United States of America f/u/b/o/ McCorvey Sheet Metal Works, L.P. v. Travelers Casualty and Surety Company of America

CourtDistrict Court, D. Maryland
DecidedJune 10, 2024
Docket8:22-cv-02789
StatusUnknown

This text of United States of America f/u/b/o/ McCorvey Sheet Metal Works, L.P. v. Travelers Casualty and Surety Company of America (United States of America f/u/b/o/ McCorvey Sheet Metal Works, L.P. v. Travelers Casualty and Surety Company of America) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America f/u/b/o/ McCorvey Sheet Metal Works, L.P. v. Travelers Casualty and Surety Company of America, (D. Md. 2024).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND

UNITED STATES OF AMERICA f/u/b/o * MCCORVEY SHEET METAL WORKS, L.P., *

Plaintiff, *

v. * Civ. No. DLB-22-2789

TRAVELERS CASUALTY AND SURETY * COMPANY OF AMERICA, et al., * Defendants. *

* * * * * * * * * * * * *

TRAVELERS CASUALTY AND SURETY * COMPANY OF AMERICA, et al., * Third-Party Plaintiffs, * v. * KDB MECHANICAL LLC f/k/a KIRLIN DESIGN BUILD, LLC, *

Third-Party Defendant. *

* CLARK CONSTRUCTION GROUP, LLC, * Cross-Claimant/Counter Defendant, * v. * KDB MECHANICAL LLC f/k/a KIRLIN DESIGN BUILD, LLC, *

Crossclaim Defendant/Counterclaimant. * MEMORANDUM OPINION In the last round of this Miller Act dispute over a construction project in Maryland, the Court granted the motion of cross-claimant Clark Construction Group, LLC (“Clark”) to dismiss the counterclaim of crossclaim defendant Kirlin Design Build, LLC (“Kirlin”), who had claimed

Clark breached their subcontract. ECF 101. Now, Kirlin has moved to file an amended answer and counterclaim to revive its breach of contract claim against Clark and add an additional claim under the Maryland Prompt Payment Act (“MPPA”), Md. Code Ann., Real Prop. §§ 9-301 et seq. ECF 121. The motion is fully briefed. ECF 121, 122, 142, 152, 156-1, 158. No hearing is necessary. See Loc. R. 105.6. For the reasons below, the Court grants, in part, Kirlin’s motion for leave to file an amended answer and counterclaim. I. Background In 2016, the United States contracted with Clark for the design and construction of a building at Ft. Meade in Maryland. ECF 122, ¶ 7. The Miller Act, 41 U.S.C. §§ 3131 et seq., required Clark, as the prime contractor on a federal project of this scale, to execute a payment bond

to the United States to guarantee that the subcontractors and suppliers would get paid. ECF 43, ¶¶ 8, 9. To that end, Clark executed a payment bond for $616,311,000 with Travelers Casualty and Surety Company of America, Federal Insurance Company, Federal and Deposit Company of Maryland, Zurich American Insurance Company, and Travelers Casualty and Surety Company (“the sureties”). Id. ¶ 8. Later that year, Clark executed a first-tier subcontract with Kirlin Mid-Atlantic, LLC for the design and installation of the project’s mechanical, plumbing, and fire protection systems. ECF 122, ¶ 8. Kirlin Mid-Atlantic then assigned the subcontract to Kirlin. Id. ¶ 9. On January 1, 2018, Kirlin executed a second-tier subcontract with McCorvey Sheet Metal Works, L.P. (“McCorvey”) for the fabrication and installation of the mechanical ductwork. ECF 43, ¶ 16. A few years later—with the project running behind schedule and over-budget—McCorvey filed this Miller Act suit against the sureties, seeking compensation for a variety of increased costs

for which McCorvey allegedly has not been paid. Id. ¶ 36. In response, the sureties filed a third- party complaint against Kirlin, asserting that Kirlin had agreed to indemnify them against McCorvey’s claims. ECF 23 (original) & 45 (amended). McCorvey, in turn, amended its complaint to name Clark as an additional defendant. ECF 43. Clark then filed crossclaims against Kirlin, alleging that Kirlin had agreed to indemnify Clark, too, and blaming Kirlin for the project’s woes. ECF 65. Closing the loop, Kirlin moved to dismiss Clark’s crossclaims and filed a counterclaim against Clark for breach of contract. ECF 83. Clark moved to dismiss Kirlin’s counterclaim. ECF 86. The Court denied Kirlin’s motion to dismiss Clark’s crossclaims and granted Clark’s motion to dismiss Kirlin’s counterclaim without prejudice. ECF 101.

