United States ex rel. Forsberg v. Fleischmann Const. Co.

298 F. 320, 1923 U.S. Dist. LEXIS 1035
CourtDistrict Court, E.D. Virginia
DecidedAugust 4, 1923
StatusPublished
Cited by12 cases

This text of 298 F. 320 (United States ex rel. Forsberg v. Fleischmann Const. Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Forsberg v. Fleischmann Const. Co., 298 F. 320, 1923 U.S. Dist. LEXIS 1035 (E.D. Va. 1923).

Opinion

GRONER, District Judge.

This action was brought to enforce liability of the defendants, as contractor and surety, respectively, under the provisions'of the statute of February 24, 1905 (33 Stat. 811 [Comp. St. § 6923]), amending the Act of August 13, 1894 (28 Stat. 278) commonly known as the “Heard Act.” The record is very voluminous, the interventions very numerous, and it was apparent to the court and to counsel, when the Case was ready for trial, that it would be a matter of very serious inconvenience to all concerned to attempt to complete the entire case at a single session of the court. The convenience of witnesses and the time of counsel were therefore considered by the court as.justifying, with the consent and at the suggestion of all parties, [323]*323a reference of the case to a special master to take the evidence and find the facts, and then, by stipulation of counsel, the evidence, together with the master’s finding, was to be reported to the court, and the lyhole matter of law and facts submitted to the court without the intervention of a jury.

It is sufficient for an understanding of the case to say that the Fleischmann Construction Company entered into a contract with the United States for the construction of the naval torpedo assembly plant at Alexandria, Va., on October 14, 1918, for the sum of $999,750. The National Surety Company became surety on the contractor’s bond in the sum of $300,000. The contract reserved to the United States the right to make changes, alterations, and additions, the cost of which was to be determined by a government board.. Changes were made, new work was added, and these were known to the government as change orders 1 to 21, inclusive. Subsequently these orders were incorporated into a supplementary contract between the same parties, dated May 24, 1919, the price tó be paid by the government being fixed at $199,160.07, and the same bonding company became surety in the sum of $59,748. Apparently additional change orders were from time to time issued, and were known as change orders A to F, inclusive. The master summarizes the contractual relation between the parties as obtaining under “contract No. 3425, supplemental contract No. 3425-X and change orders A to F, inclusive.” The principal contractor, Fleischmann, sublet to a company known as the Premier Engineering Company a large' portion of the work. Many of the interventions passed on were for failure to pay for work done under the direction of this subcontractor.

It is first insisted on behalf of the surety company that, except the claim of Forsberg embraced in the original action, all of the interveners filed their petitions in the suit too late, under the statute. The basis of this is the finding of the master that the work under the contract was completed February 5, 1920. Although the master finds that the work itself was completed on February 5, 1920, he likewise finds that the date of final settlement was October 1, 1920. Whether the conclusion of the master that the work was substantially completed on February 5, 1920, is justified by the evidence, it is, in my opinion, unnecessary to determine, for I think that date has no relation to the rights of the parties. The act provides that no suit shall be brought until six months from the completion and final settlement of the contract. Unquestionably the master was correct in ascertaining the date of the completion of the contract and final settlement with the government as October 1st. It follows, therefore, that no suit could have been brought until the 1st of April, 1921, and but one creditor is permitted, by the terms of the act, to bring the suit; the others being required to come in and file their petitions of intervention. If, therefore, the period when the work was completed is- fixed as of February 5th, and if that date controls the period of intervention, it follows that, except for one creditor, the rights of all the parties in interest would be foreclosed, because more than a year would have passed after February 5th before the expiration of the six months period from October 1st. The justification of this position on the part of the surety company grows out of the loose language found in the act, as follows:

[324]*324“And provided further, that where suit is so instituted by a creditor or by creditors, only one action shall be brought, and any creditor may file his claim in such action and he made party thereto 'loithm one year from the completion of the worlo under said contract, and not later.”

The act itself has been passed on by the Supreme Court in a great number of cases, and the burden of all of these is that:

“The purpose of the act was to provide security for the payment of all persons who provide labor or material on public work. This was done by giving a claim under the bond in lieu of the lien upon land and buildings customary where property is' owned by private persons. Decisions of this court have made it clear that the statute and bonds given under it must be construed liberally, in order to effectuate the purpose of Congress as declared in the act. In every case which has come before this court, where labor and materials were actually furnished for and used in part performance of the work contemplated in the bond, recovery was allowed, if the suit was brought within the period prescribed by the act. Technical rules otherwise protecting sureties from liability have never been applied in proceedings under this statute.” Illinois Surety Co. v. John Davis Co., 244 U. S. 376, 37 Sup. Ct. 614, 61 L. Ed. 1206.

To hold, as the defendants would have me hold in this case, that the government could delay the period of final settlement, as apparently it did in this case, until all the claims under the bonds would be outlawed by limitation, would be exactly contrary to the purpose Congrc ss had in enacting the law. The true construction of the act is that a suit must be brought within a period of a year after the final settlement with the government, and not less than six months after the same. The first period of six months is for the benefit of the government, to enable it to bring suit if it elects to do so. If it does not within the six months period, then the rights of the creditors of the contractor become effective from that time for a further period of six months, and the rights of the interveners, who are denied the right to bring separate actions, cannot be, upon any theory of the law, of lesser dignity than the claim of the principal claimant. They all grow out of the same statute, and all equally depend upon its terms for the ascertainment of their rights. The precise point was decided in London, etc., Co. v. Smoot, 287 Fed. 952, 52 App. D. C. 378, nnd the Supreme Court, in Bryant Co. v. N. Y. Steam Fitting Co., 235 U. S. 327, 35 Sup. Ct. 108, 59 L. Ed. 253, has called attention to the ambiguous language of the statute and to the duty of a court to give coherence to its provisions to accomplish the intent and .purpose of Congress. There can be no doubt, I think, if this precise question is submitted to the Supreme .Court, that it will hold that the time of all the creditors, both the plaintiff creditor and the intervening creditors, begins to run from the same event, to wit, final settlement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
298 F. 320, 1923 U.S. Dist. LEXIS 1035, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-forsberg-v-fleischmann-const-co-vaed-1923.