UNITED STATES FOR THE USE OF COLORADO CUSTOM ROCK CORP. v. G&C FAB-CON, LLC

CourtDistrict Court, D. New Jersey
DecidedFebruary 14, 2024
Docket3:20-cv-02968
StatusUnknown

This text of UNITED STATES FOR THE USE OF COLORADO CUSTOM ROCK CORP. v. G&C FAB-CON, LLC (UNITED STATES FOR THE USE OF COLORADO CUSTOM ROCK CORP. v. G&C FAB-CON, LLC) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
UNITED STATES FOR THE USE OF COLORADO CUSTOM ROCK CORP. v. G&C FAB-CON, LLC, (D.N.J. 2024).

Opinion

NOT FOR PUBLICATION UNITED STATES DISTRICT COURT DISTRICT OF NEW JERSEY

UNITED STATES FOR THE USE OF COLORADO CUSTOM ROCK CORPORATION, Plaintiff, Civil Action No. 20-02968 (GC) (RLS) V. MEMORANDUM ORDER G&C FAB-CON, LLC and EVEREST REINSURANCE CO., Defendants.

CASTNER, U.S.D.J. THIS MATTER comes before the Court upon four Motions in Limine submitted by the parties in advance of trial. (ECF Nos. 76, 78, 79, 80.) The parties were given an opportunity to oppose, and after careful review, the Court now decides the motions without oral argument pursuant to Federal Rule of Civil Procedure (“Rule”) 78(b) and Local Civil Rule 78.1(b). I. BACKGROUND This case arises from a federal construction project known as the “Pike’s Peak National Cemetery Project,” located in Colorado Springs, Colorado. (ECF No. 96 at 1.') The project involved the construction of a United States Department of Veteran Affairs (the “VA”) national cemetery. (/d.) The VA entered into a contract with G&C Fab-Con, LLC, the prime contractor on the project. (id.) G&C then entered into a subcontract with Colorado Custom Rock Corp., for

Page numbers for record cites (i.e., “ECF Nos.”) refer to the page numbers stamped by the Court’s e-filing system and not the internal pagination of the parties.

Colorado Custom to perform masonry work on two buildings: the project’s administrative building and the maintenance building. (/d.) G&C posted a performance bond for the project that was provided by Everest Reinsurance Co, (Jd. at 1-2.) Plaintiff's position is that it performed its masonry work in accordance with the subcontract, and G&C breached the subcontract by improperly terminating Colorado Custom and failing to pay for its work. (/d. at 2.) Defendants’ position is that Colorado Custom’s work was defective due to alleged plumbness” issues and, therefore, Colorado Custom was properly terminated in accordance with the subcontract. (Ud.) Defendants also contend that G&C was compelled to perform extensive corrective work, which resulted in costs that far exceed any amounts that may have been due to Colorado Custom under the subcontract. (Id.) On August 8, 2023, the Court issued a Pretrial Scheduling Order directing the parties to submit their anticipated motions in limine. (ECF No. 74.) Trial was scheduled to commence on September 25, 2023. Cd.) On August 10, 2023, Defendants submitted three motions in limine (ECF Nos. 76, 78, 80), and Plaintiff submitted one motion in limine (ECF No. 79). The parties responded to the respective motions on August 16. (ECF Nos. 86-89.) Trial was subsequently post-postponed until February 27, 2024, due to the inability of one of the expert witnesses to travel to New Jersey to testify at trial. (ECF Nos. 117 & 121.) U. LEGAL STANDARD District Courts have “wide discretion in determining the admissibility of evidence under the Federal Rules.” United States y. Abel, 469 U.S. 45, 54 (1984). “Unlike a summary judgment motion, which is designed to eliminate a trial in cases where there are no genuine issues of fact, a

2 Plumbness refers to the quality or state of being plumb or vertical.

motion in limine is designed to narrow the evidentiary issues for trial and to eliminate unnecessary trial interruptions.” Bradley vy. Pittsburgh Bd. of Educ., 913 F.2d 1064, 1069 (3d Cir. 1990). “The purpose of a motion in limine is to allow the trial court to rule in advance of trial on the admissibility and relevance of certain forecasted evidence.” United States v. Tartaglione, 228 F. Supp. 3d 402, 406 (E.D. Pa. 2017). “Evidence should not be excluded pursuant to a motion in limine, unless it is clearly inadmissible on all potential grounds. ... The movant bears the burden of demonstrating that the evidence is inadmissible on any relevant ground, and the court may deny a motion in limine when it lacks the necessary specificity with respect to the evidence to be excluded.” Leonard v. Stemtech Health Scis., Inc., 981 F. Supp. 2d 273, 276 (D. Del. 2013) (citations omitted). A trial court’s ruling on a motion in limine is “subject to change when the case unfolds, particularly if actual testimony differs from what was contained in the movant’s proffer. Indeed even if nothing unexpected happens at trial, the district judge is free, in the exercise of sound judicial discretion, to alter a previous in limine ruling.” Luce v. United States, 469 U.S. 38, 41-42 (1984); see also Faragalla v. Otundo, 626 F. Supp. 3d 783, 785 (D.N.J. 2022) (“Because a ruling on a motion in limine is ‘subject to changes as the case unfolds,’ this ruling constitutes a preliminary determination in preparation for trial.” (quoting United States v. Perez, Crim. No. 09- 1153, 2011 WL 1431985, at *1 (S.D.N.Y. Apr. 12, 2011))). I. DISCUSSION A. MOTION TO PRECLUDE FACT TESTIMONY OF CALEB BAUSERMAN Defendants G&C and Everest move to preclude the fact testimony of non-party Caleb Bauserman, a former employee of Colorado Custom. (ECF No. 76.) According to Defendants, Mr. Bauserman was a supervisor for Colorado Custom “during the most critical time frames”— when the allegedly “defective work was performed, ... was discovered, and when testing of the

