Andolina Shipping Ltd. v. TBS Eurolines Ltd.

84 F. Supp. 2d 527, 2000 U.S. Dist. LEXIS 1867, 2000 WL 218399
CourtDistrict Court, S.D. New York
DecidedFebruary 23, 2000
Docket99 CIV 3319 SHS
StatusPublished
Cited by1 cases

This text of 84 F. Supp. 2d 527 (Andolina Shipping Ltd. v. TBS Eurolines Ltd.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Andolina Shipping Ltd. v. TBS Eurolines Ltd., 84 F. Supp. 2d 527, 2000 U.S. Dist. LEXIS 1867, 2000 WL 218399 (S.D.N.Y. 2000).

Opinion

OPINION

STEIN, District Judge.

The question for resolution on this petition to appoint an arbitrator and compel arbitration pursuant to 28 U.S.C. § 1333 and 9 U.S.C. §§ 1 and 1px solid var(--green-border)">4 is whether the parties entered into a binding agreement to arbitrate. Petitioner Andolina Shipping Ltd. (“Andolina”), which seeks arbitration in New York against respondent TBS Eu-rolines Ltd. (“Eurolines”), believes they have. Eurolines contends that the parties did not enter into a binding charter party and that, consequently, no agreement to arbitrate was made. For the reasons set forth below, this Court finds that no charter party was formed and therefore denies Andolina’s petition.

BACKGROUND

The parties have submitted the dispute to the Court on the basis of the facts set forth in the pleadings and affidavits. Those facts are as follows: On or about February 8, 1999, Eurolines expressed an interest to Andolina in chartering a vessel. 1 Negotiations commenced three days later, when Eastern sent Andolina’s firm offer to Globe for the charter of Andolina’s vessel, WV WINDSONG. The next day — February 12 — Andolina directed the vessel to sail from Piraeus, Greece in order to meet the anticipated delivery date in Antwerp, Belgium.

After a series of counteroffers were exchanged, the parties reached agreement on the main terms of the charter party — a “fixture” — on February 16, 1999. Sea-trader Maritime confirmed the fixture by telex and Primera received a pro forma charter party on February 17. The fixture of the vessel, however, was “subject to reconfirmation” by Eurolines within 24 hours. It is common practice within the *529 shipping industry to subject the fixture either to the charterer’s reconfírmation, as in this case, or to approval of the charter’s board of directors. In anticipation of Eu-rolines’ reconfírmation of the fixture, the parties continued to negotiate the details of the charter party and apparently came to agreement on the details on February 19. Clause 74 of the pro forma charter party provided that “[a]ll disputes arising out of [the] contract shall be arbitrated at New York ... and subject to U.S. law....”

Although Eurolines was originally to have “lifted the subject,” i.e., reconfirmed the fixture, on February 17, 1999, it requested and received from Andolina four consecutive extensions of the deadline for reconfírmation. 2 Andolina asserts that Eurolines represented these extensions as necessary to receive “European Union” approval to pay certain transport charges at the contemplated discharge port, which approval Andolina understood to be a “minor issue.” Eurolines denies this representation, maintaining that it asked for the extensions to reconfirm the fixture because of unresolved issues with its sub-charterer.

Upon the vessel’s arrival in Antwerp on February 23, 1999, Eurolines advised An-dolina that the subject was not lifted on the charter party and that it would not accept delivery of the vessel. Andolina protested and subsequently advised Euro-lines of its intent to demand arbitration. Upon Eurolines’ refusal to appoint an arbitrator, Andolina filed and served this petition.

DISCUSSION

As noted above, this petition to compel arbitration and appoint an arbitrator is brought pursuant to the Federal Arbitration Act, 9 U.S.C. §§ 1 and 1px solid var(--green-border)">4, and 28 U.S.C. § 1333. Section 4 of the Federal Arbitration Act, 9 U.S.C. § 4, provides in relevant part as follows:

A party aggrieved by the alleged failure ... of another to arbitrate under a written agreement for arbitration may petition any United States district court which ... would have jurisdiction ... in admiralty of the subject matter of a suit arising out of the controversy ... for an order directing that such arbitration proceed in the manner provided for in such agreement.... If the making of the arbitration agreement ... be in issue, the court shall proceed summarily to the trial thereof.... [I]f the matter in dispute is within admiralty jurisdiction, the court shall hear and determine such issue.

See Deloitte Noraudit A/S v. Debate Haskins & Sells, U.S., 9 F.3d 1060, 1063 (2d Cir.1993) (“ ‘Thus, section 4 ... directs a district court to compel arbitration unless the “making” of an arbitration agreement ... is in question.’ ” (citation omitted)).

Andolina’s petition to compel arbitration is based on an arbitration clause contained in the pro forma charter party between the parties. Therefore, the issue before this Court is whether the charter party was binding on the parties. “[A] charter party is merely a contract, subject to all the rules and requirements of contract law.” Great Circle Lines, Ltd. v. Matheson & Co., 681 F.2d 121, 124 (2d Cir.1982). “However, where ... the contract is one of charter party, established practices and customs of the shipping industry inform the court’s analysis of what the parties agreed to.” Samsun Corp. v. Khozestan Mashine Kar Co., 926 F.Supp. 436, 439 (S.D.N.Y.1996).

According to federal admiralty law, a charter party is formed only when the owner and charterer agree to its essential terms. See Great Circle Lines, Ltd., 681 F.2d at 124-25. “A ‘recap’ communication, or ‘fixture,’ is recognized throughout the shipping industry as an agreement to a charter party’s essential *530 terms.” U.S. Titan, Inc. v. Guangzhou Zhen Hua Shipping Co., 16 F.Supp.2d 326, 329 (S.D.N.Y.), modified in part, 182 F.R.D. 97 (S.D.N.Y.1998). “The fixture is considered a binding contract, even if it is ‘subject to details’ — that is, even if the less important terms of the charter party remain to be agreed upon. Moreover, a fixture ‘subject to details’ does not create a condition subsequent that can defeat the duty to perform under the contract. Rather, it indicates an intention to continue negotiations, provided that the pro forma charter party will govern if the parties do not reach further agreement on the details.” Matter of Herlofson Management A/S and Ministry of Supply, Kingdom of Jordan, 765 F.Supp. 78, 79 n. 1 (S.D.N.Y. 1991) (citing Great Circle Lines, Ltd.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Safic Alcan & Cie v. M/T KASCO
565 F. Supp. 2d 519 (S.D. New York, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
84 F. Supp. 2d 527, 2000 U.S. Dist. LEXIS 1867, 2000 WL 218399, Counsel Stack Legal Research, https://law.counselstack.com/opinion/andolina-shipping-ltd-v-tbs-eurolines-ltd-nysd-2000.