United States of America for the Use and Benefit of Electric MacHinery Enterprises of Puerto Rico, Inc. v. Fraya, S.E. And Continental Insurance Co.

145 F.3d 1, 42 Cont. Cas. Fed. 77,304, 1998 U.S. App. LEXIS 10479, 1998 WL 250753
CourtCourt of Appeals for the First Circuit
DecidedMay 26, 1998
Docket97-1606
StatusPublished
Cited by38 cases

This text of 145 F.3d 1 (United States of America for the Use and Benefit of Electric MacHinery Enterprises of Puerto Rico, Inc. v. Fraya, S.E. And Continental Insurance Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America for the Use and Benefit of Electric MacHinery Enterprises of Puerto Rico, Inc. v. Fraya, S.E. And Continental Insurance Co., 145 F.3d 1, 42 Cont. Cas. Fed. 77,304, 1998 U.S. App. LEXIS 10479, 1998 WL 250753 (1st Cir. 1998).

Opinion

DiCLERICO, District Judge.

This action arises from a dispute between the plaintiff-appellant, Electric Machinery Enterprises of Puerto Rico, Inc. (“EME”), and the defendant-appellees, Fraya, S.E. (“Fraya”) and Continental Insurance Company (“CIC”), concerning a construction project for the ’ United States Navy. CIC filed a motion for summary judgment which the district court granted before EME filed its response. EME’s request for post-judgment relief was then denied. Because EME appears to have run afoul of a combination of factors, the most material of which is an ambiguity in the Local Rules of the United States District Court for the District of Puer-to Rico (“Local Rules”) as to what date should have served as EME’s deadline to respond, the court vacates the district court’s order granting summary judgment and remands the matter to the district court so that it may reconsider CIC’s motion for summary judgment in light of EME’s objection to that motion.

Factual and Procedural Background 1

EME worked as a subcontractor on a construction project for the United States Navy *2 on which Fraya was the general contractor. CIC was Fraya’s surety. EME brought this action under the Miller Act, 40 U.S.C. • § 270(b), against Fraya and CIC when Fraya failed to pay EME $74,831.22, plus interest, costs, and attorney’s fees, that EME alleges it is owed for work performed under the subcontract. Fraya brought a counterclaim against EME for $248,234.59 in damages allegedly caused by EME’s performance under the subcontract. CIC, on behalf of Fraya, contested liability for the debt and alleged that EME had not complied with the jurisdictional requirements of the Miller Act because it had not filed its claim within one year of the date it last performed on the subcontract.

After several delays at the outset of the case, the district court required CIC to file any summary judgment motions by November 18, 1996. 2 On November 6, CIC sought an extension of time in which to file for summary judgment until December 15, 1996, which the court denied. On November 18, CIC filed a timely motion for summary judgment, alleging that EME’s claim was filed outside the one year statute of limitations. In addition, it requested that it be allowed to file several documents in Spanish in support of its summary judgment motion.

Local Rule 108.1, concerning translations, provides in pertinent part as follows:

All documents not in the English language which are presented to or filed in this Court, whether as evidence or otherwise, shall be accompanied at the time of presentation or filing by an English translation thereof, unless the Court shall otherwise order.
Whenever a case is removed to this Court, there shall be filed with the record, an English translation of all papers____ Unless such translation accompanies the record, the Clerk shall refuse to receive and file the record.

The court denied CIC’s request to file documents in Spanish on December 3 and ordered CIC to file certified translations of the documents by December 9. On December 6, EME received a copy of the district court’s December 3 order denying CIC’s motion to file documents in Spanish and ordering that the English translations be filed by December 9.

Local Rule 311.5, concerning responses to motions, provides in pertinent part as follows:

If the respondent opposes a motion, he or she shall file a response within ten (10) days after service of the motion, including brief and such supporting documents as are then available____ For good cause appearing therefor, a respondent may be required to file a response and supporting documents, including brief, within such shorter period of time as the Court may specify, or may be given additional time to file a response as provided in subsection .6 of this Rule, including documents and brief.

