United States of America f/u/b/o/ McCorvey Sheet Metal Works, L.P. v. Travelers Casualty and Surety Company of America

District Court, D. Maryland·Decided December 20, 2023·No. 8:22-cv-02789·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF MARYLAND

UNITED STATES OF AMERICA f/u/b/o * MCCORVEY SHEET METAL WORKS, L.P., *

Plaintiff, *

v. * Civ. No. DLB-22-2789

TRAVELERS CASUALTY AND SURETY * COMPANY OF AMERICA, et al., * Defendants. *

* * * * * * * * * * * * *

TRAVELERS CASUALTY AND SURETY * COMPANY OF AMERICA, et al., * Third-Party Plaintiffs, * v. * KDB Mechanical LLC f/k/a KIRLIN DESIGN BUILD, LLC, *

Third-Party Defendant. *

* * * * * * * * * * * * *

* CLARK CONSTRUCTION GROUP, LLC, * Cross-Claimant/Counter Defendant, * v. * KDB Mechanical LLC f/k/a KIRLIN DESIGN BUILD, LLC, *

Crossclaim Defendant/Counterclaimant. * MEMORANDUM OPINION In the latest phase of this Miller Act dispute over a construction project in Maryland, crossclaim defendant Kirlin Design Build, LLC (“Kirlin”) counterclaims that cross-claimant Clark Construction Group, LLC (“Clark”) breached their subcontract. ECF 83. Clark moves to dismiss

Kirlin’s counterclaim. ECF 86. The matter is fully briefed. ECF 86-1, 87, 88. No hearing is necessary. See Loc. R. 105.6. For the reasons below, the Court grants Clark’s motion to dismiss. I. Background In 2016, the United States contracted with Clark for the design and construction of a building at Ft. Meade in Maryland. ECF 83, ¶ 7. The Miller Act, 41 U.S.C. § 3131 et. seq., required Clark, as the prime contractor on a federal project of this scale, to execute a payment bond to the United States to guarantee that the subcontractors and suppliers would get paid. ECF 43, ¶¶ 8, 9. To that end, Clark executed a payment bond for $616,311,000 with Travelers Casualty and Surety Company of America, Federal Insurance Company, Federal and Deposit Company of Maryland, Zurich American Insurance Company, and Travelers Casualty and Surety Company

(“the sureties”). Id. ¶ 8. Later that year, Clark executed a first-tier subcontract with Kirlin Mid-Atlantic, LLC for the design and installation of the project’s mechanical, plumbing, and fire protection systems. ECF 83, ¶ 8. Kirlin Mid-Atlantic then assigned the subcontract to Kirlin. Id. ¶ 9. On January 1, 2018, Kirlin executed a second-tier subcontract with McCorvey Sheet Metal Works, L.P. (“McCorvey”) for the fabrication and installation of the mechanical ductwork. ECF 43, ¶ 16. A few years later—with the project running behind schedule and over-budget—McCorvey filed this Miller Act suit against the sureties, seeking compensation for a variety of increased costs for which McCorvey allegedly has not been paid. Id. ¶ 36. In response, the sureties filed a third- party complaint against Kirlin, asserting that Kirlin had agreed to indemnify them against McCorvey’s claims. ECF 23 (original) & 45 (amended). McCorvey, in turn, amended its complaint to name Clark as an additional defendant. ECF 43. Clark then filed crossclaims against Kirlin, alleging that Kirlin had agreed to indemnify Clark, too, and blaming Kirlin for the project’s

woes. ECF 65. Closing the loop, Kirlin moved to dismiss Clark’s crossclaims and filed a counterclaim against Clark for breach of contract. ECF 83. According to Kirlin, Clark is the one at fault. Clark allegedly failed to provide reasonable schedules for the completion of the project. Id. at 25–27. Clark allegedly provided defective designs and repeatedly changed them. Id. at 27–28. And Clark allegedly failed to compensate Kirlin timely and fully, both for the original contract work and for the additional work Kirlin did to make up for Clark’s deviations from the original plans. Id. at 30. For those alleged breaches of the subcontract, Kirlin requested at least $46,743,342.00 in damages: $2,187,028.18 for the original contract work, $7,668,846.00 for the change work, and the remaining money for the schedule amendments and other delays. Id. at 30 ¶¶ 34–35; id. at 31 ¶ 39.

