Granite Re Inc. v. Jay Mills Contracting Inc.

Court of Appeals of Texas·Decided April 23, 2015·No. 02-14-00357-CV·Published

Opinion

COURT OF APPEALS

SECOND DISTRICT OF TEXAS

FORT WORTH

NO. 02-14-00357-CV

GRANITE RE INC. APPELLANT V.

JAY MILLS CONTRACTING INC. APPELLEE

----------

FROM THE 355TH DISTRICT COURT OF HOOD COUNTY TRIAL COURT NO. C2014036

----------

MEMORANDUM OPINION 1 ON REHEARING ----------

On April 10, 2015, appellant Granite Re Inc. (Granite) filed a motion for rehearing directed to our March 26, 2015 memorandum opinion and judgment. We deny the motion for rehearing but withdraw our prior opinion and judgment and substitute the following. See Tex. R. App. P. 49.3.

1 See Tex. R. App. P. 47.4.

Granite appeals from the trial court’s order denying its motion to compel arbitration. We reverse the trial court’s order and remand for entry of an order compelling arbitration.

I. BACKGROUND

A. UNDERLYING AGREEMENTS

The City of Granbury (the city) hired appellee Jay Mills Contracting, Inc.

(JMC) to design and build a recreational boardwalk, boat dock, and fishing dock (the project). JMC then subcontracted with North American Marine Industries (NAMI) to perform the required work. JMC and NAMI entered into a “Blanket Agreement . . . between the Contractor and the Design/Build Subcontractor” (the blanket agreement). NAMI signed the blanket agreement on June 19, 2012, and JMC signed it on June 28, 2012. The blanket agreement included an arbitration clause, which provided that “all claims, disputes and controversies arising out of or relating to this Blanket Agreement and any Work Orders issued hereunder, including claims for extra work or changed conditions to or related to the Subcontract Work, shall be decided by arbitration.” The arbitration clause further stated that the “claimant” in any such arbitration proceeding could be either “the Contractor”—JMC—or the “Design/Build Subcontractor”—NAMI. Similarly, the blanket agreement provided that “[n]othing contained in this Blanket Agreement shall create a contractual relationship with, or create a cause of action in favor of, a third party which is neither the Contractor [JMC] nor Design/Build Subcontractor [NAMI]. [JMC] and [NAMI] agree that there are no third party

beneficiaries to the Blanket Agreement.” The blanket agreement further provided that NAMI would furnish a performance bond “in a form satisfactory to [JMC],” if JMC required such a bond. It is uncontradicted that JMC required NAMI to furnish a performance bond.

On the same dates that JMC and NAMI signed the blanket agreement, they also signed a “Work Order to Blanket Agreement” (the work order), incorporating the terms of the blanket agreement. The work order required NAMI to “provide bonding for the project for an additional $8,730.00.” On June 21, 2012—before JMC signed the blanket agreement and work order but after NAMI did so—NAMI executed a performance bond, with Granite acting as the surety, in the amount of $291,719. 2 The performance bond stated that the work order between JMC and NAMI was “incorporated by reference and made a part of this [performance bond] for all purposes.”

B. UNDERLYING DISPUTE 3

JMC alleged that by October 2012, NAMI had abandoned the project, defaulted on the blanket agreement and work order, and “clos[ed] shop.” On

2 The performance bond was not a statutory performance bond because it was not executed by JMC as the city’s contractor. See Tex. Gov’t Code Ann. § 2253.021 (West Supp. 2014).

3 Our factual statements regarding the parties’ underlying dispute merely provide context for our discussion of the enforceability of the arbitration clause at issue and, of course, are not a comment on the merits of JMC’s claims, the merits of Granite’s defenses to those claims, or the legal import of the contracts between JMC and NAMI. Indeed, these issues are not before us in this appeal.

March 10, 2014, JMC sued NAMI and Granite, as NAMI’s surety, for breach of contract—the blanket agreement, the work order, and the performance bond— and sought damages arising from JMC’s efforts to complete the project and from JMC’s settlement of the city’s claims against it. JMC’s breach-of-contract claim against Granite solely encompassed Granite’s alleged breach of the performance bond, not any breach of the blanket agreement or the work order. At some point in 2014, NAMI filed for bankruptcy protection. After the bankruptcy court granted NAMI a discharge, JMC filed a notice of nonsuit as to its claims against NAMI, and the trial court entered a dismissal order as to those claims. See Tex. R. Civ. P. 162; Epps v. Fowler, 351 S.W.3d 862, 868 (Tex. 2011).

