United States v. Broderick Investment Co.

963 F. Supp. 951, 27 Envtl. L. Rep. (Envtl. Law Inst.) 21267, 45 ERC (BNA) 1794, 1997 U.S. Dist. LEXIS 7000, 65 U.S.L.W. 2768
District Court, D. Colorado·Decided May 15, 1997·No. Civil Action 86-Z-369·Published·Cited by 6 cases

Opinion

MEMORANDUM OPINION AND ORDER

WEINSHIENK, District Judge.

The matter before the Court concerns the liability of Burlington Northern Railroad Company (BN) to the United States and the State of Colorado for clean-up costs associated with the Broderick Wood Products Site (Site) located near Denver, Colorado. In an Opinion filed February 25, 1997, the Court determined that BN was liable for a portion of the response costs incurred by plaintiffs pursuant to the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), excepting certain costs the Court found to have been arbitrarily and capriciously incurred. At that time, the Court reserved ruling on one class of response costs, those incurred in connection with the removal from the Site and incineration of solids during the interim remedial phase. On March 25, 1997, the Court heard additional argument on this issue, supplementing two days of argument on overall liability issues presented on November 18 and 19,1996. 1

*953 Throughout the clean-up process, the United States Environmental Protection Agency (EPA) served as the government’s primary representative. EPA’s first Record Of Decision (ROD 1), issued on June 80, 1986, recorded the agency’s choice of an interim remedy designed to control the major sources of contamination and direct contact exposure. (Environmental Protection Agency, Superfund Record Of Decision: Broderick Wood Products, CO., June 30, 1988, at i.) ROD 1 selected several remedial activities, including excavation and on-site incineration of the sludge and oil contained in two impoundments, with off-site disposal of the residual ash. (Id., at abstract.) EPA termed this interim remedy Operable Unit 1 (OU1).

In September of 1988, the EPA published an Amendment to ROD 1 (Amended ROD) which substituted a different remedy for the sludges. “Based on new technical data and cost information obtained subsequent to the June 1988 ROD,” the document explains, “EPA has reconsidered its decision to employ on-site incineration.” (EPA, Amendment To June 1988 Record Of Decision Broderick Wood Products, Sept. 1988, at 1.) Instead, the agency chose to utilize “off-site reclamation of the useful components of the sludge, and incineration and disposal of the residues.” (Id., at 2.)

As described in the Amended ROD, the selected remedy called for both solid and liquid sludges to be excavated, mixed with a solvent, and pumped into rail tank ears for shipment to a permitted reeycler. At the off-site facility, the sludge mixture would be recycled by a process of filter pressing, dehydration, distillation and combination with other chemicals. Residue from the recycling process was to be incinerated, with residual ash buried in a licensed landfill. The temporary impoundment cell liner, which initial projections estimated would fill three boxes, was also to be shipped off-site and incinerated.

During implementation, however, problems arose with EPA’s selected remedy. In particular, the feasibility studies conducted prior to selecting the OU1 remedy anticipated that solid material would comprise only 15 percent of the total sludge volume. (See Ex. 2.' to Pis.’ Reply, at 2, 3 (Feb. 3, 1997); Omaha Dist. Reply To EPA Region VII Gen. Technical Issues Of Concern, at 1 (Ex. 3 to Pls.’s Addendum (Jan. 3, 1997) (hereinafter Omaha Dist. Reply).)) As Allied Signal, the contractor selected to carry out the OU1 remedy, began processing the sludges, it discovered that the solid concentration was significantly higher. Ultimately, it appears that the solid concentration was actually close to 51 percent. (Id., at 1,5.)

Due to this significantly higher volume of solids, Allied Signal and its subcontractors took three remedial actions that were not anticipated in ROD 1 or Allied Signal’s contract. First, because the pumping equipment used to transfer the sludges to the railcars repeatedly clogged due to the high solid concentration, the contractors installed a settling box. Second, after the sludge-filled railcars arrived at the Alabama recycling site, Allied Signal discovered that additional solids had settled in the bottom of the cars, and that this material could not be made pumpable again. Accordingly, these tar heels were removed from the cars by hand and incinerated in Alabama.

The third unanticipated action was the incineration of far more miscellaneous material than was planned for in the Amended ROD. The OU1 remedy required incineration of the plastic liner that had contained the sludges in the impoundment ponds, and Allied Signal’s contract included packaging the liner in 20 one-cubic-yard boxes, shipment to Alabama, and incineration. Because of the unexpectedly high solid content, however, a total of 396 boxes were shipped, and their contents incinerated. (Ex. 2 to Pis.’ Reply, at 11 (Feb. 3, 1997); Basis Of Government Settlement Offer (Ex. 2 to Pis.’ Addendum (Jan. 3, 1997).)) In addition to the plastic liner, these boxes contained muck that had adhered to the liner; the impoundment covers; and material scraped from the impoundment walls and floor after the liner had been removed. (See Ex. A to Pis.’ Mot. Partial Reconsideration (Dec. 18, 1996).) Taken together, these three addition actions resulted in an Allied Signal bill that exceeded the original contract by approximately $1.3 million.

*954 Section 107(a) of CERCLA provides, “Notwithstanding any other provision or rule of law, and subject only to the defenses set forth in subsection (b) of this section,” a potentially responsible party such as BN “shall be liable for ... all costs of removal or remedial action incurred by the United States government ... not inconsistent with the national contingency plan.” 42 U.S.C. § 9607(a). Accordingly, BN bears the burden of showing that the actions of United States, acting through the EPA, were inconsistent with the national contingency plan (NCP). 2 U.S. v. Hardage, 982 F.2d 1436, 1442 (10th Cir.1992), cert. denied, 510 U.S. 913, 114 S.Ct. 300, 126 L.Ed.2d 248 (1993). To meet this burden, BN must show that “the EPA acted arbitrarily and capriciously in choosing a particular response action to respond to a hazardous waste site.” Id.; see also 42 U.S.C. § 9613(j)(3).

1. Characterization of Site Conditions

As an initial matter, BN asserts that EPA arbitrarily and capriciously failed to characterize adequately Site conditions prior to selecting a remedy. BN is correct that the NCP requires EPA to study site conditions carefully prior initiating any action. EPA must “collect data necessary to adequately characterize the site for the purpose of developing and evaluating effective remedial alternatives.” 40 C.F.R. § 300.430(d)(1). In part, this compels EPA to

Free access — add to your briefcase to read the full text and ask questions with AI

United States v. Broderick Investment Co., 963 F. Supp. 951, 27 Envtl. L. Rep. (Envtl. Law Inst.) 21267, 45 ERC (BNA) 1794, 1997 U.S. Dist. LEXIS 7000, 65 U.S.L.W. 2768 (D. Colo. 1997).

963 F. Supp. 951 (United States v. Broderick Investment Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

General Electric Co. v. Jackson
595 F. Supp. 2d 8 (District of Columbia, 2009)
General Electric Co. v. Browner
District of Columbia, 2009
United States v. Broderick Investment
200 F.3d 679 (Tenth Circuit, 1999)
United States v. Burlington Northern Railroad
200 F.3d 679 (Tenth Circuit, 1999)
United States v. Vertac Chemical Corp.
33 F. Supp. 2d 769 (E.D. Arkansas, 1998)
Public Service Co. of Colorado v. Gates Rubber Co.
22 F. Supp. 2d 1180 (D. Colorado, 1997)