United Air Lines, Inc. v. Conductron Corp.

387 N.E.2d 1272, 69 Ill. App. 3d 847, 26 Ill. Dec. 344, 25 U.C.C. Rep. Serv. (West) 1320, 1979 Ill. App. LEXIS 2255
CourtAppellate Court of Illinois
DecidedFebruary 26, 1979
Docket77-1497
StatusPublished
Cited by33 cases

This text of 387 N.E.2d 1272 (United Air Lines, Inc. v. Conductron Corp.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Air Lines, Inc. v. Conductron Corp., 387 N.E.2d 1272, 69 Ill. App. 3d 847, 26 Ill. Dec. 344, 25 U.C.C. Rep. Serv. (West) 1320, 1979 Ill. App. LEXIS 2255 (Ill. Ct. App. 1979).

Opinion

Mr. PRESIDING JUSTICE GOLDBERG

delivered the opinion of the court:

United Air Lines, Inc. (plaintiff), brought an action for breach of contract against Conductron Corporation, McDonnell Douglas Electronics Company, a subsidiary of McDonnell Douglas Corporation, and McDonnell Douglas Corporation (defendants). In due course Conductron merged into McDonnell Douglas Electronics Company (later dissolved) and became a division of McDonnell Douglas Corporation. The case involves sale by defendants to plaintiff of an aircraft flight simulator. This machine was destroyed by fire while on plaintiff’s property. The trial court entered summary judgment in favor of plaintiff for *1,326,573.20. Defendants appeal.

Defendants contend that the trial court erred in entering summary judgment for plaintiff because the risk of loss of the simulator was upon plaintiff at the time of its destruction. In this regard defendants urge that at the very least there were issues of material fact concerning whether the simulator conformed to the agreement and had been accepted by plaintiff. Defendants contend these factors would shift the risk of loss to plaintiff. Defendants also contend that there was a genuine issue of material fact as to the causation of the fire. Defendants assert that plaintiff’s action was barred by a four-year statute of limitations and that the trial court abused its discretion in denying defendants leave to file an amended answer pleading the statute as a bar. Finally, defendants contend that they were not amenable to service of process in Illinois and denial by the trial court of their motion to quash service of process violated due process.

Plaintiff contends that at the time the simulator was destroyed the risk of loss was upon defendants. In this regard, plaintiff urges that defendants defaulted under the terms of the contract by failing to deliver a conforming aircraft flight simulator; this default was never cured; the simulator was never accepted by plaintiff because of its deficiencies and plaintiff at all times retained the right of rejection. Plaintiff further contends that defendants waived the issue regarding the statute of limitations by tardy attempt to raise the point; the trial court acted within its discretion in denying leave to defendants to amend and there was no excuse for the tardiness of defendants. Plaintiff finally contends that defendants have submitted to the jurisdiction of the court of Illinois.

Many of the facts which appear from the pleadings, interrogatories, depositions, and affidavits are undisputed. The purchase agreement between plaintiff and defendants, some 65 pages in length, was executed on December 30, 1966. The agreement contains 19 articles and was supplemented by a number of change orders. It required defendants to deliver a Boeing 727 digital flight simulator to plaintiff on January 13, 1968. A flight simulator is a highly sophisticated electro-mechanical device operated by computers. It is designed to simulate the experiences of a pilot in the cockpit of a jet airplane during flight. As flight simulators are used for training pilots, they must meet the requirements necessary for approval by the Federal Aviation Administration (FAA). The contract so provided. In addition the contract provided that the simulator would conform to plaintiff’s specifications.

The original contract provided for inspection and testing of the simulator by plaintiff at defendants’ plant prior to its shipment to plaintiff’s Flight Training Center in Denver, Colorado. The defendants agreed to correct any deficiency or discrepancy appearing from such inspection. The agreement further provided that when delivery of the simulator was made tide would pass to plaintiff but that such delivery would not constitute acceptance of the simulator by plaintiff. Final acceptance by plaintiff was subject to satisfactory completion and also to certification by the FAA.

Defendants failed to complete fabrication of the simulator by the agreed-upon date. This resulted in a request by plaintiff that the simulator be delivered to the plaintiff’s training center in Colorado for the testing process which, under the original agreement, could have been completed at defendants’ plant. On February 20, 1969, the parties entered into a modification of the contract referred to as Change Order Number 3. This order provided for disassembly of the machine, its delivery to plaintiff by common carrier not later than February 28, 1969, and reassembly by defendants on plaintiff’s premises not later than March 15, 1969. From July 1, 1969, to August 1, 1969, the simulator was to be available to plaintiff for demonstration purposes and for correction by defendants of deviations noted by plaintiff in the above-mentioned testing. The document stated that in the event the defendants were unable satisfactorily to correct all deviations prior to November 1, 1969, the plaintiff would have the right to cancel the agreement and receive a refund of all payments made to the defendants as buyer plus liquidated damages. The change order also gave plaintiff the right to use the simulator for personnel training purposes.