masonry walls at issue took place.” (ECF No. 76-1 at 5.) Furthermore, Mr. Bauserman supposedly “conducted a plumb bob survey” that is relevant to the parties’ dispute as to whether the masonry walls were “constructed significantly out of plumb.” (/d.) Despite the relevance of Mr. Bauserman’s testimony, Defendants argue that he should not be allowed to testify because he failed to contact them or attend a deposition on March 9, 2021, even though they served a deposition subpoena on February 27, 2021. (Jd. at 5-6.) In opposition, Plaintiff argues that G&C and Everest are seeking to punish it for their own tactical errors. (ECF No. 89-1 at 4.) Notably, when Mr. Bauserman did not appear at the March 9, 2021 deposition, Defendants filed a petition to compel his appearance but chose to voluntarily withdraw that petition on May 13, 2021, prior to the close of fact discovery. Ud.) Plaintiff submits that it would be unfair to bar Mr. Bauserman’s testimony at trial because it “played by the rules, providing ... Mr. Bauserman’s last known address and telephone number,” and G&C did not act diligently despite knowing that Mr. Bauserman is a material witness. (Jd. at 8.) The Court agrees that there is no basis presented to bar Mr. Bauserman from being called by Plaintiff as a fact witness at trial. As Defendants acknowledge, Mr. Bauserman’s testimony is likely to be highly relevant to the disputed factual issues, and there is no indication that Plaintiff acted in bad faith, had control over its former employee, or is responsible for Mr. Bauserman’s failure to appear for his deposition. Indeed, it is undisputed that Plaintiff identified Mr. Bauserman to Defendants in September 2020 as one of three individuals who “reviewed, supervised, or approved” the work on the project. (ECF No. 39-4 at 7.) Plaintiff also provided Mr. Bauserman’s telephone number. (/d.) After Mr. Bauserman failed to appear for the March 9, 2021 deposition, Defendants filed a petition with this Court for issuance of a Commission. (ECF No, 39.) In that petition, they confirmed that counsel for Plaintiff had informed them that Colorado Custom “would not be representing Mr. Bauserman as a former employee... and provided his last known address

such that an appropriate subpoena for deposition could be prepared.” (Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Luce v. United States
469 U.S. 38 (Supreme Court, 1984)
United States v. Abel
469 U.S. 45 (Supreme Court, 1984)
Daubert v. Merrell Dow Pharmaceuticals, Inc.
509 U.S. 579 (Supreme Court, 1993)
Bull v. United Parcel Service, Inc.
665 F.3d 68 (Third Circuit, 2012)
In Re Paoli Railroad Yard PCB Litigation
35 F.3d 717 (Third Circuit, 1994)
Charles Kannankeril v. Terminix International, Inc.
128 F.3d 802 (Third Circuit, 1997)
Carmelita Elcock v. Kmart Corporation
233 F.3d 734 (Third Circuit, 2000)
David Oddi v. Ford Motor Company
234 F.3d 136 (Third Circuit, 2000)
Calhoun v. Yamaha Motor Corporation
350 F.3d 316 (Third Circuit, 2003)
ZF Meritor LLC v. Eaton Corporation
696 F.3d 254 (Third Circuit, 2012)
Pineda v. Ford Motor Co.
520 F.3d 237 (Third Circuit, 2008)
In re Urethane Antitrust Litigation
152 F. Supp. 3d 357 (D. New Jersey, 2016)
United States v. Tartaglione
228 F. Supp. 3d 402 (E.D. Pennsylvania, 2017)
Leonard v. Stemtech Health Sciences, Inc.
981 F. Supp. 2d 273 (D. Delaware, 2013)
Sabol v. Allstate Property & Casualty Insurance
309 F.R.D. 282 (M.D. Pennsylvania, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
UNITED STATES FOR THE USE OF COLORADO CUSTOM ROCK CORP. v. G&C FAB-CON, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-for-the-use-of-colorado-custom-rock-corp-v-gc-fab-con-llc-njd-2024.