6 THE DISTRICT COURT OF GUAM
8 UNITED STATES OF AMERICA, for the use CIVIL CASE NO. 17-00074 of JWS RERIGERATION & AIR 9 CONDITIONING, LTD.,
10 Plaintiff, DECISION AND ORDER ON OBJECTIONS TO 11 vs. MAGISTRATE JUDGE’S REPORT AND RECOMMENDATION 12 FIDELITY AND DEPOSIT COMPANY OF MARYLAND, 13 and 14
15 P & S CONSTRUCTION, INC.
16 Defendants.
Before the court is Defendant P & S Construction, Inc.’s (“P&S”) Objection to 18 Magistrate Judge Joaquin Manibusan, Jr.’s Report and Recommendation (“Report”). See ECF 19 No. 43. Appearing on behalf of the Plaintiffs were Ms. Joyce C.H. Tang and Ms. Leslie Anne 20 Travis. Appearing on behalf of the Defendants were Minakshi V. Hemlani and Mr. Eric N. 21 Heyer. After careful consideration and after having reviewed the parties’ briefs, relevant cases 22 and statutes, and having heard argument from counsel on the matter on November 26, 2018, the 23 24 1 court hereby ACCEPTS in part and REJECTS in part the conclusions within the Report for the 2 reasons stated herein. 3 I. BACKGROUND 4 A. Facts
5 In 2014, P&S entered into a contract with the United States Government to upgrade the 6 HVAC system in Building 18002 at Andersen Air Force Base. See R. & R. at 2, ECF No. 38. 7 P&S as principal and Fidelity and Deposit Company of Maryland (“Fidelity”) as surety furnished 8 the United States with a payment bond in the amount of $3,412,700. Id. 9 P&S then subcontracted JWS Refrigeration and Air Conditioning, Ltd. (“JWS”) 10 to provide materials, labor, and equipment for the project. Id. Article 19.1 of that Subcontract 11 provides: 12 Subcontractor agrees that any and all claims or disputes arising out of or relating to this Agreement or the breach thereof shall be decided, at the sole discretion of 13 Contractor, by submission to (1) arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association in a venue 14 selected solely by Contractor or (2) judicial decision by the Middlesex County Superior Court in the Commonwealth of Massachusetts . . . 15 Subcontract at art. 19.1, ECF No. 1-3. 16 Following a dispute, P&S terminated JWS and refused to pay money that JWS claims it 17 is due. R. & R. at 3, ECF No. 38. 18 B. Procedural History 19 JWS initiated the present suit on June 28, 2017. Compl., ECF No. 1. JWS alleged four causes 20 of action: (1) a Miller Act bond claim against Fidelity, id. at 6-7, (2) a breach of contract claim 21 against P&S for failure to pay, id. at 7-8, (3) a breach of contract claim against P&S for wrongful 22 termination, id. at 8, and (4) a quantum merit claim against P&S, id. 23 On July 18, 2017, P&S and Fidelity (collectively, “Defendants”) moved to dismiss the 24 complaint, or, alternatively, to stay this case pending the completion of arbitration. Mot. Dismiss 1 or, Alternatively, to Stay, ECF No. 5. Defendants argued this court lacks subject matter 2 jurisdiction to entertain this dispute because P&S and JWS agreed to arbitrate “any and all 3 claims or disputes arising out of or relating to” the Subcontract. Id. at 13. Defendants further 4 argued that the interests of judicial economy weigh strongly in favor of a stay, because the 5 parties are currently arbitrating a similar dispute in Boston and this case should be litigated at the 6 same venue. ECF No. 5-1, at 16. 7 In opposition, JWS argued that the Subcontract’s arbitration clause is unconscionable. 8 Opp. at 5, ECF No. 10. In the alternative, JWS argued that even if its claims against P&S are
