Bancamerica Commercial Corp. v. Trinity Industries, Inc.

900 F. Supp. 1427, 1995 U.S. Dist. LEXIS 13100, 1995 WL 519393
CourtDistrict Court, D. Kansas
DecidedAugust 2, 1995
DocketCiv. A. 90-2325-GTV
StatusPublished
Cited by19 cases

This text of 900 F. Supp. 1427 (Bancamerica Commercial Corp. v. Trinity Industries, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bancamerica Commercial Corp. v. Trinity Industries, Inc., 900 F. Supp. 1427, 1995 U.S. Dist. LEXIS 13100, 1995 WL 519393 (D. Kan. 1995).

Opinion

TABLE OF CONTENTS

INTRODUCTION AND BACKGROUND.1435

FINDINGS OF FACT.1435

I. The Parties.1435

II. The Site.1436

III. Activities at the Site.1437

A. ASARCO .1437

B. KCSS 1.1437

C. KCSS II.1437

D. Trinity/Mosher.1438

E. BACC.1441

TV. The Contamination and Cleanup.1442

A. The Initial Investigation and Response.1442
B. EPA Negotiations, Orders, and Actions.1443
C. BACC’s Cleanup Activities.1445
D. ASARCO’s Cleanup Activities.1445
V. Cleanup Costs.1446
A. BACC.1446
B. ASARCO .1448
VI. Sources of Contamination.1448
A. Barrels.1448
B. Asbestos.1448
C. Lead.1449

CONCLUSIONS OF LAW.1450

I. CERCLA Claims.1450
A. Nature of the Action — Cost Recovery vs. Contribution.1450
B. Liability of Trinity and Mosher Steel .1450
1. Consistency with the National Contingency Plan.1451
2. Trinity and Mosher Steel as Responsible Parties.1454

a. Trinity and Mosher Steel as Operators.1454

b. Hazardous Substance Disposal.1455

C. BACC’s Liability .1455
D. Response Costs...1458
1. BACC’s Response Costs...1458

a. Barrel Removal.1459

b. Underground Storage Tank Remediation.1461

c. Asbestos Remediation.1462

d. Lead Removal .1463

e. Guard Costs.1463

f. Attorney Fees and Expenses.1463

g. EPA Oversight Costs.1466

2. ASARCO’s Response Costs .1467

a. Lead Removal .1467

b. Attorney Fees .1468

3. Prejudgment Interest.1469
4. Summary — Response Costs.1470
E. Apportionment and Allocation.1470
1. Apportionment of Harm.1470
2. Allocation of Costs.1472
3. Allocating Specific Costs.1474

a. Barrel Removal.1474

b. Security Guards.1475

*1435 e. Lead Removal .1475

d. Attorney Fees .1475

F. Summary — CERCLA Liability and Allocation of Costs.1475
II. Indemnification.1475
III. Breach of Contract.1477
A. Condition of Premises.1477
B. Diminution in Value.1478
C. Property Taxes.1479
D. Attorney Fees.1480
E. Summary — Breach of Contract Claims.1481

CONCLUSION.1481

Appendix A: BACC Attorney Fee Response Costs Adjustments.1482

Appendix B: BACC Attorney Fee Response Costs Summary.1487

Appendix C: ASARCO Attorney Fee Response Costs Adjustments .1488

MEMORANDUM AND ORDER

VAN BEBBER, Chief Judge.

INTRODUCTION AND BACKGROUND

This action involves the environmental cleanup of a 27-acre industrial site located at 2100 Metropolitan Avenue in Kansas City, Kansas (the “Site”). Plaintiffs Bancamerica Commercial Corporation (“BACC”) and AS-ARCO Incorporated (“ASARCO”) seek to hold defendants Trinity Industries, Inc. (“Trinity”) and Mosher Steel Company (“Mosher Steel”) liable under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (“CERCLA”), 42 U.S.C. §§ 9601 et seq., as amended, for costs incurred by the plaintiffs in response to a release of hazardous substances at the Site. BACC is the current owner of the Site and ASARCO is the successor corporation to a company that operated one of the largest lead smelters in the country at the Site in the 1890s. Trinity and Mosher Steel operated a structural steel fabrication facility at the site during the 1980s. In addition to the CERC-LA claims, BACC also asserts pendent state law claims against Trinity for indemnification and breach of contract. Trinity has asserted an indemnity counterclaim against BACC.

BACC began this suit by bringing a CERCLA action against Trinity and Mosher Steel on September 14, 1990. Trinity and Mosher Steel impleaded ASARCO as a third party defendant on December 31, 1990, and BACC added ASARCO as a defendant on July 9, 1991. ASARCO filed counterclaims against BACC, Trinity, and Mosher Steel. BACC also added three individual defendants who had been officers and directors of Kansas City Structural Steel, a company that operated at the Site from 1907 until 1982. The individual defendants entered into settlement agreements and are no longer part of this suit. BACC and ASARCO also settled the claims between themselves, and ASAR-CO was realigned as a party plaintiff.

The court denied a number of summary judgment motions, and no substantive issues were resolved prior to trial. A trial to the court was held over 17 days during the period January 18 to April 15, 1994. After the United States Supreme Court issued a ruling in June 1994 regarding the treatment of attorney fees as CERCLA response costs, the court reopened the record and the parties returned to present additional testimony and evidence on September 22, 1994.

All parties have submitted proposed findings of fact and conclusions of law, in addition to a variety of other trial and post-trial briefs. The court has considered the testimony, evidence, and arguments of the parties. Pursuant to Fed.R.Civ.P. 52(a), the court makes the following findings of fact and conclusions of law.

FINDINGS OF FACT 1

I. The Parties

1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shell Oil Co. v. United States
93 Fed. Cl. 439 (Federal Claims, 2010)
New York v. SOLVENT CHEMICAL CO., INC.
685 F. Supp. 2d 357 (W.D. New York, 2010)
Raytheon Aircraft Co. v. United States
532 F. Supp. 2d 1306 (D. Kansas, 2007)
Browning-Ferris Industries of Illinois, Inc. v. Ter Maat
13 F. Supp. 2d 756 (N.D. Illinois, 1998)
Morrison Enterprises v. McShares, Inc.
13 F. Supp. 2d 1095 (D. Kansas, 1998)
Pichowicz v. Atlantic Richfield
37 F. Supp. 2d 98 (D. New Hampshire, 1997)
Stearns & Foster Bedding Co. v. Franklin Holding Corp.
947 F. Supp. 790 (D. New Jersey, 1996)
Atlantic Richfield Co. v. American Airlines, Inc.
98 F.3d 564 (Tenth Circuit, 1996)
In Re Combustion, Inc.
968 F. Supp. 1112 (W.D. Louisiana, 1996)
Town of New Windsor v. Tesa Tuck, Inc.
935 F. Supp. 317 (S.D. New York, 1996)
Sun Co., Inc.(R & M) v. Browning-Ferris, Inc.
919 F. Supp. 1523 (N.D. Oklahoma, 1996)
Sun Co., Inc. (R & M) v. Browning-Ferris, Inc.
919 F. Supp. 1523 (N.D. Oklahoma, 1996)
Johnson County Airport Commission v. Parsonitt Co.
916 F. Supp. 1090 (D. Kansas, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
900 F. Supp. 1427, 1995 U.S. Dist. LEXIS 13100, 1995 WL 519393, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bancamerica-commercial-corp-v-trinity-industries-inc-ksd-1995.