United States v. Burlington Northern Railroad

200 F.3d 679, 30 Envtl. L. Rep. (Envtl. Law Inst.) 20281, 2000 Colo. J. C.A.R. 43, 49 ERC (BNA) 1897, 1999 U.S. App. LEXIS 33143
CourtCourt of Appeals for the Tenth Circuit
DecidedDecember 21, 1999
DocketNos. 97-1328, 97-1352 and 97-1353
StatusPublished
Cited by26 cases

This text of 200 F.3d 679 (United States v. Burlington Northern Railroad) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Burlington Northern Railroad, 200 F.3d 679, 30 Envtl. L. Rep. (Envtl. Law Inst.) 20281, 2000 Colo. J. C.A.R. 43, 49 ERC (BNA) 1897, 1999 U.S. App. LEXIS 33143 (10th Cir. 1999).

Opinion

HENRY, Circuit Judge.

This appeal arises from an action filed by the United States, pursuant to the Comprehensive Environmental Response, Compensation and Liability Act (“CERCLA”), 42 U.S.C. §§ 9601-9675, to recover costs incurred by the Environmental Protection Agency (“EPA”) while remediating hazardous substance contamination at the Broderick Wood Products Site (the “Site”), located in Adams County, Colorado. The United States (with the State of Colorado as an intervenor and cross-appellee) argues that the district court erred in reducing Burlington Northern’s (“BN’s”) $8.5 million dollar settlement decree. Specifically, the United States argues that: (1) the district court erred when it found that [682]*682the EPA’s conclusion to remediate the Site to a 1 x 10 ~5 cancer risk level was arbitrary and capricious; (2) the district court erred when it ruled that the EPA’s failure to amend the Record of Decision for Operable Unit I when it encountered the unexpected rock content in the sludge was arbitrary and capricious; and, (3) even if the actions regarding the Record of Decision for Operable Unit I were arbitrary and capricious, the district court erred in not requiring BN to prove that the cost would not have been incurred in any event.

BN cross-appeals. It argues that the district court erred in reducing the judgment against BN according to the geographic apportionment of a prior settlement with other defendants, rather than by the entire amount of the settlement. Further, BN argues that the district court erred in holding it liable for remediation costs incurred by the EPA before the EPA notified BN of its potential liability for the Site. For the reasons set forth below, we affirm the district court’s decision in part and reverse in part.

First, we conclude that the EPA’s remediation decision is supported by substantial evidence in the record and, therefore, is not arbitrary and capricious. Second, with regard to the EPA’s refusal to review or amend the plan for the first phase of cleanup, we reach different conclusions as to the particular remedial measures in question. As to the use of a settling tank to remove rock from liquified sludge, we conclude that no significant change or fundamental alteration of the scope, performance or cost of the remedial plan was involved. Therefore, the EPA was not required to amend the remediation plan in order to use the settling tank or to amend the plan. In contrast, the other remedial measures (the use of additional liners in rail cars containing sludge from the Site and the removal of tar heels solidifying from the sludge) did significantly change and fundamentally alter the scope and cost of the remedy implemented by the EPA. Therefore, as to these remedial measures, we agree with the district court that the EPA actions were arbitrary and capricious for failing to amend the plan.

Third, we disagree with the district court’s conclusion as to the impact of the EPA’s errors in adopting these new remedial measures. We hold that the district court erred in refusing to require BN to demonstrate that the EPA’s errors resulted in expenditures in excess of those that would have occurred in the absence of the errors. Accordingly, we remand the case to the district court so that it may determine whether the EPA’s errors resulted in costs that would not have otherwise been incurred.

Finally, we reject the arguments advanced in BN’s cross-appeal. We hold that the district court correctly reduced the judgment against BN pursuant to a geographic apportionment of a prior settlement with other defendants. Additionally, we hold that the district court did not err in finding BN liable for remediation costs incurred before the EPA notified BN of its potential liability for the Site.

BACKGROUND

Beginning in 1947, the Broderick Wood Products Company (“Broderick WP”) operated a wood treatment facility on a sixty-four acre parcel of land located immediately northwest of Denver, Colorado in Adams County (the “Site”). From 1947 through 1981, Broderick WP, and its successor, Broderick Investment Company (“BIC”), operated a wood treatment facility at the Site to treat power poles and other wood products with creosote and pentachlorophenol, which are CERCLA hazardous substances under 40 C.F.R. § 302.4(a).