9 subject to arbitration, its Miller Act claim against Fidelity is not. Id. at 15. Finally, JWS cross- 10 moved to compel arbitration in Guam. Id. at 19. 11 In their reply, Defendants rebutted JWS’s arguments related to the motion to stay and 12 argued that compelling arbitration in Guam would amount to a judicial rewrite of the 13 Subcontract’s arbitration clause. Reply at 12, ECF No. 14. JWS subsequently filed a reply in 14 support of its cross-motion to compel arbitration in Guam. Reply, ECF No. 17. 15 The Magistrate Judge held a hearing on Defendants’ motion to dismiss or alternatively to 16 stay. See ECF No. 26. At that hearing, the Magistrate Judge raised the issue that Defendants may 17 have waived the arbitration clause by failing to initiate arbitration proceedings prior to filing 18 their motion to dismiss or stay this case. Trscpt. at 75, 139, ECF No. 41. To address that issue,
19 the Magistrate Judge permitted the parties to submit a Supplemental Statement of Facts. Id. at 20 143; see also P&S’s Supp. Statement of Facts & Procedural History, ECF No.27; JWS’s Supp. 21 Statement of Facts and Procedural History, ECF No. 30. 22 On March 3, 2018, the Magistrate Judge issued his Report. R. & R., ECF No. 38. The 23 Magistrate Judge found that P&S was in default in seeking arbitration. R. & R. at 9, ECF No. 38. 24 However, because JWS consented to arbitration proceedings so long as they were held in Guam, 1 the Magistrate Judge recommended this court grant Defendants’ motion to stay the proceedings 2 but also grant Plaintiff’s cross-motion to compel arbitration in Guam. Id. 3 Defendants object to that Report on three grounds. Obj. to Report, ECF No. 43. They 4 argue that (1) they did not waive the Subcontract’s arbitration clause, (2) JWS waived its right to 5 compel arbitration in Guam, and (3) JWS’s claims in this action are “inextricably intertwined” 6 with its claims in a separate arbitration proceeding between JWS and P&S. Id. at 4. 7 II. LEGAL STANDARDS 8 The parties disagree as to what standard of review this court should apply when 9 reviewing the Magistrate Judge’s Report. Defendants argue for de novo review pursuant to 28 10 U.S.C. § 636(b)(1)(A). Opp. at 5, ECF No. 43. JWS, by contrast, notes that a magistrate judge’s 11 report on nondispositive motions is reviewed under the clearly erroneous standard. Response at 12 2-6, ECF No. 46 (citing FRCP 72(a)). Thus, while JWS agrees that the Magistrate Judge’s 13 recommendation as to Defendants’ motion to dismiss should be reviewed de novo, JWS argues 14 that the Report’s recommendation as to Defendants’ alternative motion to stay should be 15 reviewed for clear error. Id. at 4 (citing Powershare Inc. v. Syntel, Inc., 597 F.3d 10, 14 (1st Cir. 16 2010) (“A federal court’s ruling on a motion to stay litigation pending arbitration is not 17 dispositive of either the case or any claim or defense within it.”)). 18 JWS has cited no case in which a district court has applied different standards of review 19 to the same Report. Nor has this court found any such case. More importantly, this court referred 20 Defendants’ motion in its entirety to the Magistrate Judge, pursuant to 28 U.S.C. § 636(b)(1)(B). 21 See Order, ECF No. 8. This court’s order of referral did not differentiate the motion to dismiss 22 from the motion to stay. Absent that order of referral, this court would have directly ruled upon 23 Defendants’ motion. Therefore, it would be inappropriate for this court to apply anything less 24 than de novo review to the Magistrate Judge’s Report. Accordingly, this court proceeds with de 1 novo review. 2 III. DISCUSSION 3 A. Whether Defendants waived the arbitration provision 4 Defendants object to the Magistrate Judge’s conclusion that P&S “defaulted and waived 5 its rights under Section 3 of the FAA.” R. & R. at 8, ECF No. 38.
Free access — add to your briefcase to read the full text and ask questions with AI
6 THE DISTRICT COURT OF GUAM
8 UNITED STATES OF AMERICA, for the use CIVIL CASE NO. 17-00074 of JWS RERIGERATION & AIR 9 CONDITIONING, LTD.,
10 Plaintiff, DECISION AND ORDER ON OBJECTIONS TO 11 vs. MAGISTRATE JUDGE’S REPORT AND RECOMMENDATION 12 FIDELITY AND DEPOSIT COMPANY OF MARYLAND, 13 and 14
