meetings & Expositions, Inc. v. Tandy Corp., 490 F.2d 714, 717 (2d Cir. 1974). The only conflict of any significance concerned Rule’s duties. We have some doubt that the law and the evidence support the conclusion that the Deputy Secretary vested him with authority to commit the Navy to the expenditure of additional millions of dollars for the construction of the vessel. This issue, however, is not material to our decision. The uncontradicted evidence establishes that by August 25, the Navy had notified the shipyard of the necessity for review and approval of any settlement Rule negotiated. The critical question therefore is whether the August 20 oral agreement was a binding settlement as the shipyard insists and the district court found.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mitchell v. GrainComm II, LLC
E.D. North Carolina, 2025
Elite Entertainment, Inc. v. Khela Bros. Entertainment Inc.
396 F. Supp. 2d 680 (E.D. Virginia, 2005)
Applegate v. United States
52 Fed. Cl. 751 (Federal Claims, 2002)
Andolina Shipping Ltd. v. TBS Eurolines Ltd.
84 F. Supp. 2d 527 (S.D. New York, 2000)
Williams v. Dynatech
Fourth Circuit, 1998
Conley v. Whittlesey
888 P.2d 804 (Idaho Court of Appeals, 1995)
Boeing Co. v. United States
38 Cont. Cas. Fed. 76,332 (Court of Claims, 1992)
Hoskins Lumber Co. v. United States
37 Cont. Cas. Fed. 76,178 (Court of Claims, 1991)
Byrum v. Bear Investment Company
936 F.2d 173 (Fourth Circuit, 1991)
Byrum v. Bear Investment Co.
936 F.2d 173 (Fourth Circuit, 1991)
Fried v. Smith
22 Va. Cir. 181 (Fairfax County Circuit Court, 1990)
Durable Metal Products, Inc. v. United States
36 Cont. Cas. Fed. 75,897 (Court of Claims, 1990)
PBI Electric Corp. v. United States
35 Cont. Cas. Fed. 75,669 (Court of Claims, 1989)
Morrison v. United States Department of Labor
713 F. Supp. 664 (S.D. New York, 1989)
Federal Deposit Insurance v. Jones
846 F.2d 221 (Fourth Circuit, 1988)
Derrickson v. City of Danville
845 F.2d 715 (Seventh Circuit, 1988)
United States v. Jones & Laughlin Steel Corporation
804 F.2d 348 (Sixth Circuit, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
571 F.2d 1283, 24 Cont. Cas. Fed. 82,155, 1978 U.S. App. LEXIS 12419, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-newport-news-shipbuilding-and-dry-dock-company-and-ca4-1978.