United States ex rel. T.L. Wallace Construction, Inc. v. Fireman's Fund Insurance

790 F. Supp. 680, 1992 U.S. Dist. LEXIS 6634, 1992 WL 86415
CourtDistrict Court, S.D. Mississippi
DecidedApril 20, 1992
DocketCiv. A. No. W91-0014(B)
StatusPublished
Cited by6 cases

This text of 790 F. Supp. 680 (United States ex rel. T.L. Wallace Construction, Inc. v. Fireman's Fund Insurance) is published on Counsel Stack Legal Research, covering District Court, S.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. T.L. Wallace Construction, Inc. v. Fireman's Fund Insurance, 790 F. Supp. 680, 1992 U.S. Dist. LEXIS 6634, 1992 WL 86415 (S.D. Miss. 1992).

Opinion

MEMORANDUM OPINION AND ORDER

BARBOUR, Chief Judge.

This cause is before the Court on Defendant’s Motion for Summary Judgment and Plaintiff’s Cross-Motion for Summary Judgment. The Court, having considered the Motions and responses, along with memoranda of authorities and attachments thereto, is of the opinion that Defendant’s Motion is well taken and should be granted.

I. FACTS AND PROCEDURAL HISTORY

This case arises under the Miller Act, 40 U.S.C. § 270a, et seq., which requires contractors that construct, alter or repair public buildings or public works of the United States pursuant to a contract with the United States to secure performance bonds for the protection of the United States and payment bonds for the protection of persons supplying labor and material in the prosecution of the work provided for in the contract. 40 U.S.C. § 270a(a)(l) and (2). Plaintiff T.L. Wallace Construction, Inc. seeks payment for work performed pursuant to a subcontract with Lewis Miller Construction Co., Inc. (“Lewis Miller”), the prime contractor to a contract with the United States Army Corps of Engineers (“Corps of Engineers”). Defendant Fireman’s Fund Insurance Company is surety on a payment bond obtained by Lewis Miller as required by 40 U.S.C. § 270a.

On October 8, 1987, Plaintiff entered into a subcontract with Lewis Miller to construct a drainage structure for the Rocky Bayou Area Levee, Item 1-B in Yazoo County, Mississippi, Contract No. DACW38-87-C-0011 (“the Project”). Lewis Miller was prime contractor on the Project under a contract entered into with the Corps of Engineers. On July 25, 1988, representatives of Lewis Miller and representatives of the Corps of Engineers inspected the subcontract work performed by Plaintiff. See Exhibit “A” to Defendant’s Motion for Summary Judgment, Affidavit of Timothy Temple. On July 27, 1988, Timothy Temple, Vice-President of Construction for Lewis Miller, notified Plaintiff by letter of “final work” that needed to be completed on the drainage structure. See Exhibit “2” to Defendant’s Exhibit “A,” Affidavit of Timothy Temple. The “final work” included completion of a paved ditch; installation of concrete footing and stairs; installation of steel grates; formation and notification of a plan to take corrective action to realign motor anchor bolts and replace stem guide anchor bolts; and application of a “Class ‘B’ ” finish to the concrete structure. Id. The letter also notified Plaintiff of the probable arrival date of new stem and guides. Id.

Plaintiff subsequently performed the work and submitted its last certified payroll record for the project for the period from September 11, 1988, to September 17, 1988. See Exhibit “3” to Defendant’s Exhibit “A,” Affidavit of Timothy Temple. The payroll record indicates that Plaintiff performed its last labor on September 15, 1988. Id. Plaintiff concedes that it “substantially completed” its work under the subcontract in September 1988. See Exhibit “K” to Plaintiffs Cross-Motion for Summary Judgment, Affidavit of Randy Adams. On October 5, 1988, the Corps of Engineers accepted the Project as “substantially complete.” See Exhibit “4” to Defendant’s Exhibit “A,” Affidavit of Timothy Temple; Exhibit “D” to Plaintiff’s Cross-Motion for Summary Judgment, October 11, 1988, Memorandum from Gordon O. Inman, Area Engineer for Corps of Engineers, and November 8, 1988, Letter from Robert P. Petersen, Major, Corps of Engineers, Contracting Officer.

On November 1, 1989, Joe Strawbridge, Operations Manager for Lewis Miller, notified Plaintiff that Plaintiff needed to complete two “punch list” items so that Lewis [682]*682Miller could “final” [sic] the project. See Exhibit “1” to Exhibit “B” to Defendant’s Motion for Summary Judgment, Affidavit of Joe Strawbridge. Charles J. Gordon, Project Engineer for the Corps of Engineer, confirms by affidavit that the government required completion of punch list items prior to final acceptance of the Project. See Exhibit “E” to Plaintiffs Cross-Motion for Summary Judgment, Affidavit of Charles J. Gordon. The “punch list,” which Strawbridge attached to his letter to Plaintiff, specified seventeen items to be completed by various parties. The two items for which Plaintiff was responsible read as follows:

1. North-East column approx. 4' below top deck cracked & needs repair.
* * * * * *

4. Repaint stem guides

See Exhibit “1” to Defendant’s Exhibit “B;” Exhibit “A” to Plaintiff’s Exhibit “E.” On February 27, 1990, and March 16, 1990, Plaintiff worked on the Project to complete the punch list items. See Defendant’s Exhibit “G” and Exhibit “K.” Plaintiff did not invoice or charge Lewis Miller for the punch list work. See Defendant’s Exhibit “B.”

On October 3, 1990, Plaintiff’s Vice-President/Controller, Donavon G. Inkster, wrote Lewis Miller demanding final payment under the subcontract. See Defendant’s Exhibit “4.” Plaintiff was to be paid $110,000 under the subcontract, but, according to its estimates, has been paid $82,350 in progress payments and its account has been charged $3,850 in contractor tax. See Plaintiff’s Exhibit “C.”

Plaintiff filed the present action against Defendant, as surety for Lewis Miller, on March 1, 1991, pursuant to the Miller Act, 40 U.S.C. § 270a et seq., for $27,650.00 due and owing for labor and material provided by Plaintiff for the Project.1

The Court has jurisdiction pursuant to 28 U.S.C. § 1331, this being a case arising under the laws of the United States.

II. ANALYSIS

Rule 56 of the Federal Rules of Civil Procedure states in relevant part that summary judgment shall be rendered forthwith if the pleadings, depositions, answers to interrogatories, and admissions on file, together with affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to summary judgment as a matter of law. Fed.R.Civ.P. 56(c). The United States Supreme Court has held that this language “mandates the entry of summary judgment, after adequate time for discovery and upon motion, against a party who fails to make a sufficient showing to establish the existence of an essential element to that party’s case, and on which that party will bear the burden of proof at trial.” Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 2552, 91 L.Ed.2d 265 (1986); see also Moore v. Mississippi Valley State University,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Land Holdings I, LLC v. GSI Services, LLC
265 So. 3d 147 (Mississippi Supreme Court, 2019)
R.E. Monks Construction Co. v. Aetna Casualty & Surety Co.
944 P.2d 517 (Court of Appeals of Arizona, 1997)
RE MONKS CONST. v. Aetna Cas. & Sur.
944 P.2d 517 (Court of Appeals of Arizona, 1997)
United States v. Sun Engineering Enterprises, Inc.
817 F. Supp. 1009 (D. Puerto Rico, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
790 F. Supp. 680, 1992 U.S. Dist. LEXIS 6634, 1992 WL 86415, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-tl-wallace-construction-inc-v-firemans-fund-mssd-1992.