United States Ex Rel. Blount Fabricators, Inc. v. Pitt General Contractors, Inc.

769 F. Supp. 1016, 37 Cont. Cas. Fed. 76,214, 1991 U.S. Dist. LEXIS 16760, 1991 WL 127185
CourtDistrict Court, E.D. Tennessee
DecidedFebruary 15, 1991
DocketCiv. 3-89-507
StatusPublished
Cited by2 cases

This text of 769 F. Supp. 1016 (United States Ex Rel. Blount Fabricators, Inc. v. Pitt General Contractors, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Blount Fabricators, Inc. v. Pitt General Contractors, Inc., 769 F. Supp. 1016, 37 Cont. Cas. Fed. 76,214, 1991 U.S. Dist. LEXIS 16760, 1991 WL 127185 (E.D. Tenn. 1991).

Opinion

MEMORANDUM OPINION

ROBERT P. MURRIAN, United States Magistrate Judge.

This case came before the undersigned on February 7, 1991, for trial without a jury and pursuant to 28 U.S.C. § 636(c) and Rule 73, Fed.R.Civ.P.

This is an action under 40 U.S.C. § 270b to recover on bonds given under 40 U.S.C. § 270a by a contractor engaged in the construction, alteration, or repair of a public building or public work of the United States. Jurisdiction is predicated upon 28 U.S.C. § 1331, and is not in dispute.

The use plaintiff Blount Fabricators, Inc. (“Blount”) claims that on September 14, 1988, the defendant Pitt General Contractors, Inc., entered into U.S. Government Contract Number V621C-386 for the reinforcement of warehouse floors at the Veterans Administration Medical Center at Johnson City, Tennessee; that, pursuant to 40 U.S.C. § 270a(a)(l), Pitt General Contractors, Inc. (“Pitt”), as the principal, and the defendants Edgar L. Powell and Richard F. Keyworth, as sureties, executed and delivered their payment bonds to the United States of America in reference to this contract, binding themselves jointly and severally for the payment of all persons having a direct relationship with the principal or with a subcontractor of the principal for furnishing labor, material or both in the prosecution of the work provided for in U.S. Government Contract Number V621C386; that the “penal sum” of the bond was $21,210.95; that pursuant to 40 U.S.C. § 270a(a)(2), Pitt as the principal and Messrs. Powell and Keyworth as the sureties, executed and delivered their performance bonds to the United States, binding themselves jointly and severally for performance of the contract; that the “penal sum” on the performance bond was $42,-421.91; that Blount entered into a subcontract with the defendant Pitt in reference to the contract under which Blount agreed to provide all materials and labor necessary to fabricate aluminum tread plates to reinforce the warehouse floor pursuant to the contract; and that Blount has performed all of its obligations owed to the defendant Pitt under this contract. It is not disputed that Blount has not been paid for any of its work on the job.

On January 10, 1991, summary judgment entered in Blount’s favor and against Pitt for the full amount of the subcontract ($40,018.35), plus interest in the amount of $6,333.00 for a total amount of $46,351.00 [Doc. 42], Blount has not been paid any of this amount by Pitt.

Messrs. Powell and Keyworth claim that the liability of both defendants, if any, is limited to the face amount of the payment bond ($21,210.95) and that they have no obligation to Blount under the performance bond.

Messrs. Powell and Keyworth filed a cross-claim against Pitt for indemnification based upon a general indemnification agreement.

Messrs. Powell and Keyworth filed a third-party claim against Jerome A. Pittman and Minerva Banks, corporate officers of Pitt, based on that same general indemnification agreement.

There is no doubt that Blount, as a subcontractor on this project has the right to sue on the payment bond. 40 U.S.C. § 270b(a). Furthermore, Blount is entitled to judgment against Messrs. Powell and Keyworth, jointly and severally, for the amount of the payment bond. The difficult qúestion is whether or not Blount is also entitled to recover under the performance bond as well.

Blount argues that Pitt failed to perform an obligation it had under the contract with the United States; that Blount now stands in the shoes of the United States or is a third-party beneficiary of Pitt’s promise to the United States to pay Pitt’s subcontractors; and that Blount is entitled to recover against Messrs. Powell and Keyworth be *1018 cause they agreed to be sureties on Pitt’s performance of the contract with the United States.

Blount relies upon the following contract provision in support of its argument:

The Contractor, prior to receiving a progress or final payment under this contract, shall submit to the Contracting Officer a certification that the Contractor has made payment from proceeds of pri- or payments, or that timely payment will be made from the proceeds of the progress or final payment then due, to subcontractors and suppliers in accordance with the contractual arrangements with them.

This certification was made by Jerome A. Pittman on January 31, 1989, as Pitt’s chief executive officer. He claimed the contract price of $42,421.91 and certified that

I have made payment from proceeds of prior payments and I will make timely payment from the proceeds of the final payment now due to my subcontractors and suppliers in accordance with contractual arrangements with them.

Exhibit 7. Mr. Pittman was paid for the job by the United States in full but has not kept his promise to pay Blount. He and Blount agreed that the latter would be paid when Pitt was paid. He nor Pitt has ever paid Blount any of the amount owing under the subcontract ($40,018.35 plus interest).

Blount also points to the following provision in the original contract between the United States and Pitt:

1.31 PAYMENT UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (VAAR 852.236-82) (APR 1984)
The clause entitled “Payments Under Fixed-Price Construction Contracts” in FAR 52.232.5 is implemented as follows: (a) retainage:
(1) The contracting officer may retain funds:
(i) Where performance under the contract has been determined to be deficient or the Contractor has performed in an unsatisfactory manner in the past____
******
(2) Examples of deficient performance justifying a retention of funds include, but are not restricted to, the following:
******
(D) Failure to comply in good faith with approved subcontracting plans, certifications or contract requirements.

Exhibit 1 at p. 01001-18.

Retainage may not exceed 10% of the contract price and “[rjetained amounts shall be paid promptly upon completion of all contract requirements____” Id. at p. 01001-18. No retainage was withheld in this case.

Blount argues that Pitt’s failure to comply with the certification Mr. Pittman gave on Pitt’s behalf amounts to deficient performance for which Pitt and its sureties, Messrs. Powell and Keyworth, are liable under the performance bond.

I agree with the Court in the case of United States ex rel. James E.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

TransAmerica Premier Insurance v. Ober
894 F. Supp. 471 (D. Maine, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
769 F. Supp. 1016, 37 Cont. Cas. Fed. 76,214, 1991 U.S. Dist. LEXIS 16760, 1991 WL 127185, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-blount-fabricators-inc-v-pitt-general-contractors-tned-1991.