United States v. Condron

98 F.4th 1
CourtCourt of Appeals for the First Circuit
DecidedMarch 28, 2024
Docket23-1032
StatusPublished
Cited by1 cases

This text of 98 F.4th 1 (United States v. Condron) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Condron, 98 F.4th 1 (1st Cir. 2024).

Opinion

United States Court of Appeals For the First Circuit

No. 23-1032

UNITED STATES,

Appellee,

v.

CHRISTOPHER N. CONDRON,

Defendant, Appellant.

APPEAL FROM THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MASSACHUSETTS

[Hon. Indira Talwani, U.S. District Judge]

Before

Montecalvo, Thompson, and Rikelman, Circuit Judges.

Eamonn R. C. Hart, with whom Brann & Isaacson was on brief, for appellant.

Alexia R. De Vincentis, Assistant United States Attorney, with whom Joshua S. Levy, Acting United States Attorney, was on brief, for appellee.

March 28, 2024 RIKELMAN, Circuit Judge. After a fourteen-day trial, a

jury convicted Christopher Condron of wire fraud and conspiracy to

defraud the United States by obtaining payment for false claims.

On appeal, Condron argues that the district court erred in denying

his motion for a judgment of acquittal because: (1) there was

insufficient evidence as to each count to support his conviction;

and (2) the government's argument and evidence at trial

constructively amended, or at least prejudicially varied from, one

of the wire fraud counts. Additionally, he contends that the

district court abused its discretion when it limited his cross-

examination of a key government witness. After careful

consideration of the trial record, we affirm the verdict and

Condron's conviction.

I. BACKGROUND

This case centers on Condron's role in submitting

applications to the United States Department of the Treasury

("Treasury") for grant money in connection with purported

renewable energy projects. The facts here are complicated, and to

put them in context, we begin with an overview of the federal grant

program at issue.

A. The Section 1603 Grant Program

In 2009, Congress enacted section 1603 of the American

Recovery and Reinvestment Act ("Section 1603") to encourage

investments in clean, renewable energy projects. See generally

- 2 - Pub. L. No. 111-5, § 1603, 123 Stat. 115, 364 (2009). Section

1603 provides for cash grants, in lieu of otherwise available tax

credits, to entities that "place[d] in service specified energy

property" within a certain timeframe, id. § 1603(a), including

small wind energy, trash, and open-loop biomass facilities.1

Treasury contracted with the National Renewable Energy

Laboratory ("NREL"), "a government-funded research and development

organization that specializes in renewable energy," to review

Section 1603 grant applications.2 In turn, NREL created and

managed an online portal through which grant-seekers could submit

an application, upload any supporting documents, and respond to

any subsequent requests from NREL seeking additional information.

Under the Section 1603 program, there were two types of

applications: (1) a "placed in service" application; and (2) a

"placeholder" application, also known as a "start of construction"

application. A grant-seeker could submit a placed-in-service

application if the property had been "placed in service" at the

time of the application, meaning it was "ready and available for

1 Open-loop biomass facilities use "cellulosic waste" material

(i.e., plant-derived material like tree bark or sawdust) and/or livestock waste material (e.g., manure) to generate electricity.

2 During all relevant times here, Treasury did not conduct its "own independent review of [an] application aside from NREL's" review.

- 3 - its specific use."3 A placeholder application, by contrast, was

available for a grant-seeker that had begun construction on a

renewable energy project in 2009, 2010, or 2011 that would not "be

placed in service until beyond 2011."

When submitting a placed-in-service application, a

grant-seeker would submit a commissioning report, which was "[a]

report provided by the project engineer, . . . equipment vendor,

or an independent third party that certifie[d] that the equipment

ha[d] been installed, tested, and [was] ready and capable of being

used for its intended purpose." Treasury also required

"documentation to support the cost basis claimed for the property,"

including "a detailed breakdown of all costs included in the

basis." The cost basis was generally the amount that the grant-

seeker spent on the property, including "installation costs and

the cost for freight incurred in construction of

the . . . property." If the grant-seeker claimed a cost basis

that was more than $500,000, Treasury required that it submit "an

independent accountant's certification attesting to the accuracy

of all costs claimed as part of the basis of the property."

After reviewing a placed-in-service application, NREL

would provide Treasury with a report recommending that the

3A grant-seeker could submit a "placed in service" application if its property was placed in service in 2009, 2010, or 2011.

- 4 - application be approved (for a certain amount) or denied. For

those applications that it recommended approval, NREL would assign

a grant award that was up to 30 percent of the cost basis of the

property. For example, if the cost basis was $100,000, NREL would

assign a grant award of up to $30,000. Once NREL recommended that

a particular application be approved, Treasury would then initiate

payment to the grant-seeker via a wire transfer.

Importantly, placeholder applications, or start-of-

construction applications, did not provide an option to request a

grant payment. The purpose of a placeholder application was to

allow a grant-seeker whose property was not yet complete to later

request grant funds once the property was placed in service. A

grant-seeker submitting a placeholder application was required to

demonstrate via "[p]aid invoices and/or other financial

documents . . . that physical work of a significant nature ha[d]

begun on the property." Placeholder applications were required to

be submitted by October 1, 2012, and only after construction began.

NREL assigned a unique number to each application

submitted on its online platform.

B. The Indictment

On August 9, 2017, Condron and Jessica Metivier -- his

then-girlfriend and the mother of his children -- were indicted on

one count of conspiracy to defraud the United States with respect

to claims in violation of 18 U.S.C § 286 (Count One) and three

- 5 - counts of wire fraud in violation of 18 U.S.C. § 1343 (Counts Two

- Four).

With respect to the conspiracy charge, the indictment

alleged that Condron and Metivier conspired to defraud the United

States "by obtaining and aiding to obtain the payment and allowance

of false, fictitious, and fraudulent claims for monetary grants

under Section 1603." It further alleged that Condron and Metivier

hired a Massachusetts-based attorney to submit applications "to

Treasury seeking more than $50 million in Section 1603 grants on

behalf of [four] companies that the [a]ttorney created for

M[etivier]:" Acton Bio Energy, LLC ("ABE"); Concord Nurseries,

LLC; Kansas Green Energy, LLC ("KGE"); and Ocean Wave Energy, LLC

("OWE").

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Perez-Otero
First Circuit, 2026
SEC v. Veldhuis
First Circuit, 2026
United States v. Vavic
139 F.4th 1 (First Circuit, 2025)

Cite This Page — Counsel Stack

Bluebook (online)
98 F.4th 1, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-condron-ca1-2024.