Now, Kirlin has moved for leave to file an amended answer and counterclaim against Clark for breach of contract. ECF 121. Clark filed an opposition. ECF 142. Kirlin replied. ECF 152. Clark also moved for leave to file a surreply. ECF 156.1

1 The Court will grant Clark’s motion for leave to file a surreply. Although surreplies are generally impermissible, they are permissible when “the moving party would be unable to contest matters presented to the court for the first time in the opposing party’s reply.” See Khoury v. Meserve, 268 F. Supp. 2d 600, 605–06 (D. Md. 2003) (citing Lewis v. Rumsfeld, 154 F. Supp. 2d 56, 61 (D.D.C. 2001)). That is the case here. Kirlin’s motion for leave to file the proposed amended counterclaim featured almost no argument at all. See ECF 121, at 2–4. As a result, Clark had no opportunity in its opposition to address any of the arguments Kirlin later made in its reply. Several provisions of the subcontract between Clark and Kirlin that were relevant to Clark’s motion to dismiss Kirlin’s original counterclaim remain relevant now. Presenting them in the order in which they appear in the subcontract, the first is § 4(j): At any time all monies due Clark from the Owner[2] are not paid because of Owner withholding, Clark will, in its sole discretion, apportion the nonpayment equitably and reduce the payments otherwise due Subcontractor accordingly. However, if the withholdings are identified by the Owner as due to the undisputed fault of Clark or other subcontractors and not involving Subcontractor, then Clark shall pay Subcontractor amounts otherwise due hereunder. Subcontractor agrees that it relies for payment for all work performed pursuant to this Subcontract on the credit and ability to pay of the Owner, and not that of Clark, and Subcontractor agrees that payment by the Owner to Clark for work performed by the Subcontractor or its lower-tier subcontractors is a condition precedent to any payment obligation of Clark to Subcontractor. Subcontractor agrees that the liability of Clark’s sureties on any bond for payment to Subcontractor is subject to the same conditions precedent as are applicable to Clark’s liability to Subcontractor. The conditions precedent described in this paragraph shall not apply if the Owner’s non-payment is due to the undisputed fault of Clark or its other subcontractors or suppliers.

ECF 83-1, at 3 § 4(j), 45–47 (amendments).3 The second is § 8(a): Subcontractor will proceed with the work in a prompt and diligent manner, in accordance with Clark’s schedules as reasonably amended from time to time. Subcontractor shall be liable to Clark for failure to adhere to Clark’s schedules including amendments even if such schedules differ from schedules set forth in the Contract Documents or the time of completion called for by the Contract Documents.

Id. at 4 § 8(a), 45–47 (amendments). The third is § 8(d): Subcontractor shall be entitled to additional compensation for compliance with schedule amendments or damages for delay only to the extent the Contract Documents entitle Clark to damages from the Owner or other third parties or to a contract adjustment increasing the price or Guaranteed Maximum Cost of the contract between Clark and Owner.

Id. at 4 § 8(d), 45–47 (amendments). The fourth is § 9(b):

2 Throughout the subcontract, “Owner” refers to the United States. ECF 83-1, at 2. 3 Kirlin attached the complete subcontract to its original answer and counterclaim. ECF 83-1. Kirlin has not reattached the subcontract to its proposed amended answer and counterclaim, but the Court may consider it anyway. See Loc. R. 103.6 (amended pleadings need not include original attachments). Subcontractor shall submit to Clark any requests or claims for adjustment in the price, schedule or other provisions of the Subcontract for changes directed by the Owner, as a result of deficiencies or discrepancies in the Contract Documents, or for circumstances otherwise permitted by the Contract Documents.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Aaron Tobey v. Terri Jones
706 F.3d 379 (Fourth Circuit, 2013)
Goodman v. Praxair, Inc.
494 F.3d 458 (Fourth Circuit, 2007)
Lazorcak v. Feuerstein
327 A.2d 477 (Court of Appeals of Maryland, 1974)
Continental Masonry Co. v. Verdel Construction Co.
369 A.2d 566 (Court of Appeals of Maryland, 1977)
Taylor v. NationsBank, N.A.
776 A.2d 645 (Court of Appeals of Maryland, 2001)
State Highway Administration v. Greiner Engineering Sciences, Inc.
577 A.2d 363 (Court of Special Appeals of Maryland, 1990)
Polek v. J.P. Morgan Chase Bank, N.A.
36 A.3d 399 (Court of Appeals of Maryland, 2012)
Rogers Refrigeration Co. v. Pulliam's Garage, Inc.
505 A.2d 878 (Court of Special Appeals of Maryland, 1986)
Lewis v. Rumsfeld
154 F. Supp. 2d 56 (District of Columbia, 2001)
Khoury v. Meserve
268 F. Supp. 2d 600 (D. Maryland, 2003)
Moore Brothers Co v. Brown & Root Inc
207 F.3d 717 (Fourth Circuit, 2000)
Gordon Goines v. Valley Community Services Board
822 F.3d 159 (Fourth Circuit, 2016)
United States v. Justin Hawley
919 F.3d 252 (Fourth Circuit, 2019)
Robert Turner v. Al Thomas, Jr.
930 F.3d 640 (Fourth Circuit, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
United States of America f/u/b/o/ McCorvey Sheet Metal Works, L.P. v. Travelers Casualty and Surety Company of America, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-fubo-mccorvey-sheet-metal-works-lp-v-mdd-2024.