UNITED STATES FOR THE USE OF COLORADO CUSTOM ROCK CORP. v. G&C FAB-CON, LLC

District Court, D. New Jersey·Decided October 1, 2024·No. 3:20-cv-02968·Unknown

Opinion

NOT FOR PUBLICATION

UNITED STATES DISTRICT COURT DISTRICT OF NEW JERSEY

UNITED STATES FOR THE USE OF COLORADO CUSTOM ROCK CORPORATION,

Plaintiff, Civil Action No. 20-02968 (GC) (RLS) v. OPINION G&C FAB-CON, LLC and EVEREST REINSURANCE CO.,

Defendants.

CASTNER, District Judge

THIS MATTER comes before the Court on three post-trial motions: Defendant G&C Fab- Con, LLC’s Motion for Attorney’s Fees and Costs; Plaintiff United States for the Use of Colorado Custom Rock Corporation’s Motion to Amend/Correct Judgment to Include Pre-Judgment and Post-Judgment Interest; and Defendants G&C Fab-Con, LLC and Everest Reinsurance Company’s Motion for Judgment as a Matter of Law, or in the Alternative, to Alter and/or Amend the Judgment, or in the Alternative, for a New Trial. (ECF Nos. 161, 162, 164.) The parties briefed the motions. (ECF Nos. 166-68, 175-77, 182.) The Court carefully considered the parties’ submissions and decides the motions without oral argument pursuant to Federal Rule of Civil Procedure (“Rule”) 78(b) and Local Civil Rule 78.1(b). For the reasons set forth below, the Court DENIES Defendants’ motion for judgment as a matter of law/to alter or amend the judgment/for a new trial, DENIES Defendant G&C’s motion for attorney’s fees and costs, and GRANTS in part and DENIES in part Plaintiff’s motion for pre-judgment and post-judgment interest.1 I. BACKGROUND2

This case involves a federal construction project known as the “Pike’s Peak National Cemetery Project,” located in Colorado Springs, Colorado. The project called for the construction of a United States Department of Veteran Affairs (the “VA”) national cemetery. The VA entered into a contract with Defendant G&C Fab-Con, LLC, the general contractor on the project. G&C then entered into a subcontract with Plaintiff Colorado Custom Rock Corp., for Colorado Custom to perform masonry work on the project, including for two buildings: the project’s administration building and the maintenance building. G&C posted a performance bond for the project that was provided by Defendant Everest Reinsurance Co. During the construction of the two buildings, a dispute arose as to the quality of the masonry work that Colorado Custom was performing. Plaintiff took the position that it performed its masonry work in accordance with the subcontract (or timely corrected any faulty work) and G&C breached the subcontract by improperly terminating Colorado Custom and failing to then

pay for its labor and materials. Defendants’ position was that Colorado Custom’s work was defective due to plumbness3 issues and Colorado Custom was properly terminated in accordance

1 On September 27, 2024, Defendants also filed an emergent motion under Rule 62(b) “for an order staying execution of the judgment entered on March 13, 2024 . . . pending disposition of the post-trial motions” in light of Plaintiff’s September 26, 2024 demand for payment within seven days. (See ECF No. 184 at 3; ECF No. 184-2.) Because a First Amended Judgment will accompany this Opinion and enforcement of an Amended Judgment is automatically stayed for 30 days under Rule 62(a), the Court DENIES as moot Defendants’ motion for a stay of execution of the Court’s March 13, 2024 Judgment. See Rule 62(a) (“. . . [E]xecution on a judgment and proceedings to enforce it are stayed for 30 days after its entry, unless the court orders otherwise.”).

2 Page numbers for record cites (i.e., “ECF Nos.”) refer to the page numbers stamped by the Court’s e-filing system and not the internal pagination of the parties.