Clark moved to dismiss Kirlin’s counterclaim under Fed. R. Civ. P. 12(b)(6) for failure to state a claim. ECF 86. Kirlin opposed the motion. ECF 87. Clark replied. ECF 88. Several provisions of the subcontract between Clark and Kirlin are particularly relevant to the dispute over Clark’s crossclaims and Kirlin’s counterclaim. Presenting them in the order in which they appear in the subcontract, the first is § 4(j): At any time all monies due Clark from the Owner1 are not paid because of Owner withholding, Clark will, in its sole discretion, apportion the nonpayment equitably and reduce the payments otherwise due Subcontractor accordingly. However, if the withholdings are identified by the Owner as due to the undisputed fault of Clark or other subcontractors and not involving Subcontractor, then Clark shall pay Subcontractor amounts otherwise due hereunder. Subcontractor agrees that it relies

1 Throughout the subcontract, “Owner” refers to the United States. ECF 83-1, at 2. for payment for all work performed pursuant to this Subcontract on the credit and ability to pay of the Owner, and not that of Clark, and Subcontractor agrees that payment by the Owner to Clark for work performed by the Subcontractor or its lower-tier subcontractors is a condition precedent to any payment obligation of Clark to Subcontractor. Subcontractor agrees that the liability of Clark’s sureties on any bond for payment to Subcontractor is subject to the same conditions precedent as are applicable to Clark’s liability to Subcontractor. The conditions precedent described in this paragraph shall not apply if the Owner’s non-payment is due to the undisputed fault of Clark or its other subcontractors or suppliers.

ECF 83-1, at 3 § 4(j), 45–47 (amendments). The second is § 8(a): Subcontractor will proceed with the work in a prompt and diligent manner, in accordance with Clark’s schedules as reasonably amended from time to time. Subcontractor shall be liable to Clark for failure to adhere to Clark’s schedules including amendments even if such schedules differ from schedules set forth in the Contract Documents or the time of completion called for by the Contract Documents.

Id. at 4 § 8(a), 45–47 (amendments). The third is § 8(d): Subcontractor shall be entitled to additional compensation for compliance with schedule amendments or damages for delay only to the extent the Contract Documents entitle Clark to damages from the Owner or other third parties or to a contract adjustment increasing the price or Guaranteed Maximum Cost of the contract between Clark and Owner.

Id. at 4 § 8(d), 45–47 (amendments). The fourth is § 9(b): Subcontractor shall submit to Clark any requests or claims for adjustment in the price, schedule or other provisions of the Subcontract for changes directed by the Owner, as a result of deficiencies or discrepancies in the Contract Documents, or for circumstances otherwise permitted by the Contract Documents. Said requests or claims shall be submitted in writing by Subcontractor in time to allow Clark to comply with the applicable provisions of the Contract Documents.

Free access — add to your briefcase to read the full text and ask questions with AI

United States of America f/u/b/o/ McCorvey Sheet Metal Works, L.P. v. Travelers Casualty and Surety Company of America, (D. Md. 2023).

United States of America f/u/b/o/ McCorvey Sheet Metal Works, L.P. v. Travelers Casualty and Surety Company of America (United States of America f/u/b/o/ McCorvey Sheet Metal Works, L.P. v. Travelers Casualty and Surety Company of America) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Aaron Tobey v. Terri Jones
706 F.3d 379 (Fourth Circuit, 2013)
Continental Masonry Co. v. Verdel Construction Co.
369 A.2d 566 (Court of Appeals of Maryland, 1977)
State Highway Administration v. Greiner Engineering Sciences, Inc.
577 A.2d 363 (Court of Special Appeals of Maryland, 1990)
Polek v. J.P. Morgan Chase Bank, N.A.
36 A.3d 399 (Court of Appeals of Maryland, 2012)
Gordon Goines v. Valley Community Services Board
822 F.3d 159 (Fourth Circuit, 2016)
Birmingham v. PNC Bank, N.A. (In Re Birmingham)
846 F.3d 88 (Fourth Circuit, 2017)
Robert Turner v. Al Thomas, Jr.
930 F.3d 640 (Fourth Circuit, 2019)
Tina Ray v. Michael Roane
948 F.3d 222 (Fourth Circuit, 2020)
Svetlana Lokhova v. Stefan Halper
995 F.3d 134 (Fourth Circuit, 2021)
United States ex rel. Kitchens to Go v. John C. Grimberg Co.
283 F. Supp. 3d 476 (E.D. Virginia, 2017)