15 P & S CONSTRUCTION, INC.
16 Defendants.
Before the court is Defendant P & S Construction, Inc.’s (“P&S”) Objection to 18 Magistrate Judge Joaquin Manibusan, Jr.’s Report and Recommendation (“Report”). See ECF 19 No. 43. Appearing on behalf of the Plaintiffs were Ms. Joyce C.H. Tang and Ms. Leslie Anne 20 Travis. Appearing on behalf of the Defendants were Minakshi V. Hemlani and Mr. Eric N. 21 Heyer. After careful consideration and after having reviewed the parties’ briefs, relevant cases 22 and statutes, and having heard argument from counsel on the matter on November 26, 2018, the 23 24 1 court hereby ACCEPTS in part and REJECTS in part the conclusions within the Report for the 2 reasons stated herein. 3 I. BACKGROUND 4 A. Facts
5 In 2014, P&S entered into a contract with the United States Government to upgrade the 6 HVAC system in Building 18002 at Andersen Air Force Base. See R. & R. at 2, ECF No. 38. 7 P&S as principal and Fidelity and Deposit Company of Maryland (“Fidelity”) as surety furnished 8 the United States with a payment bond in the amount of $3,412,700. Id. 9 P&S then subcontracted JWS Refrigeration and Air Conditioning, Ltd. (“JWS”) 10 to provide materials, labor, and equipment for the project. Id. Article 19.1 of that Subcontract 11 provides: 12 Subcontractor agrees that any and all claims or disputes arising out of or relating to this Agreement or the breach thereof shall be decided, at the sole discretion of 13 Contractor, by submission to (1) arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association in a venue 14 selected solely by Contractor or (2) judicial decision by the Middlesex County Superior Court in the Commonwealth of Massachusetts . . . 15 Subcontract at art. 19.1, ECF No. 1-3. 16 Following a dispute, P&S terminated JWS and refused to pay money that JWS claims it 17 is due. R. & R. at 3, ECF No. 38. 18 B. Procedural History 19 JWS initiated the present suit on June 28, 2017. Compl., ECF No. 1. JWS alleged four causes 20 of action: (1) a Miller Act bond claim against Fidelity, id. at 6-7, (2) a breach of contract claim 21 against P&S for failure to pay, id. at 7-8, (3) a breach of contract claim against P&S for wrongful 22 termination, id. at 8, and (4) a quantum merit claim against P&S, id. 23 On July 18, 2017, P&S and Fidelity (collectively, “Defendants”) moved to dismiss the 24 complaint, or, alternatively, to stay this case pending the completion of arbitration. Mot. Dismiss 1 or, Alternatively, to Stay, ECF No. 5. Defendants argued this court lacks subject matter 2 jurisdiction to entertain this dispute because P&S and JWS agreed to arbitrate “any and all 3 claims or disputes arising out of or relating to” the Subcontract. Id. at 13. Defendants further 4 argued that the interests of judicial economy weigh strongly in favor of a stay, because the 5 parties are currently arbitrating a similar dispute in Boston and this case should be litigated at the 6 same venue. ECF No. 5-1, at 16. 7 In opposition, JWS argued that the Subcontract’s arbitration clause is unconscionable. 8 Opp. at 5, ECF No. 10. In the alternative, JWS argued that even if its claims against P&S are
9 subject to arbitration, its Miller Act claim against Fidelity is not. Id. at 15. Finally, JWS cross- 10 moved to compel arbitration in Guam. Id. at 19. 11 In their reply, Defendants rebutted JWS’s arguments related to the motion to stay and 12 argued that compelling arbitration in Guam would amount to a judicial rewrite of the 13 Subcontract’s arbitration clause. Reply at 12, ECF No. 14. JWS subsequently filed a reply in 14 support of its cross-motion to compel arbitration in Guam. Reply, ECF No. 17. 15 The Magistrate Judge held a hearing on Defendants’ motion to dismiss or alternatively to 16 stay. See ECF No. 26. At that hearing, the Magistrate Judge raised the issue that Defendants may 17 have waived the arbitration clause by failing to initiate arbitration proceedings prior to filing 18 their motion to dismiss or stay this case. Trscpt. at 75, 139, ECF No. 41. To address that issue,
