United States v. Dickerson

660 F. Supp. 227, 25 ERC 2087, 18 Envtl. L. Rep. (Envtl. Law Inst.) 20269, 25 ERC (BNA) 2087, 1987 U.S. Dist. LEXIS 5125
CourtDistrict Court, M.D. Georgia
DecidedMay 4, 1987
DocketCiv. A. 84-80-VAL (WDO), 84-76-VAL (WDO)
StatusPublished
Cited by8 cases

This text of 660 F. Supp. 227 (United States v. Dickerson) is published on Counsel Stack Legal Research, covering District Court, M.D. Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Dickerson, 660 F. Supp. 227, 25 ERC 2087, 18 Envtl. L. Rep. (Envtl. Law Inst.) 20269, 25 ERC (BNA) 2087, 1987 U.S. Dist. LEXIS 5125 (M.D. Ga. 1987).

Opinion

MEMORANDUM OPINION AND ORDER

OWENS, Chief Judge:

These actions, consolidated by order dated September 21, 1984, seek to clarify the rights and obligations of the various parties to the administrative order (the order) issued by the Environmental Protection Agency (EPA) on July 19, 1984. Pursuant to the Comprehensive Environmental Response Compensation and Liability Act (CERCLA), 42 U.S.C. §§ 9601-75, this order required James L. Dickerson, Lareeta H. Dickerson, and Amtreco, Inc. (hereinafter the Dickersons) to initiate a cleanup of its abandoned wood treatment facility located in Homerville, Georgia. The Dickersons were given until July 24, 1984, to *229 begin the cleanup of the Homerville site, and were instructed that the cleanup should be completed no later than forty-two days thereafter. The Dickersons responded to this request by submitting for the EPA’s approval its own proposed plan for cleaning up the site. The EPA extended the July 24, 1984, deadline in order to consider this proposal by the Dickersons. Following the submittal of their plan on August 27, 1984, the EPA, after considering its contents, rejected it on the basis that it did not propose an adequate solution to the problems at the Homerville site. The EPA subsequently informed the Dickersons that beginning September 5,1984, it would begin a cleanup of the site utilizing funds from the Hazardous Substance Response Trust Fund.

In response to these actions, the Dicker-sons, on September 4, 1984, filed a complaint in this court seeking declaratory and injunctive relief from the proposed cleanup of the EPA. A temporary restraining order was granted to the Dickersons, thus maintaining the status quo pending resolution of the matter by the court. On September 21, 1984, the EPA filed its own complaint for declaratory and injunctive relief seeking, primarily, court permission for its immediate access to the Homerville site so that it could begin the cleanup process. Following the granting of the temporary restraining order, the parties informally agreed to attempt a settlement of this matter without the court’s intervention. This settlement process has apparently reached an impasse, and, therefore, the court must now resolve the controversy.

The EPA’s Motion to Dismiss

The EPA has filed a motion to dismiss the Dickersons’ complaint for failure to demonstrate subject matter jurisdiction over the claims. It is the EPA’s contention that CERCLA precludes pre-enforcement review of its “response” actions unless those actions constitute either a cost recovery action under 42 U.S.C. § 9607 or a civil abatement suit under 42 U.S.C. § 9606. The reasons for this lack of pre-enforcement review is asserted to be that the nature of the EPA’s work, protecting the public and the environment from the dangers of hazardous waste, requires it to have the ability to respond immediately, which under normal circumstances is long before legal determinations of liability have been made. The EPA admits, however, that its response actions are not completely unreviewable, but it contends that review is limited solely to the issue of whether a site poses a threat to either the public or the environment warranting a response action in the first instance. On this issue, the EPA urges that a determination by the EPA that a site is dangerous is subject to an arbitrary and capricious, abuse of discretion, or not otherwise in accordance with law standard of review. See 42 U.S.C. § 9604(e)(5)(B). In this case, the EPA maintains that the Homerville site clearly is a hazard that needs to be cleaned up, and its decision to do so was not clearly arbitrary and capricious. The Dickersons, on the other hand, contend that the site is not an imminent threat to the public health and welfare or the environment, nor has there been a “release” or threat of release at the Homerville site. They further contend that the cleanup proposal that they submitted is consistent with the national contingency plan and should, thus, be accepted by the EPA. The evidence presented to the court concerning the Homerville site shows the following.

Factual Background

The land in question is located in Homer-ville, Georgia. Prior to ceasing operation sometime during 1980, the 5.6 acre site was used in a wood product preserving business. The primary chemical used in this business was creosote. Creosote has been classified as a hazardous substance, pursuant to 42 U.S.C. § 9601 (14), and is a recognized human and animal carcinogen. In January, 1984, representatives of the State of Georgia entered the site and collected test samples. The EPA was informed of the site by the Environmental Protection Division of the Georgia Department of Natural Resources in May of 1984. Shortly thereafter, on May 16, 1984, the EPA conducted its own inspection and preliminary *230 assessment of the site. That inspection, along with subsequent investigations, revealed the presence of two hundred and fifty-two drums in various conditions containing cresote constituents and hazardous solvents such as methyl ethyl ketone and benzene. Also present at the site are a pressure cylinder, two 20,000 gallon tanks and one 10,000 gallon tank, all of which contain, in various amounts, waste creosote. The site also contains two large, unlined surface impoundments, that contain large quantities of waste creosote.

Ten residences which use shallow wells to obtain drinking water from a nearby aquifer are located within one quarter mile of the site. The nearest well to the site being used for drinking purposes has been replaced with a deep well. There is no evidence, as of yet, that waste creosote has contaminated any of these wells, nor is there any evidence that this creosote has permeated into the water supply generally. Throughout the Homerville site, soil and vegetation stained by creosote are readily visible. The site is not secured from the public, and there are no containment walls that might prevent the spread of creosote during a heavy rainstorm. Based upon these relatively undisputed facts, the EPA seeks to enter the site and begin a cleanup that would include removing the hazardous waste to an authorized hazardous waste disposal area. The Dickersons contend that this sort of cleanup is much too expensive and seek to implement their own cleanup using an allegedly cheaper process known as biodegradation. Because of the government’s motion to dismiss, the court must now determine what rights each of the parties maintain in this case that might block the actions of the other at this juncture.

Conclusions of Law

Initially, the court must determine what rights, if any, the EPA has that would allow it to enter the Homerville site. On this point, CERCLA provides in relevant part,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
660 F. Supp. 227, 25 ERC 2087, 18 Envtl. L. Rep. (Envtl. Law Inst.) 20269, 25 ERC (BNA) 2087, 1987 U.S. Dist. LEXIS 5125, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-dickerson-gamd-1987.