General Electric Co. v. Browner

District Court, District of Columbia·Decided January 27, 2009·No. Civil Action No. 2000-2855·Published

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

GENERAL ELECTRIC COMPANY

Plaintiff,

v. Civil Action No. 00-2855 (JDB)

LISA JACKSON,1 Administrator, United States Environmental Protection Agency, and the UNITED STATES ENVIRONMENTAL PROTECTION AGENCY

Defendant.

MEMORANDUM OPINION

This case presents a broad constitutional attack on a significant federal environmental program. Plaintiff General Electric Company ("GE" or "plaintiff") challenges the U.S. Environmental Protection Agency's ("EPA") administration of section 106 of the Comprehensive Environmental Response, Compensation, and Liability Act ("CERCLA" or "the Act"), 42 U.S.C.§ 9601 et seq. GE contends that EPA's "pattern and practice" of administering section 106, 42 U.S.C. § 9606, violates the Due Process Clause of the Fifth Amendment. Am. Compl. at ¶ 1. Before the Court are the motions for summary judgment of GE and EPA and its administrator, Lisa Jackson.2 For the reasons that follow, the Court rejects GE's novel, but

1 Former acting administrator Stephen L. Johnson was previously named as the lead defendant in this case. Pursuant to Federal Rule of Civil Procedure 25(d), the Court automatically substitutes his successor, Lisa Jackson, as the new lead defendant.

2 EPA styled its motion as a motion for judgment on the pleadings, or alternatively, a motion for summary judgment. The same legal standard applies for each kind of motion. See Greenhouse v. Green, 574 F. Supp. 2d 57, 63-64 (D.D.C. 2008). Because the record in this case contains material from the parties' extensive discovery, the Court will treat EPA's motion as one

substantial, challenge. On the record presented, the administrative order regime under section 106 of CERCLA, as administered by EPA, does not offend due process.

BACKGROUND

I. The CERCLA Framework3 CERCLA was enacted to ensure efficient and expedient clean-up of hazardous waste sites resulting from industrial pollution. See Key Tronic Corp. v. United States, 511 U.S. 809, 814 (1994); see also United States v. Bestfoods, 524 U.S. 51, 55 (1998). Congress intended the parties responsible for polluting a site to clean it up themselves, or at least to pay the costs of clean-up. See Control Data Corp. v. S.C.S.C. Corp., 53 F.3d 930, 936 (8th Cir. 1995). Under CERCLA, once EPA identifies a hazardous site, it seeks to identify "potentially responsible parties" ("PRPs"). EPA may then initiate negotiations with PRPs to clean up a site. See 42 U.S.C. § 9622.

EPA has several options if negotiations fail. One option is to perform the clean-up itself, paying for it out of the so-called "Superfund" established by Congress for this purpose. EPA would then bring an action in federal district court under section 107 of CERCLA to recover clean-up costs from responsible parties. Id. §§ 9607(a)(4)(A), 9611(a). Another option is to seek an order from a federal district court compelling a responsible party to clean up a hazardous site. Id. § 9606(a). EPA's third option is to issue a "unilateral administrative order" ("UAO") under

for summary judgment.

3 The Court set forth a more comprehensive discussion of the CERCLA framework in its previous opinions in this case. See General Electric Co. v. Whitman, 257 F. Supp. 2d 8, 12-14 (D.D.C. 2003) (General Electric I); General Electric Co. v. Johnson, 362 F. Supp. 2d 327, 330-31 (D.D.C. 2005) (General Electric III); see also General Electric Co. v. EPA, 360 F.3d 188, 189-90 (D.C. Cir. 2004) (General Electric II).

section 106, ordering PRPs to clean up a site. Id. EPA may issue a UAO upon a finding "that there may be an imminent and substantial endangerment to the public health or welfare or the environment because of an actual or threatened release of a hazardous substance from a facility." Id. EPA's practice of issuing UAOs under section 106 is at the heart of GE's due process challenge in this case.

Under CERCLA, a PRP that believes it is not responsible for the clean-up faces a choice whether or not to comply with a UAO. If the PRP complies, it may seek reimbursement from other PRPs or from EPA itself upon completion of the clean-up. Id. § 9606(b). If the PRP does not comply, then EPA must file a civil action in federal district court to enforce the UAO. Id. § 9606(a). The court reviews EPA's remedy selection (i.e., its selection of a UAO) under the Administrative Procedure Act's "arbitrary and capricious" standard. See id. § 9606(b)(2)(D). The court reviews EPA's selection of the responsible party de novo. See Kelley v. EPA, 15 F.3d 1100, 1108 (D.C. Cir. 1994).

EPA may seek two kinds of monetary penalties if a PRP does not comply with a UAO.