Granite then filed a motion to compel arbitration under the arbitration clause contained in the blanket agreement, arguing that the clause in the blanket agreement was incorporated into the performance bond through the work order. Thus, Granite argued that the performance bond incorporated the valid arbitration clause and that JMC’s claims fell within the scope of the clause. Granite’s argument was analogous to the children’s song “There Was an Old Lady Who Swallowed a Fly”: Because the work order swallowed the performance bond and the blanket agreement swallowed the work order, the blanket agreement necessarily swallowed the performance bond contained in the work order. 4

4 This is shown by Granite’s argument that “[JMC] does have an enforceable arbitration agreement with [Granite] by virtue of the Bond, which

Granite also asserted that even if the arbitration clause in the blanket agreement could not be found to have been incorporated into the performance bond such that it applied to JMC’s claims against Granite, JMC’s claims were subject to the arbitration clause based on direct-benefits estoppel and JMC’s status as a third-party beneficiary of the performance bond. In other words, Granite argued that if the performance bond that Granite signed was not incorporated into the blanket agreement such that the performance bond did not contain an arbitration clause, Granite could enforce the clause against JMC under equitable-estoppel theories. 5 JMC responded that the performance bond did not contain an arbitration clause and that even if the performance bond were deemed to include an arbitration clause, its indemnity claim against Granite did not fall within the clause’s scope.

After holding a nonevidentiary hearing, the trial court denied Granite’s motion to compel without entering findings of fact or conclusions of law. Granite filed an accelerated appeal and argues that the trial court erred by denying its motion because a valid arbitration clause existed that governed JMC’s claims.

incorporates the Work Order, which incorporates the Blanket Agreement, which contains an arbitration agreement.”

5 At the hearing on Granite’s motion, Granite stated that its “argument is you can’t have the breach of contract claim under the performance bond, which incorporates the work order, which incorporates the blanket agreement, without taking out all subject to the arbitration. . . . The entire concept of incorporation by reference, the doctrine of equitable estoppel . . . all come into play when [JMC] can’t sue Granite based on the supposed default under a binding contract and escape the arbitration clause.”

See Tex. Civ. Prac. & Rem. Code Ann. § 51.016 (West 2015) (allowing interlocutory appeal from denial of motion to compel arbitration under the FAA).

In its motion to compel, Granite asserted the Federal Arbitration Act applied “because the parties have engaged in interstate commerce.” See 9 U.S.C.A. § 2 (West 2009) (providing FAA governs contracts relating to interstate commerce). JMC did not object to the application of the FAA and the only argument raised in the trial court was that the FAA applied; thus, we apply the FAA. See IKON Office Solutions, Inc. v. Eifert, 2 S.W.3d 688, 696 (Tex. App.—Houston [14th Dist.] 1999, orig. proceeding & no pet.) (holding burden is on party seeking to compel arbitration to show FAA applies).

Free access — add to your briefcase to read the full text and ask questions with AI

Granite Re Inc. v. Jay Mills Contracting Inc., (Tex. Ct. App. 2015).

Granite Re Inc. v. Jay Mills Contracting Inc. (Granite Re Inc. v. Jay Mills Contracting Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

J.M. Davidson, Inc. v. Webster
128 S.W.3d 223 (Texas Supreme Court, 2003)
In Re Kellogg Brown & Root, Inc.
166 S.W.3d 732 (Texas Supreme Court, 2005)
In Re Poly-America, L.P.
262 S.W.3d 337 (Texas Supreme Court, 2008)
In Re NEXT Financial Group, Inc.
271 S.W.3d 263 (Texas Supreme Court, 2008)
In Re Labatt Food Service, L.P.
279 S.W.3d 640 (Texas Supreme Court, 2009)
Chrysler Insurance Co. v. Greenspoint Dodge of Houston, Inc.
297 S.W.3d 248 (Texas Supreme Court, 2009)
Epps v. Fowler
351 S.W.3d 862 (Texas Supreme Court, 2011)
Hal Rachal, Jr. v. John W. Reitz
403 S.W.3d 840 (Texas Supreme Court, 2013)
Associated Glass, Ltd. v. Eye Ten Oaks Investments, Ltd.
147 S.W.3d 507 (Court of Appeals of Texas, 2004)
In Re Weeks Marine, Inc.
242 S.W.3d 849 (Court of Appeals of Texas, 2007)
Cappadonna Electrical Management v. Cameron County
180 S.W.3d 364 (Court of Appeals of Texas, 2005)
Ikon Office Solutions, Inc. v. Eifert
2 S.W.3d 688 (Court of Appeals of Texas, 1999)
Gloucester City v. AM. ARBITRATION ASS'N.
755 A.2d 1256 (New Jersey Superior Court App Division, 2000)
Teal Construction Co. v. Darren Casey Interests, Inc.
46 S.W.3d 417 (Court of Appeals of Texas, 2001)
Owen v. Hendricks
433 S.W.2d 164 (Texas Supreme Court, 1968)