19 the Magistrate Judge permitted the parties to submit a Supplemental Statement of Facts. Id. at 20 143; see also P&S’s Supp. Statement of Facts & Procedural History, ECF No.27; JWS’s Supp. 21 Statement of Facts and Procedural History, ECF No. 30. 22 On March 3, 2018, the Magistrate Judge issued his Report. R. & R., ECF No. 38. The 23 Magistrate Judge found that P&S was in default in seeking arbitration. R. & R. at 9, ECF No. 38. 24 However, because JWS consented to arbitration proceedings so long as they were held in Guam, 1 the Magistrate Judge recommended this court grant Defendants’ motion to stay the proceedings 2 but also grant Plaintiff’s cross-motion to compel arbitration in Guam. Id. 3 Defendants object to that Report on three grounds. Obj. to Report, ECF No. 43. They 4 argue that (1) they did not waive the Subcontract’s arbitration clause, (2) JWS waived its right to 5 compel arbitration in Guam, and (3) JWS’s claims in this action are “inextricably intertwined” 6 with its claims in a separate arbitration proceeding between JWS and P&S. Id. at 4. 7 II. LEGAL STANDARDS 8 The parties disagree as to what standard of review this court should apply when 9 reviewing the Magistrate Judge’s Report. Defendants argue for de novo review pursuant to 28 10 U.S.C. § 636(b)(1)(A). Opp. at 5, ECF No. 43. JWS, by contrast, notes that a magistrate judge’s 11 report on nondispositive motions is reviewed under the clearly erroneous standard. Response at 12 2-6, ECF No. 46 (citing FRCP 72(a)). Thus, while JWS agrees that the Magistrate Judge’s 13 recommendation as to Defendants’ motion to dismiss should be reviewed de novo, JWS argues 14 that the Report’s recommendation as to Defendants’ alternative motion to stay should be 15 reviewed for clear error. Id. at 4 (citing Powershare Inc. v. Syntel, Inc., 597 F.3d 10, 14 (1st Cir. 16 2010) (“A federal court’s ruling on a motion to stay litigation pending arbitration is not 17 dispositive of either the case or any claim or defense within it.”)). 18 JWS has cited no case in which a district court has applied different standards of review 19 to the same Report. Nor has this court found any such case. More importantly, this court referred 20 Defendants’ motion in its entirety to the Magistrate Judge, pursuant to 28 U.S.C. § 636(b)(1)(B). 21 See Order, ECF No. 8. This court’s order of referral did not differentiate the motion to dismiss 22 from the motion to stay. Absent that order of referral, this court would have directly ruled upon 23 Defendants’ motion. Therefore, it would be inappropriate for this court to apply anything less 24 than de novo review to the Magistrate Judge’s Report. Accordingly, this court proceeds with de 1 novo review. 2 III. DISCUSSION 3 A. Whether Defendants waived the arbitration provision 4 Defendants object to the Magistrate Judge’s conclusion that P&S “defaulted and waived 5 its rights under Section 3 of the FAA.” R. & R. at 8, ECF No. 38. Section 3 of the Federal 6 Arbitration Act (“FAA”) provides: 7 If any suit or proceeding be brought in any of the courts of the United States upon any issue referable to arbitration under an agreement in writing for such 8 arbitration, the court in which such suit is pending, upon being satisfied that the issue involved in such suit or proceeding is referable to arbitration under such an 9 agreement, shall on application of one of the parties stay the trial of the action until such arbitration has been had in accordance with the terms of the agreement, 10 providing the applicant for the stay is not in default in proceeding with such arbitration. 11 9 U.S.C. § 3. At issue is whether Defendants—“the applicant[s] for the stay”—are “in default in 12 proceeding with such arbitration.” Id. 13 “Waiver of a contractual right to arbitration is not favored.” Fisher v. A.G. Becker 14 Paribas Inc., 791 F.2d 691, 694 (9th Cir. 1986). “A party seeking to prove waiver of a right to 15 arbitration must demonstrate: (1) knowledge of an existing right to compel arbitration; (2) acts 16 inconsistent with that existing right; and (3) prejudice to the party opposing arbitration resulting 17 from such inconsistent acts.” Id. Here, there is no dispute that Defendants knew of the existing 18 right to compel arbitration. Obj. to Report at 6, ECF No. 43. 