United States v. Morley Const Co.

11 F. Supp. 841, 1935 U.S. Dist. LEXIS 1478
CourtDistrict Court, W.D. New York
DecidedSeptember 4, 1935
DocketNo. 1444-A
StatusPublished
Cited by7 cases

This text of 11 F. Supp. 841 (United States v. Morley Const Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Morley Const Co., 11 F. Supp. 841, 1935 U.S. Dist. LEXIS 1478 (W.D.N.Y. 1935).

Opinion

KNIGHT, District Judge.

This action is brought under the so-called Heard Act, title 40, § 270, U. S. C. (40 USCA § 270).

The Concrete Engineering Company and the J. S. Thorn Company, subcontractors, intervened in this suit. The complaints of these interveners were served upon Morley Construction Company and Maryland Casualty Company in or about September, 1934. The Maryland Casualty Company answered on or about October 1, 1934. The defendant Morley Construction Company has not answered. The answers of the Maryland Casualty Company, as served, set up a general denial, defenses in avoidance, and a set-off for alleged defective materials. The Maryland Casualty Company now moves to amend its answers to include in each a counterclaim for damages resulting from delay in the furnishing of materials. Such amended answer asks that “such damages should be offset and applied in reduction of the damages which the said Morley Construction Company has sustained.”

Two questions are presented here: (1) Whether the proposed counterclaims are insufficient as a matter of law; and (2) whether the defendant Maryland Casualty Company is guilty of such laches as denies its right to amend.

The rule is well established that where a surety is sued alone he cannot avail himself of claims of the principal against a creditor where there is no statute permitting such action. National Surety Co. v. Geo. E. Breece Lumber Co. (C. C. A.) 60 F.(2d) 847. This is the rule in New York State. Gillespie v. Torrance, 25 N. Y. 306, 82 Am. Dec. 355. The latter case has been followed in Lasher v. Williamson & Co., 55 N. Y. 619; Elliott v. Brady, 192 N. Y. 221, 85 N. E. 69, 18 L. R. A. (N. S.) 600, 127 Am. St. Rep. 898: Ettlinger v. National Surety Co., 221 N. Y. 467, 117 N. E. 945, 3 A. L. R. 865. The fact that the principal, the Morley Construction Company, is a party defendant to this action and has been served with a complaint by these interveners, is not ma[843]*843ferial. Ettlinger v. National Surety Co., supra. The real test of the rule prohibiting a surety from setting up a counterclaim asserting an independent cause of action in favor of the principal against a creditor is whether the principal is barred from bringing an action on the particular cause sought to be set forth in the surety’s counterclaim. It is clear that the principal here is not so barred. The surety is not without his remedy, since he can still proceed against his principal.

It is urged on behalf of the surety that the case of Gillespie v. Torrance, 25 N. Y. 306, 82 Am. Dec. 355, and those following that case, originated prior to the adoption of the present provision of the New York State Civil Practice Act, § 193, subd. 1. That section reads: “The court may determine the controversy as between the parties before it where it can do so without prejudice to the rights of others.” It does not seem that this section has application here, since the controversy herein cannot be determined without prejudice to the rights of the principal. However, both Elliott v. Brady, 192 N. Y. 221, 85 N. E. 69, 18 L. R. A. (N. S.) 600, 127 Am. St. Rep. 898, and Ettlinger v. National Surety Co., 221 N. Y. 467, 117 N. E. 945, 3 A. L. R. 865, were decided subsequent to the enactment of section 452 of the Code of Civil Procedure. This latter section includes the identical language, of section 193, subd. 1, of the Civil Practice Act. The provision in section 193, subd. 1, providing that where a complete determination of the controversy cannot be had without the presence of other parties, the court may direct that they be brought in, likewise was included verbatim in section 452 of the Code of Civil Procedure.

Attention is called to section 398, title 28 USCA, Judicial Code § 274b, which provides that equitable defenses can be interposed in actions at law. This is an action at law. Illinois Surety Co. v. United States, 240 U. S. 214, 36 S. Ct. 321, 60 L. Ed. 609; United States v. J. L. Robinson Construction Co. (D. C.) 8 F. Supp. 620. Section 398, supra, has no application here, since the Maryland Casualty Company has no legal .right to interpose the counterclaim in this suit. While Gillespie v. Torrance, supra, and cases following it, do recognize that the surety may have certain equitable rights, they in no way support the claim that they can be enforced under the facts shown her-ein.

It is contended that Gillespie v. Torrance, supra, and cases following it, were cases in which the causes of action arose under separate contracts of guaranty which was a distinct contract from that under which the claim arose and that in order to exclude the counterclaim it must arise out of an independent cause of action. No distinction in this respect is apparent. The basis of the counterclaim in each instance is an independent cause of action. In Gillespie v. Torrance, supra, the counterclaim was based on a breach of implied warranty as to quality. The court held that the counterclaim for breach of the warranty was not available to the surety. Here the defendant seeks to set up counterclaims based upon failure of the plaintiff to fulfill its contract within a fixed time.

United States v. Fleischmann Construction Co. (D. C.) 298 F. 320; United States v. Richardson (C. C. A.) 223 F. 1010, 1012; Feinstein v. Jacobs, 139 App. Div. 192, 123 N. Y. S. 750, relied on by defendant, are distinguishable and are not in point here. In Feinstein v. Jacobs, supra, it was held that the surety may avail himself of the counterclaim pleaded by the principal. In United States v. Fleischmann Construction Co., supra, no question of the right of the surety" to interpose or recover upon a counterclaim was involved. Assuming the remotest connection between this case and the suit at bar, the holding simply was that the subcontractor was liable to the main contractor in the event of the former’s failure to complete a contract in the time fixed, where the contract between the two provided for the payment of damages for delay. United States v. Fleischmann Construction Co., supra, was affirmed by the Circuit Court upon the opinion of the District Court. In United States v. Richardson, supra, the surety was permitted to interpose as a set-off a claim which it would have had against the plaintiff. This authority to interpose such set-off was given pursuant to the specific language of 3298 of the Code of Virginia 1904. The opinion in the case states: “This statute provides in terms that, where the relation of principal and surety exists, the surety may [844]*844assert any claim which its principal would have had against the person seeking to recover against such surety.”

The act, under which this suit has been brought, section 270, U. S. C. title 40 (40 USCA § 270), supra, does provide that any persons furnishing material may be made parties to the' action “and * * * have their rights and claims adjudicated in such action and judgment rendered thereon.” This language should not be construed so broadly as to prevent the determination of the rights of the claimant and all other parties as to every cause arising out of the claim. It was not intended to prevent a party from asserting at will an independent cause of action against the claimant. The act is one which confers special rights and liabilities. It should not be complicated by the inclusion of every sort of a defense or counterclaim which might be interposed by some one claiming some right against materialmen, which right could not be secured under other provisions of law. The claims of these interveners aggregate $3,800.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Martin
344 F. Supp. 350 (E.D. Michigan, 1972)
Klee v. Pittsburgh & West Virginia Railway Co.
22 F.R.D. 252 (W.D. Pennsylvania, 1958)
Garrison v. Baltimore & Ohio Railroad
20 F.R.D. 190 (W.D. Pennsylvania, 1957)
Meeker v. Halsey
87 F.2d 299 (Second Circuit, 1937)
United States ex rel. Johnson v. Morley Const. Co.
12 F. Supp. 1017 (W.D. New York, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
11 F. Supp. 841, 1935 U.S. Dist. LEXIS 1478, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-morley-const-co-nywd-1935.