Andolina Shipping Ltd. v. TBS Eurolines Ltd.

84 F. Supp. 2d 527, 2000 U.S. Dist. LEXIS 1867, 2000 WL 218399
District Court, S.D. New York·Decided February 23, 2000·No. 99 CIV 3319 SHS·Published·Cited by 1 cases

Opinion

OPINION

STEIN, District Judge.

The question for resolution on this petition to appoint an arbitrator and compel arbitration pursuant to 28 U.S.C. § 1333 and 9 U.S.C. §§ 1 and 1px solid var(--green-border)">4 is whether the parties entered into a binding agreement to arbitrate. Petitioner Andolina Shipping Ltd. (“Andolina”), which seeks arbitration in New York against respondent TBS Eu-rolines Ltd. (“Eurolines”), believes they have. Eurolines contends that the parties did not enter into a binding charter party and that, consequently, no agreement to arbitrate was made. For the reasons set forth below, this Court finds that no charter party was formed and therefore denies Andolina’s petition.

BACKGROUND

The parties have submitted the dispute to the Court on the basis of the facts set forth in the pleadings and affidavits. Those facts are as follows: On or about February 8, 1999, Eurolines expressed an interest to Andolina in chartering a vessel. 1 Negotiations commenced three days later, when Eastern sent Andolina’s firm offer to Globe for the charter of Andolina’s vessel, WV WINDSONG. The next day — February 12 — Andolina directed the vessel to sail from Piraeus, Greece in order to meet the anticipated delivery date in Antwerp, Belgium.

After a series of counteroffers were exchanged, the parties reached agreement on the main terms of the charter party — a “fixture” — on February 16, 1999. Sea-trader Maritime confirmed the fixture by telex and Primera received a pro forma charter party on February 17. The fixture of the vessel, however, was “subject to reconfirmation” by Eurolines within 24 hours. It is common practice within the *529 shipping industry to subject the fixture either to the charterer’s reconfírmation, as in this case, or to approval of the charter’s board of directors. In anticipation of Eu-rolines’ reconfírmation of the fixture, the parties continued to negotiate the details of the charter party and apparently came to agreement on the details on February 19. Clause 74 of the pro forma charter party provided that “[a]ll disputes arising out of [the] contract shall be arbitrated at New York ... and subject to U.S. law....”

Although Eurolines was originally to have “lifted the subject,” i.e., reconfirmed the fixture, on February 17, 1999, it requested and received from Andolina four consecutive extensions of the deadline for reconfírmation. 2 Andolina asserts that Eurolines represented these extensions as necessary to receive “European Union” approval to pay certain transport charges at the contemplated discharge port, which approval Andolina understood to be a “minor issue.” Eurolines denies this representation, maintaining that it asked for the extensions to reconfirm the fixture because of unresolved issues with its sub-charterer.

Upon the vessel’s arrival in Antwerp on February 23, 1999, Eurolines advised An-dolina that the subject was not lifted on the charter party and that it would not accept delivery of the vessel. Andolina protested and subsequently advised Euro-lines of its intent to demand arbitration. Upon Eurolines’ refusal to appoint an arbitrator, Andolina filed and served this petition.

DISCUSSION

As noted above, this petition to compel arbitration and appoint an arbitrator is brought pursuant to the Federal Arbitration Act, 9 U.S.C. §§ 1 and 1px solid var(--green-border)">4, and 28 U.S.C. § 1333. Section 4 of the Federal Arbitration Act, 9 U.S.C. § 4, provides in relevant part as follows:

A party aggrieved by the alleged failure ... of another to arbitrate under a written agreement for arbitration may petition any United States district court which ... would have jurisdiction ... in admiralty of the subject matter of a suit arising out of the controversy ... for an order directing that such arbitration proceed in the manner provided for in such agreement.... If the making of the arbitration agreement ... be in issue, the court shall proceed summarily to the trial thereof.... [I]f the matter in dispute is within admiralty jurisdiction, the court shall hear and determine such issue.

See Deloitte Noraudit A/S v. Debate Haskins & Sells, U.S., 9 F.3d 1060, 1063 (2d Cir.1993) (“ ‘Thus, section 4 ... directs a district court to compel arbitration unless the “making” of an arbitration agreement ... is in question.’ ” (citation omitted)).

Andolina’s petition to compel arbitration is based on an arbitration clause contained in the pro forma charter party between the parties. Therefore, the issue before this Court is whether the charter party was binding on the parties. “[A] charter party is merely a contract, subject to all the rules and requirements of contract law.” Great Circle Lines, Ltd. v. Matheson & Co., 681 F.2d 121, 124 (2d Cir.1982). “However, where ... the contract is one of charter party, established practices and customs of the shipping industry inform the court’s analysis of what the parties agreed to.” Samsun Corp. v. Khozestan Mashine Kar Co., 926 F.Supp. 436, 439 (S.D.N.Y.1996).

Free access — add to your briefcase to read the full text and ask questions with AI

Andolina Shipping Ltd. v. TBS Eurolines Ltd., 84 F. Supp. 2d 527, 2000 U.S. Dist. LEXIS 1867, 2000 WL 218399 (S.D.N.Y. 2000).

84 F. Supp. 2d 527 (Andolina Shipping Ltd. v. TBS Eurolines Ltd.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Safic Alcan & Cie v. M/T KASCO
565 F. Supp. 2d 519 (S.D. New York, 2008)