United States Surety Co. v. Hanover R.S. Ltd. Partnership

543 F. Supp. 2d 492, 2008 U.S. Dist. LEXIS 12730
District Court, W.D. North Carolina·Decided February 8, 2008·No. Civil Action 3:07-CV-00381-DCK·Published·Cited by 7 cases

Opinion

ORDER

DAVID C. KEESLER, United States Magistrate Judge.

THIS MATTER IS BEFORE THE COURT on Plaintiff United States Surety Company’s (“US Surety” or “Plaintiff’) “Motion to Declare Bond Issues Are Not Arbitrable Issues And Motion To Stay Arbitration of Bond Issues (Document No. 6), filed September 21, 2007; and “Defendant Hanover R.S. Limited Partnership’s Motion to Dismiss Or Stay Litigation and Compel Arbitration” (Document No. 19), filed October 22, 2007. The parties have consented to Magistrate Judge jurisdiction pursuant to 28 U.S.C. § 636(c), and these motions are now ripe for disposition.

Having carefully considered the arguments, the record, and the applicable authority, Plaintiffs motion will be denied; *493 Defendant Hanover R.S. Limited Partnership’s (“Hanover”) Motion to Dismiss is denied without prejudice; and Defendant Hanover’s alternative motion to “Stay Litigation And Compel Arbitration” will be granted. It will be further ordered that all claims and defenses between Plaintiff U.S. Surety and Defendant Hanover, arising out of or relating to the enforcement of the subcontract and/or surety bond are arbitrable, and must be submitted for adjudication in the pending arbitration titled: Hanover R.S. Limited Partnership v. Fuller Drywall & Paint, Ltd. and United States Surety Company (AAA Case No. 31-110-Y-00116-07).

I. FACTUAL AND PROCEDURAL BACKGROUND

Defendant Hanover is the general contractor for construction of a mixed-use residential/retail building known as “The Residence at SouthPark” located in Charlotte, North Carolina (the “Project”). Complaint (Document No. 1) at ¶ 5.

Hanover entered into a subcontract with Defendant Fuller Drywall, Ltd. (“Fuller”) dated April 10, 2006 (the “Subcontract”), whereby Fuller agreed to provide certain labor and materials for incorporation into the Project (the “Work”). Complaint (Document No. 1) at ¶ 6. A copy of the Subcontract is attached to the Complaint (Document No. 1) as Exhibit “A”.

On or about May 31, 2006, Plaintiff U.S. Surety issued a subcontract performance bond (the “Bond”) as surety for its principal, Fuller, and for the benefit of Hanover. See Complaint (Document No. 1) at ¶ 7. A copy of the Bond is attached to the Complaint (Document No. 1) as Exhibit “B”.

The Bond provides as follows: “... Subcontract is by reference made a part hereof. ...” See Complaint (Document No. 1), Exhibit “B” at 1; see also U.S. Surety’s “Memorandum in Support of Motion to Declare Bond Issues Are Not Arbitrable Issues ...” (Document No. 7) at 3 (“the Bond incorporate^] the Subcontract by reference”). The Bond further provides the following: “The responsibilities of the Obligee [Hanover] to the Surety [US Surety] shall not be greater than those of the Obligee under the Subcontract.” Complaint (Document No. 1), Exhibit “A”, Bond at p. 2, § 4.

The Subcontract contains an arbitration clause, which provides in relevant part as follows: “Any dispute arising out of or relating to • this Agreement shall ... be settled by ... binding arbitration conducted by a neutral arbitrator selected by the American Arbitration Association at its offices closest to the Project.” Complaint (Document No. 1), Exhibit “A”, Subcontract at § 19. In addition, the Subcontract provides that “Contractor may require the joinder of another person or party who may have a related claim or interest in the proceedings.” See Complaint (Document No. 1), Exhibit “A”, Subcontract at ¶ 19.

Disputes have arisen between Hanover and Fuller concerning performance under the Subcontract, each alleging the other has been and is in breach of the Subcontract. See Complaint (Document No. 1) at ¶ 9. On May 30, 2007, Hanover initiated arbitration proceedings against Fuller seeking, without limitation, breach of contract damages resulting from Fuller’s allegedly defective and incomplete work, including all costs associated with Hanover’s supplementation of Fuller’s Work. See Complaint (Document No. 1) at ¶ 10. On June 18, 2007, Fuller filed an Answering Statement and Counterclaim in the arbitration proceedings denying Hanover’s claims and seeking affirmative recovery resulting from Hanover’s alleged breach of contract, quantum meruit and negligence. See Complaint (Document No. 1) at ¶ 13.

*494 On June 12, 2007, Hanover invited U.S. Surety to consent to be joined and participate in the pending arbitration proceedings. See Complaint (Document No. 1) at ¶ 14. US Surety accepted Hanover’s invitation to participate in the pending arbitration proceedings. See Complaint (Document No. 1) at ¶ 15. 1 However, in joining the arbitration as a party, U.S. Surety sought to limit the scope of the arbitration panel’s authority by reserving the right to litigate its so-called “surety claims/defenses” (“Surety Defenses”) in a subsequent and separate court proceeding. See Complaint (Document No. 1) at ¶¶ 15 & 17.

On September 7, 2007, U.S. Surety filed the present action seeking a declaration that (a) “issues concerning its liability under the Bond are not arbitrable” and (b) “Hanover has failed to satisfy the Bond’s conditions precedent, and [US Surety’s] obligations under the Bond are fully discharged.” See Complaint (Document No. 1) at ¶¶ 21 & 24.

On September 21, 2007, U.S. Surety filed the pending Motion to Declare Bond Issues are not Arbitrable Issues and Motion to Stay Arbitration of Bond Issues. (Document Nos. 6 & 7). On October 22, 2007, Hanover filed its Motion to Dismiss or Stay Litigation and Compel Arbitration and its Response and Opposition to Plaintiffs Motion to Declare Bond Issues are not Arbitrable Issues and Motion to Stay Arbitration of Bond Issues. (Document Nos. 19 & 20). On October 31, 2007, U.S. Surety filed its Reply to Hanover R.S. Limited Partnership’s Response to Motion to Declare Bond Issues are not Arbitrable Issues and Motion to Stay Arbitration of Bond Issues. (Document No. 21). A hearing on the above motions was held by the Court with the undersigned presiding on January 29, 2008.

II. STANDARD OF REVIEW

A. Determination of Arbitrability

Free access — add to your briefcase to read the full text and ask questions with AI

United States Surety Co. v. Hanover R.S. Ltd. Partnership, 543 F. Supp. 2d 492, 2008 U.S. Dist. LEXIS 12730 (W.D.N.C. 2008).

543 F. Supp. 2d 492 (United States Surety Co. v. Hanover R.S. Ltd. Partnership) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Wang v. NYZ Management Services, LLC
W.D. North Carolina, 2020
Schneider Electric Buildings Critical System, Inc. v. Western Surety Co.
165 A.3d 485 (Court of Appeals of Maryland, 2017)
Schneider Elect. Build. Critical Systems v. Western Surety Co.
Court of Special Appeals of Maryland, 2016
Schneider Electric Buildings Critical Systems, Inc. v. Western Surety Co.
149 A.3d 778 (Court of Special Appeals of Maryland, 2016)
Granite Re Inc. v. Jay Mills Contracting Inc.
Court of Appeals of Texas, 2015
Great American Insurance v. Hinkle Contracting Corp.
826 F. Supp. 2d 969 (S.D. West Virginia, 2011)