19 The primary issue is whether Defendants took actions inconsistent with their right to 20 arbitrate. The Magistrate Judge reasoned that P&S “waived its rights” to arbitrate “when it failed 21 to demand arbitration prior to [JWS]’s cross motion to compel arbitration in Guam.” R. & R. at 22 8, ECF No. 38. The Magistrate Judge reasoned that P&S should have commenced arbitration 23 months before JWS sued, that is, when the contractual dispute arose. Id. at 8. The Magistrate 24 Judge further found that P&S unreasonably delayed to initiate arbitration proceedings “[i]n the 1 interest of saving money.” Id. 2 “In determining whether a party was ‘diligent,’ courts ask whether the party seeking to 3 compel arbitration did ‘all it could reasonably have been expected to do to make the earliest 4 feasible determination of whether to proceed judicially or by arbitration.’” Skyline Restoration, 5 Inc. v. First Baptist Church, 2017 WL 6570077, at *1 (N.D. Ill. Dec. 21, 2017) (quoting 6 Cabinetree of Wisc., Inc. v. Kraftmaid Cabinetry, Inc., 50 F.3d 388, 391 (7th Cir. 1995)); see 7 also Zuckerman Spaeder, LLP v. Auffenberg, 646 F.3d 919, 922 (D.C. Cir. 2011) (“A party who 8 fails timely to invoke his right to arbitrate is necessarily in default when he later attempts to
9 proceed with arbitration under Section 3.”) (internal quotation marks omitted). 10 Defendants cite Sims v. Montell Chrysler, Inc., 317 F. Supp. 2d 838 (N.D. Ill. 2004), for 11 the proposition that a party may successfully seek a stay pending arbitration before commencing 12 arbitration proceedings. Obj. to Report at 7, ECF No. 43. In Sims, the plaintiff sued a defendant 13 for deception in connection with the sale of a car. 317 F. Supp. 2d at 839. As part of the sale 14 agreement, the parties had signed an arbitration agreement. Id. Citing that agreement, the 15 defendant moved for a stay pending arbitration. Id. The plaintiff objected, arguing that, at the 16 time the defendant moved to stay, the defendant had neither commenced arbitration proceedings 17 nor moved for an order compelling arbitration. Id. at 840. The Sims court disagreed with the 18 plaintiff’s position after analyzing circuit and Supreme Court precedent at length. Id. at 840-44.
19 The Sims court reasoned that “there is little reason to require than an arbitration be commenced 20 by a defendant against itself before a stay can be ordered.” Id. at 841. Thus, the court concluded, 21 the proper outcome was to grant the defendant’s motion for stay, allowing the plaintiff to 22 commence an arbitration proceeding, if it so chooses. Id. at 844. 23 JWS argues that the Subcontract’s arbitration provision in this case is meaningfully 24 different from the arbitration provision in Sims. Whereas the Sims arbitration provision 1 unequivocally provided that disputes would be resolved through arbitration, id. at 839, the 2 JWS/P&S Subcontract arbitration clause is more nuanced. The arbitration provision in this case 3 provides that claims arising out of this contract “shall be decided, at the sole discretion of 4 Contractor, by submission to” arbitration or to “judicial decision by the Middlesex County 5 Superior Court in the Commonwealth of Massachusetts.” Subcontract at art. 19.1, ECF No. 1-3 6 (emphasis added). That language, JWS asserts, means that only P&S—and not JWS—has the 7 right to file an arbitration demand. Response at 9, ECF No. 46. P&S does not dispute this 8 interpretation of article 19. See Reply at 3, ECF No. 14 (“[T]he agreement calls for decisions
9 solely by P&S regarding whether to litigate or arbitrate and to fix the locale of arbitration.”). 10 Therefore, JWS argues, if this court grants a stay pending arbitration, JWS will have no way to 11 pursue its claims against P&S. 12 JWS’s argument might have merit if there was evidence that P&S never intended to 13 initiate arbitration proceedings. A lack of intent to arbitrate this case could amount to bad faith, 14 as JWS claims. Response to Obj. at 15, ECF No. 46. But the undisputed fact is that P&S is 15 attempting to arbitrate this case. In an arbitration proceeding stemming from a separate (but 16 similar) subcontract between these parties, P&S amended the arbitration demand to include a 17 claim against JWS stemming from the Subcontract at issue in this case. Supp. at 5, ECF No. 27. 18 JWS answered that amended complaint and asserted its counterclaims against P&S. Id. at 6.