While the simulator was still in possession of defendants upon their facilities, plaintiff’s personnel noted some 647 deficiencies in its operation. These difficulties were recorded and reported to defendants by means of written reports referred to as “squawk sheets.” The simulator was delivered to plaintiff’s facility and was reassembled by defendants on March 14, 1969, in accordance with Change Order Number 3. Since the machine had not received FAA approval, it could not be used as an aircraft flight simulator. It was used for training purposes to acquaint and familiarize pilots with instrument location in the cabin of a Boeing 727 aircraft.

On April 18, 1969, the simulator was tested for 10 hours by two of plaintiff’s test pilots. About 10 p.m. a fire was discovered in the machine. The simulator was substantially damaged. The origin of the fire is unknown. After the fire, plaintiff requested that defendants dismantle and ship the simulator back to their plant for repairs at plaintiff’s expense. On May 16,1969, plaintiff notified defendants that they considered there was a breach by defendants of the warranties contained in the purchase agreement. On June 4, 1969, the parties amended the agreement by Change Order Number 4. This document provided that the plaintiff would receive *60,000 as liquidated damages for the late delivery of the simulator to be deducted from the remaining payments due defendants. Plaintiff commenced this action on May 11,1973, seeking rescission of the contract and damages. On January 28,1977, plaintiff filed count VII as an amendment to the complaint. This amendment alleged that the risk of loss of the simulator was upon defendants at the time it was destroyed.

Subsequently, plaintiff filed a motion for partial summary judgment on this risk of loss count. Plaintiff later amended this motion by adding a claim for prejudgment interest. Summary judgment in favor of plaintiff was entered by the trial court based on the theory that the simulator had never been accepted by plaintiff and, therefore, the risk of loss remained upon defendants. The order allowed plaintiff *1,043,434.33 as a refund of partial payments made, *60,000 as liquidated damages for delay and prejudgment interest of *223,138.78; a total of *1,326,573.20. No issue is raised on computation of these damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fox v. Seiden
2016 IL App (1st) 141984 (Appellate Court of Illinois, 2016)
Freedberg v. Ohio National Insurance Company
2012 IL App (1st) 110938 (Appellate Court of Illinois, 2012)
D.S. America (East), Inc. v. Elmendorf Grafica, Inc.
654 N.E.2d 472 (Appellate Court of Illinois, 1995)
National Surety Corp. v. Fast Motor Service, Inc.
572 N.E.2d 1083 (Appellate Court of Illinois, 1991)
Lynch Imports, Ltd. v. Frey
558 N.E.2d 484 (Appellate Court of Illinois, 1990)
Arthur Young & Co. v. Bremer
554 N.E.2d 671 (Appellate Court of Illinois, 1990)
American Pharmaseal v. TEC SYSTEMS
515 N.E.2d 432 (Appellate Court of Illinois, 1987)
Schwaner v. Belvidere Medical Building Partnership
508 N.E.2d 522 (Appellate Court of Illinois, 1987)
Bresland v. Ideal Roller & Graphics Co.
501 N.E.2d 830 (Appellate Court of Illinois, 1986)
Gordon v. Tow
498 N.E.2d 718 (Appellate Court of Illinois, 1986)
Hoffman v. Nustra
492 N.E.2d 981 (Appellate Court of Illinois, 1986)
Mandalay Associates Ltd. Partnership v. Hoffman
491 N.E.2d 39 (Appellate Court of Illinois, 1986)
Talas v. Youngstown Sheet & Tube Co.
479 N.E.2d 1052 (Appellate Court of Illinois, 1985)
Morris v. City of Chicago
474 N.E.2d 1274 (Appellate Court of Illinois, 1985)
Club Assistance Program, Inc. v. Zukerman
594 F. Supp. 341 (N.D. Illinois, 1984)
First Nat'l Bk of Chicago v. Boelcskevy
466 N.E.2d 1182 (Appellate Court of Illinois, 1984)
Maurice Sternberg, Inc. v. James
577 F. Supp. 882 (N.D. Illinois, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
387 N.E.2d 1272, 69 Ill. App. 3d 847, 26 Ill. Dec. 344, 25 U.C.C. Rep. Serv. (West) 1320, 1979 Ill. App. LEXIS 2255, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-air-lines-inc-v-conductron-corp-illappct-1979.