While operating the wood treatment facility, the Broderick companies disposed of process waste on the northwest portion of the Site. They used two unlined impoundments: a pond located on a 17.5 acre parcel of land on the northwest portion of the Site (the “pond impoundment”), and an [683]*683impoundment area located at the processing plant on the eastern side (the “plant impoundment”).

In April of 1981, the EPA began investigating the Site. In 1984, it placed the Site on the National Priorities List for clean up pursuant to CERCLA. The United States initiated this case in 1986. At that time, the United States sought response costs from BIC, which had assumed the assets and liabilities of Broderick WP, and the current and former trustees of BIC (collectively the “BIC defendants”).

The EPA determined to remedy the Site through two “operable units” (or phases) with Operable Unit I addressing impoundment sludges, and Operable Unit II addressing soils and groundwater. The National Oil and Hazardous Substance Pollution Contingency Plan (“the Hazardous Substance Contingency Plan”), 40 C.F.R. Pt. 300, directs that sites “should generally be remediated in operable units when early actions are necessary or appropriate to achieve significant risk reduction quickly, when phased analysis and response is necessary or appropriate given the size or complexity of the site, or to expedite the completion of total site cleanup.” 40 C.F.R. § 300.430(a)(l)(ii)(A). The EPA asserts in its brief that it decided to conduct the remedy in two operable units in order to address different media of contamination.

1. The Record of Decision for Operable Unit I

On June 30, 1988, the EPA issued its Record of Decision for Operable Unit I to remedy both the pond impoundment sludge and the plant impoundment sludge. The pond impoundment consisted of 280,-000 gallons of hazardous sludge and the plant impoundment consisted of 450,000 gallons of hazardous sludge. The EPA concluded that the sludge would best be remediated through excavation and on-site incineration, with off-site disposal of the residue. The EPA further determined that the soil in both impoundments required removal and treatment, but decided to defer removal and treatment of the contaminated soils until Operable Unit II.

2. The Amendment to the Record of Decision for Operable Unit I

On September 24, 1991, the EPA issued an amendment to the Record of Decision for Operable Unit I. The amendment changed the initial remedial plan so that the impoundment sludge would be remedied through off-site reclamation rather than on-site incineration. The EPA revised the plan because incineration costs had increased substantially and equally protective alternatives (off-site reclamation) were available. The revised remedy concluded that the impoundment sludge should be removed from temporary on-site cells, placed in an on-site mixing tank, and converted into a pumpable slurry.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
D. Kansas, 2026
Orange Cnty. Water Dist. v. Alcoa Global Fasteners, Inc.
219 Cal. Rptr. 3d 474 (California Court of Appeals, 5th District, 2017)
Leathers v. Leathers
856 F.3d 729 (Tenth Circuit, 2017)
New York v. Next Millennium Realty, LLC
160 F. Supp. 3d 485 (E.D. New York, 2016)
United States v. NCR Corp.
911 F. Supp. 2d 767 (E.D. Wisconsin, 2012)
Alexander v. Mullarkey
340 F. App'x 455 (Tenth Circuit, 2009)
Friedland v. TIC-THE Industrial Co.
566 F.3d 1203 (Tenth Circuit, 2009)
General Electric Co. v. Browner
District of Columbia, 2009
McMurtry v. Aetna Life Insurance Company
273 F. App'x 758 (Tenth Circuit, 2008)
Basic Management Inc. v. United States
569 F. Supp. 2d 1106 (D. Nevada, 2008)
Vine Street, LLC v. Keeling Ex Rel. Estate of Keeling
460 F. Supp. 2d 728 (E.D. Texas, 2006)
Miami-Dade County v. United States
345 F. Supp. 2d 1319 (S.D. Florida, 2004)
United States v. EI Du Pont De Nemours & Co., Inc.
341 F. Supp. 2d 215 (W.D. New York, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
200 F.3d 679, 30 Envtl. L. Rep. (Envtl. Law Inst.) 20281, 2000 Colo. J. C.A.R. 43, 49 ERC (BNA) 1897, 1999 U.S. App. LEXIS 33143, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-burlington-northern-railroad-ca10-1999.