19 Thus, JWS’s claims notwithstanding, the evidence does not demonstrate that P&S acted in bad 20 faith by moving to stay before an arbitration proceeding was in place. Nor did it act in bad faith 21 by choosing Boston as the venue. Even assuming JWS is correct that arbitration would be more 22 efficient in Guam, see Response to Obj. at 23-24, ECF No. 46, P&S bargained for the right to 23 choose the venue. 24 This court finds that P&S did not take actions inconsistent with its right to arbitrate and 1 therefore, there is no prejudice to the opposing party. Twenty days after JWS filed its complaint, 2 Defendants moved to dismiss or stay this case. ECF No. 5. That time period does not constitute a 3 failure to timely invoke P&S’s right to arbitrate. See Zuckerman Spaeder, 646 F.3d at 922. 4 Therefore, Defendants are “not in default in proceeding with [ ] arbitration,” so this court must 5 “stay the trial of the action until such arbitration has been had in accordance with the terms of the 6 agreement.” 9 U.S.C. § 3. 7 B. Additional issues 8 Given the foregoing conclusion—that P&S did not default on the Subcontract’s
9 arbitration provision—this court must deny JWS’s motion to compel arbitration in Guam 10 pursuant to Section 4 of the FAA. That section only applies if JWS was “aggrieved by the 11 alleged failure, neglect, or refusal of [P&S] to arbitrate.” 9 U.S.C. § 4. But P&S has not failed to 12 arbitrate this matter, and JWS is not aggrieved. 13 This court need not address P&S’s alternative claim that the issues of this case are 14 inextricably intertwined with these parties’ separate arbitration proceeding such that the cases 15 must be combined. See Obj. to Report at 14, ECF No. 43. It is for the arbitrator—not this court— 16 to determine whether the two arbitration proceedings are properly joined. 17 Finally, this court considers whether JWS’s Miller Act claim against Fidelity is also 18 subject to the arbitration provision. Defendants cite abundant authority demonstrating that
19 “federal courts routinely stay Miller Act lawsuits pending arbitration to determine the 20 contractor’s liability.” United States ex. Rel. W. Ind’l, Inc. v. W. Surety Co., 2010 U.S. Dist. 21 LEXIS 88532, *7 (D. Alaska 2010); see also Mot. Dismiss Or, Alternatively, to Stay at 12-15, 22 ECF No. 5-1. Those decisions are grounded in the logic that “allowing litigation to proceed in 23 this suit alongside arbitration would disserve the ‘liberal federal policy favoring arbitration 24 agreements.’” United States f/u/b/o Milestone Tarant, LLC v. Fed. Ins. Co., 672 F. Supp. 2d 92, 1 102 (D.D.C. 2009) (citing Moses H. Cone Mem’l Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 24 2 (1983)). This court is unpersuaded by JWS’s argument that language within the Subcontract’s 3 arbitration provision distinguishes this case from the cases cited by P&S. JWS’s argument 4 notwithstanding, article 19.1’s explicit description of one situation in which a Miller Act claim 5 will be stayed does not imply that the parties intended that to be the only situation in which a 6 Miller Act claim would be stayed. See Opp. at 16-17, ECF No. 10. This court finds no language 7 within the Subcontract that would indicate an intent for Miller Act claims to be exempt from 8 arbitration; rather, article 19.1 explicitly covers “all claims or disputes arising of or relating to
9 this [Subcontract].” Thus, JWS’s Miller Act claim against Fidelity is likewise stayed pending 10 completion of arbitration. 11 IV. CONCLUSION 12 For the foregoing reasons, the court hereby ACCEPTS in part and REJECTS in part the 13 Magistrate Judge’s Report. Specifically, this court: 14 1. ACCEPTS the Report’s recommendation to deny P&S’s motion to dismiss1; 15 2. REJECTS the Report’s finding that P&S was in default in seeking arbitration; 16 3. ACCEPTS the Report’s recommendation to stay the proceedings pending arbitration; 17 4. REJECTS the Report’s recommendation to compel arbitration in Guam. 18 Therefore, IT IS HEREBY ORDERED that:
19 1. P&S’s Motion to Dismiss is DENIED. 20 2. P&S’s alternative Motion to Stay the proceedings pending completion of the 21 contractually mandated provision under article 19.1 of the JWS / P&S subcontract is 22 GRANTED. 23
24 1 The Report does not explicitly recommend that this court deny Defendants’ motion to dismiss. Nonetheless, in recommending this court grant Defendant’s alternative motion to stay, the Report implied that this court should not dismiss this case. 1 3. The parties shall file a joint status report no later than March 19, 2019, and every 2 || quarter thereafter. In addition, the parties shall appear for a status hearing before the Magistrate 3 || Judge on March 27, 2019, at 9:00 a.m. 4 SO ORDERED. 5 NG a /s/ Frances M. Tydingco-Gatewood 6 x rf J, Chief Judge ey [hy Dated: Dec 19, 2018 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24