United States v. Amtreco, Inc.

846 F. Supp. 1578, 24 Envtl. L. Rep. (Envtl. Law Inst.) 21455, 38 ERC (BNA) 1731, 1994 U.S. Dist. LEXIS 3427, 1994 WL 96758
CourtDistrict Court, M.D. Georgia
DecidedMarch 22, 1994
DocketCiv. A. 90-31-VAL (WDO)
StatusPublished
Cited by8 cases

This text of 846 F. Supp. 1578 (United States v. Amtreco, Inc.) is published on Counsel Stack Legal Research, covering District Court, M.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Amtreco, Inc., 846 F. Supp. 1578, 24 Envtl. L. Rep. (Envtl. Law Inst.) 21455, 38 ERC (BNA) 1731, 1994 U.S. Dist. LEXIS 3427, 1994 WL 96758 (M.D. Ga. 1994).

Opinion

ORDER

OWENS, Chief Judge.

Before the court is the United States’ motion for summary judgment regarding response costs under the Comprehensive Environmental Response, Compensation, and Liability Act, 42 U.S.C. § 9601, et seq. (“CERCLA”). After careful consideration of the arguments of counsel, the relevant case law, and the record as a whole, the court issues the following order.

FACTS

This case has a long and complex history in this court. On March 31, 1977, defendant James Dickerson incorporated Amtreco, Inc. (“Amtreco”), a business that treated and sold wooden fence posts. Dickerson was the president, sole shareholder, and sole director of Amtreco.

In the summer of 1977, construction of a wood treatment plant for Amtreco began. The plant was constructed upon a 5.6 acre tract of land in Homerville, Georgia, that was owned by Dickerson. Between September 1977 and March 1978, thousands of gallons of creosote, a primary chemical used in the wood treating process that is classified as a hazardous substance under 42 U.S.C. § 9601(14), were delivered to the Amtreco site.

On March 30, 1978, Dickerson conveyed the property on which the plant was constructed to Amtreco in fee simple. Amtreco has held title to the property through the time of the filing of this lawsuit. 1

Amtreco operated the wood treatment plant until sometime in 1980, when it was forced to close due to financial hardship. In January, 1984, representatives from the Environmental Protection Division of the Georgia Department of Natural Resources (“Georgia EPD”) entered the Amtreco site, and, after collecting and testing samples from the site, they notified the Environmental Protection Agency (“EPA”) in May. On May 16, 1984, the EPA conducted an investigation of the Amtreco site and determined that hazardous wastes were present 2 and that they should be removed from the site.

On July 19, 1984, the EPA issued an administrative order requiring Dickerson and Amtreco to initiate a cleanup at the Amtreco site. Under the administrative order, Dickerson and Amtreco were given until July 24, 1984, to begin the cleanup, and they were to complete the cleanup within forty-two days. Dickerson and Amtreco submitted a proposal to the EPA to use biodegradation to clean the site, and the EPA extended the July deadline in order to consider the proposal.

On August 27, 1984, the EPA rejected the proposal on the ground that it was not an adequate method to remove the waste from the Amtreco site. The EPA then informed defendants that it would begin a cleanup of the site on September 5, 1984, using funds from the Hazardous Substance Response Trust Fund.

On September 4, 1987, Dickerson and Amtreco sought to block the EPA action by filing a suit in this court for injunctive and declaratory relief from the EPA’s proposed cleanup. This court ultimately denied the relief and held that the EPA was entitled to enter the Amtreco site and conduct a cleanup action there. United States v. Dickerson, 660 F.Supp. 227 (M.D.Ga.1987). This court specifically found that the EPA had established that “there has been a release or may be a release of a hazardous substance” at the site, Dickerson, 660 F.Supp. at 231; therefore, the EPA had the right to conduct a response action. Id. The Eleventh Circuit affirmed in Dickerson v. Administrator, En *1581 vironmental Protection Agency, 834 F.2d 974 (11th Cir.1987).

On July 2, 1987, the EPA selected off-site transport as the-method to remove the hazardous materials from the Amtreeo site, and funding for the cleanup was authorized. The actual cleanup took place from August 10, 1987 to March 18, 1988.

On April 26, 1990, the United States filed its complaint in this court seeking from defendants the recovery of all costs connected to the cleanup.

On December 22, 1992, this court granted the United States’ motion for summary judgment regarding the issue of defendants’ liability for response costs under CERCLA. United States v. Amtreco, Inc., 809 F.Supp. 959 (M.D.Ga.1992). In concluding, this court wrote:

The determination of the United States’ motion leaves the following issues to be determined at trial:
1. All Costs Attributable to the Cleanup of the Amtreeo Site
2. Whether the Amtreeo Response Action Was a Removal or Remediation
3. Those Costs Not Inconsistent With the National Contingency Plan

In determining which costs are not inconsistent with the national contingency plan, the following issues are among those that will be considered if defendants choose to raise them:

1. Cost Effectiveness (if required)
2. EPA Selection of the Response
3. Petroleum Exclusion

Amtreco, Inc., 809 F.Supp. at 971. In response to the December 22, 1992 order, the United States filed this motion for summary judgment regarding response costs.

DISCUSSION

In addressing the United States’ motion for summary judgment on costs, this court is required to undertake a three-part inquiry. First, the court must decide whether the Amtreeo response action was a “removal” or a “remediation.” Second, the court must determine what costs are attributable to the cleanup of the Amtreeo site. Finally, the court must determine whether any of the costs incurred by the United States are inconsistent with the National Contingency Plan (“NCP”).

I. “Removal” or “Remediation”

Defendants assert that the United States undertook a “remedial” action 3 at the Amtreeo site, not a “removal” action 4 , and, *1582 therefore, because the United States failed to meet the NCP’s requirements for a “remedial” action, defendants are not liable for the costs incurred. Defendants contend that “[r]emoval actions are only meant to remove whatever immediate threat is present so that funds can be utilized on other sites____ The action taken by the EPA was not a short term, emergency action but was in the nature of an alleged permanent long term remedy.” This particular argument, however, was rejected by the Eighth Circuit Court of Appeals in General Electric Co. v. Litton Industrial Automation Systems, Inc., 920 F.2d 1415, 1419 n. 4 (8th Cir.1990). The court wrote:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
846 F. Supp. 1578, 24 Envtl. L. Rep. (Envtl. Law Inst.) 21455, 38 ERC (BNA) 1731, 1994 U.S. Dist. LEXIS 3427, 1994 WL 96758, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-amtreco-inc-gamd-1994.