Based on Local Rule 311.5, if CIC’s filing were considered complete on November 18 when it filed the motion for summary judgment, EME’s response would have been due on December 2. On December 2, EME’s counsel drafted a request for an extension of time to reply to the motion for summary judgment. It was signed on December 3 but, because of a clerical error at counsel’s firm, it was not filed until December 6. Once filed, the motion was not docketed until December 11.

In the meantime, on December 11, without knowledge that EME had filed a request for an extension of time to answer, the district court granted CIC’s motion for summary judgment. It found that CIC’s unopposed request for summary judgment supported the allegation that more than one year had passed between the time that EME last performed under the subcontract and the time it *3 filed the action seeking to recover on the subcontract.

On December 16, having previously granted summary judgment to CIC, the district court denied EME’s request for an extension of time to respond. The district court ruled that EME should have sought an extension of time before December 2, which it viewed as the deadline for EME’s response. On December 17, EME filed a motion for relief from judgment pursuant to Federal Rule of Civil Procedure 60, claiming, inter alia, excusable neglect for its failure to file its response or request for extension of time within the deadline. In an order filed February 10,1997, the district court denied the motion.

EME then filed this timely appeal, contesting the district court’s grant of summary judgment and denial of post-judgment relief. EME asserts that, if allowed, it is able to file an immediate response to the motion for summary judgment setting forth a meritorious defense to the statute of limitations bar.

Discussion

EME raises several contentions on appeal, but the court need only consider in detail its assertion that the district court erred in calculating the proper time period for EME to respond to CIC’s motion for summary judgment. EME asserts that the ten-day period within which it was required to reply to the motion for summary judgment should have begun running, not on November 18 when the motion for summary judgment was filed, but on December 9, the date that CIC, in accordance with the court’s order, filed its certified translations of Spanish-language documents supporting the motion for summary judgment. The district court rejected EME’s'argument, stating the following:

Plaintiff also argues that [CIC’s] motion for summary judgment was not complete until it filed certified translations of the documents in support thereof on December 9, and therefore plaintiffs motion requesting an extension of time was not tardy. Although Local Rule 108.1 requires that any document filed with this Court in a language other than English be accompanied by a certified translation, it does not state — nor does plaintiff point to any ease law so holding — that a motion for summary judgment is not considered filed until such translations are provided. More im-portantlyi plaintiff does not suggest that failure to provide translations hindered its ability to oppose the motion for summary ■judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re: Michelle A. Veale
D. Delaware, 2022
Harrison v. Kernan
N.D. California, 2021
Tesla, Inc. v. Tripp
D. Nevada, 2020
Falk v. Life Insurance Co. of North America
2013 DNH 124 (D. New Hampshire, 2013)
Fifield v. HM Life Insurance C o .
2012 DNH 176 (D. New Hampshire, 2012)
Kaufmann v. Prudential Ins. Co.
2012 DNH 003 (D. New Hampshire, 2012)
Exeter Hospital v. New England Homes
2011 DNH 135 (D. New Hampshire, 2011)
Few v. Liberty Mutual
2009 DNH 027 (D. New Hampshire, 2009)
Urso v. Prudential Insurance
2008 DNH 004 (D. New Hampshire, 2008)
Howard v. Warden, NHCF
2007 DNH 001 (D. New Hampshire, 2007)
Perroti-Johns v. Wal-Mart et al.
2006 DNH 079 (D. New Hampshire, 2006)
Davey v. Life Ins. Co. of N.A.
2006 DNH 068 (D. New Hampshire, 2006)
Perez-Cordero v. Wal-mart Puerto Rico
440 F.3d 531 (First Circuit, 2006)
Morris v. MetLife
2005 DNH 086 (D. New Hampshire, 2005)
Maureen Keough v. Liberty Life Assur.
2005 DNH 032 (D. New Hampshire, 2005)
Arsenault v. Metropolitan Life
2004 DNH 143 (D. New Hampshire, 2004)
Crowley v. L.L. Bean, Inc.
361 F.3d 22 (First Circuit, 2004)
Douglas v. York County
360 F.3d 286 (First Circuit, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
145 F.3d 1, 42 Cont. Cas. Fed. 77,304, 1998 U.S. App. LEXIS 10479, 1998 WL 250753, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-for-the-use-and-benefit-of-electric-machinery-ca1-1998.