First, if the noncomplying PRP lacks "sufficient cause" and willfully violates the order, then EPA may seek $32,500 for each day of noncompliance. Id. § 9606(b). Second, EPA may seek punitive damages up to three times "the amount of any costs incurred by the [Superfund] as a result of such failure to take proper action." Id. § 9607(c)(3). But these penalties are not automatic under CERCLA. If the reviewing court finds that the PRP had sufficient cause for noncompliance, then it cannot impose either form of penalty. Id. §§ 9606(b), 9607(c)(3). Even absent a finding of sufficient cause, moreover, the court has complete discretion as to the imposition and amount of any penalty. Id. § 9607(c)(3).

II. Procedural History GE filed its Complaint on November 28, 2000, and amended it on March 14, 2001. GE challenges CERCLA in two ways. First, GE alleges that the text of CERCLA itself facially violates the Due Process Clause. Am. Compl. at ¶¶ 21-28, 50, 54. Second, GE alleges that EPA's "pattern and practice" of administering the UAO regime under section 106 violates GE's due process rights. Id. at ¶¶ 17-20, 51-52, 54.

In March 2001, EPA moved to dismiss GE's Amended Complaint on jurisdictional grounds. EPA argued that this Court lacked subject matter jurisdiction because section 113(h) of CERCLA bars judicial review of a section 106 order until the clean-up is complete. This Court agreed and granted EPA's motion to dismiss. General Electric I, 257 F. Supp. 2d at 12. On appeal, however, the D.C. Circuit reversed and instructed this Court to consider the merits of GE's due process challenge on remand. General Electric II, 360 F.3d at 194. The court of appeals agreed that section 113(h) bars review of "as-applied, or particularized challenges," but concluded that section 113(h) does not bar "facial, or 'systemic'" challenges to CERCLA. Id. at 192. The court of appeals relied primarily on two cases to reach its holding: Johnson v. Robison, 415 U.S. 361, 373-74 (1974), and McNary v. Haitian Refugee Center, Inc., 498 U.S. 479, 492-94 (1991). Robison was a facial constitutional challenge to the Veterans' Readjustment Benefits Act, 38 U.S.C. § 211(a). Section 211 of that Act barred review of individual benefit determinations, but the Supreme Court held that section 211 did not extend to facial constitutional challenges to the statute. Robison, 415 U.S. at 367. McNary was a challenge to the Immigration and Naturalization Service's "pattern and practice" of administering the Special Agricultural Workers (SAW) provisions of the Immigration Reform Control Act, 8 U.S.C. §

1160. Section 210(e) of that Act barred judicial review "of a determination respecting an application" for SAW status, but the Supreme Court held that section 210(e) did not apply to "general collateral challenges to unconstitutional practices and policies used by the agency in processing applications." McNary, 498 U.S. at 492. Because Robison and McNary permitted facial and pattern and practice claims to proceed in the face of provisions similar to CERCLA's section 113(h), the D.C. Circuit instructed this Court to consider GE's due process challenges to CERCLA on remand. 360 F.3d at 194.

Free access — add to your briefcase to read the full text and ask questions with AI

General Electric Co. v. Browner, (D.D.C. 2009).

General Electric Co. v. Browner (General Electric Co. v. Browner) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Corn v. City of Lauderdale Lakes
95 F.3d 1066 (Eleventh Circuit, 1996)
Marbury v. Madison
5 U.S. 137 (Supreme Court, 1803)
Ex Parte Young
209 U.S. 123 (Supreme Court, 1908)
Missouri Pacific Railway Co. v. Nebraska
217 U.S. 196 (Supreme Court, 1910)
Missouri Pacific Railway Co. v. Tucker
230 U.S. 340 (Supreme Court, 1913)
Chicago, Milwaukee & St. Paul Railway Co. v. Polt
232 U.S. 165 (Supreme Court, 1914)
Joint Anti-Fascist Refugee Committee v. McGrath
341 U.S. 123 (Supreme Court, 1951)
Hannah v. Larche
363 U.S. 420 (Supreme Court, 1960)
Reisman v. Caplin
375 U.S. 440 (Supreme Court, 1964)
Fuentes v. Shevin
407 U.S. 67 (Supreme Court, 1972)
United States v. Florida East Coast Railway Co.
410 U.S. 224 (Supreme Court, 1973)
Johnson v. Robison
415 U.S. 361 (Supreme Court, 1974)
Arnett v. Kennedy
416 U.S. 134 (Supreme Court, 1974)
Mitchell v. W. T. Grant Co.
416 U.S. 600 (Supreme Court, 1974)
Mathews v. Eldridge
424 U.S. 319 (Supreme Court, 1976)
Paul v. Davis
424 U.S. 693 (Supreme Court, 1976)
Califano v. Boles
443 U.S. 282 (Supreme Court, 1979)
Andrus v. Allard
444 U.S. 51 (Supreme Court, 1979)