3 Plumbness refers to the quality or state of being plumb or vertical. with the subcontract for defaulting on its obligations thereunder. G&C also claimed that it was compelled to retain other subcontractors to perform extensive corrective work, resulting in costs far exceeding what was otherwise due to Colorado Custom. Plaintiff Colorado Custom sued and Defendant G&C countersued, both parties asserting claims for breach of the subcontract.4 (ECF No. 1 at 3-4; ECF No. 22 at 9-10.) A six-day jury

trial was held in late-February and early-March 2024, which included testimony from ten witnesses (both fact and expert) and the admission of over eighty exhibits. (ECF Nos. 169-174.) The jury rendered a unanimous verdict on March 7, 2024, finding that G&C breached the subcontract and awarding Colorado Custom $589,000.00 in damages on its breach-of-contract claim. (ECF No. 155.) The jury also found that Colorado Custom breached the subcontract but awarded G&C just $1.00 in nominal damages on its breach-of-contract counterclaim. (Id.) On March 13, 2024, the Court entered a Judgment Order consistent with the jury’s verdict and directing that any post-trial motions be filed by the parties within thirty days. (ECF No. 160.) On March 27, 2024, Defendant G&C moved for the Court to award it attorney’s fees and

costs under the subcontract. (ECF No. 161.) On April 10, 2024, Plaintiff Colorado Custom moved to amend/correct the judgment to include pre-judgment and post-judgment interest. (ECF No. 162.) Defendants G&C and Everest also moved on April 10 for judgment as a matter of law, to alter/amend the judgment, or for a new trial. (ECF No. 164.) The parties briefed the motions in late-April and early-May 2024. (ECF Nos. 166-68, 175-77, 182.) II. DISCUSSION

A. DEFENDANTS’ MOTION FOR JUDGMENT AS A MATTER OF LAW

Defendants’ motion for judgment as a matter of law, to alter or amend the judgment, or for

4 Plaintiff also sued Everest under the Miller Act, 40 U.S.C. § 3131, et seq., for payment on the payment bond that G&C posted. (ECF No. 1 at 4-5.) a new trial centers on the contention that Plaintiff Colorado Custom “failed to present . . . competent evidence upon which the jury could reasonably render a verdict on [Plaintiff’s] claim for damages.” (ECF No. 164-1 at 9.) Defendants argue that Plaintiff did not provide documentary evidence for $398,268.41 sought at trial, consisting of $132,190.00 in unpaid “stored materials” in Plaintiff’s March and April 2019 payment applications and $266,078.41 for Plaintiff’s unbilled

work (labor and stored materials) on the administration building. (Id. at 8-9.) Defendants further argue that the testimony proffered by Todd Robertson, Plaintiff’s Chief Executive Officer and owner, as to damages was “vague, conclusory and speculative,” and insufficient to support the damages claimed. (Id. at 9-14.) In opposition, Plaintiff argues that a party does not need to “prove damages with documentary evidence,” and even so, the trial “record contains ‘documentary evidence’ to support both the fact of damages and the amount.” (ECF No. 168 at 25-26.) Plaintiff also notes that the “jury did not award [Colorado Custom] all of the damages it sought, but . . . reduced that amount by $102,758.33. Although the jury did not itemize its damages calculation on the verdict sheet,

Free access — add to your briefcase to read the full text and ask questions with AI

UNITED STATES FOR THE USE OF COLORADO CUSTOM ROCK CORP. v. G&C FAB-CON, LLC, (D.N.J. 2024).

UNITED STATES FOR THE USE OF COLORADO CUSTOM ROCK CORP. v. G&C FAB-CON, LLC (UNITED STATES FOR THE USE OF COLORADO CUSTOM ROCK CORP. v. G&C FAB-CON, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hensley v. Eckerhart
461 U.S. 424 (Supreme Court, 1983)
Hewitt v. Helms
482 U.S. 755 (Supreme Court, 1987)
Farrar v. Hobby
506 U.S. 103 (Supreme Court, 1992)
Dunn v. HOVIC
13 F.3d 58 (Third Circuit, 1993)
Eaves v. County Of Cape May
239 F.3d 527 (Third Circuit, 2001)
National Security Systems, Inc. v. Iola
700 F.3d 65 (Third Circuit, 2012)
Jeffrey J. Prosser v.
534 F. App'x 126 (Third Circuit, 2013)
Chin v. CHRYSLER LLC
538 F.3d 272 (Third Circuit, 2008)
Blakey v. Continental Airlines, Inc.
992 F. Supp. 731 (D. New Jersey, 1998)
Lazaridis v. Wehmer
591 F.3d 666 (Third Circuit, 2010)
Lane v. Oil Delivery, Inc.
524 A.2d 405 (New Jersey Superior Court App Division, 1987)