Talas v. Youngstown Sheet & Tube Co.

479 N.E.2d 1052, 134 Ill. App. 3d 103, 89 Ill. Dec. 46, 1985 Ill. App. LEXIS 2081
CourtAppellate Court of Illinois
DecidedJune 3, 1985
Docket84-1650
StatusPublished
Cited by15 cases

This text of 479 N.E.2d 1052 (Talas v. Youngstown Sheet & Tube Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Talas v. Youngstown Sheet & Tube Co., 479 N.E.2d 1052, 134 Ill. App. 3d 103, 89 Ill. Dec. 46, 1985 Ill. App. LEXIS 2081 (Ill. Ct. App. 1985).

Opinion

JUSTICE O’CONNOR

delivered the opinion of the court:

Defendant and third-party plaintiff, Youngstown Sheet & Tube Company (Youngstown), appeals from the trial court’s order granting summary judgment in favor of third-party defendant Correct Piping Company (Correct Piping) as to count II of Youngstown’s amended third-party complaint, which alleged an implied right of indemnity from Correct Piping. Youngstown also appeals the trial court’s denial of its motion for leave to amend its third-party complaint with a count alleging breach of contract. We affirm in part, reverse in part and remand.

This case arose out of an accident which occurred on the night of June 25, 1978, during the course of work being done at Youngstown’s steel plant located in Gary, Indiana. Correct Piping, an industrial piping contractor, had been called in by Youngstown, the owner of the steel manufacturing plant, to do some repair and maintenance work on the No. 1 reheat furnace at Youngstown’s No. 3 hot strip mill. Another piping contractor, Eichleay Corporation, who is also a defendant in the underlying suit, had begun the repair work on the No. 1 reheat furnace but had been discharged by Youngstown. On June 23, 1978, Youngstown personnel allegedly telephoned Correct Piping regarding the completion of repairs on the furnace. Correct Piping began staffing the project that same day. Youngstown and Correct Piping contracted on a time and material basis in which Correct Piping would invoice Youngstown for time spent and materials utilized for the repair project. A written purchase order invoice for the job was issued by Youngstown on June 28, 1978, three days after the accident and five days after Correct Piping started work on the project. The purchase order referred to the June 23 telephone conversation and stated that Correct Piping was to furnish necessary equipment, tools, supervision and pipefitters to complete the job. Allegedly, Youngstown and Correct Piping previously had done business in this manner.

The accident involving plaintiff Woodrow Talas took place at approximately 11:45 p.m. on June 25, 1978. Talas had been hired as a pipefitter by Correct Piping on June 23, 1978, to work the night shift, while Correct Piping was working around-the-clock on the project. During the 6 p.m. to 12 a.m. shift on Sunday, June 25, Talas was working in the basement underneath the No. 1 reheat furnace at the Youngstown plant. The basement is divided into a number of “bays” or compartments which were about 15 to 25 feet high with large pipes running through them. Talas worked in bay No. 1 with another Correct Piping pipefitter, Gene Klamczynski, from 6 p.m. to approximately 10:30 p.m. and then moved to bay No. 2. There was a scaffold approximately 10 feet off the ground in bay No. 2. This scaffold consisted of three 12-foot long boards laid on top of some large pipes and required a ladder to reach it. Shortly after starting work in bay No. 2, Talas and Correct Piping superintendent Larry Gregory looked for a 10-foot ladder among Correct Piping’s equipment but could only find a new 8-foot ladder, which Talas then took to bay No. 2. Ascending the ladder, Talas had to scramble off the ladder and onto the scaffolding in order to measure some pipes. On his second trip up the ladder, Talas attempted to climb up onto the scaffolding and hit his head on a pipe which had one end disconnected. He fell and sustained serious injuries.

On July 17, 1978, Talas and his wife brought suit against Youngstown and Eichleay Corporation, charging that Youngstown negligently failed to provide: (1) proper and adequate lighting; (2) proper and adequate scaffolding; (3) a safe clean working area; (4) proper supervision of the work; (5) proper coordination of the work of its contractors and subcontractors; (6) safe and proper access to the scaffold upon which he was working; and (7) negligently provided Talas with a scaffold that was dangerous when Youngstown knew or should have known the scaffolding was in a dangerous condition. Youngstown filed its amended answer denying it was negligent and raising several affirmative defenses.

On May 30, 1980, Youngstown filed its original third-party complaint against Correct Piping. Count I alleged breach of contract, count II alleged breach of express indemnity contract, and count III sounded in constructive indemnity. On June 8, 1981, Judge Gomberg dismissed counts I and II with prejudice, but did not find that there was "no just reason for delaying enforcement or appeal.” The court also struck count III but gave Youngstown leave to amend. On September 24, 1981, Youngstown filed an amended third-party complaint which consisted of one count alleging a right to indemnity based on the respondeat superior doctrine. Youngstown later added another count to its amended third-party complaint which sounded in implied indemnity and is now one of the subjects of this appeal. Correct Piping’s motion to dismiss counts I and II of the amended third-party complaint was denied. On December 28, 1982, Correct Piping moved for summary judgment on counts I and II which Judge Gomberg denied with respect to count I on October 13, 1983, but which he granted with respect to count II on December 22, 1983. On June 14, 1984, Youngstown sought leave to amend its amended third-party complaint in order to add a proposed count III alleging breach of contract. Judge Gomberg denied Youngstown’s motion for leave to amend in a final and appealable order. Youngstown now appeals that decision as well as Judge Gomberg’s decision to grant summary judgment with respect to count II alleging implied indemnity.

We find, and the parties concede, that under the criteria set forth in Ingersoll v. Klein (1970), 46 Ill. 2d 42, 262 N.E.2d 593, Indiana law governs the substantive issues raised by Youngstown’s third-party complaint. Illinois law governs the procedural aspects of the case since Illinois is the forum State. 46 Ill. 2d 42, 44-45.

Initially, we must decide whether the trial court erred in denying Youngstown’s motion for leave to amend its amended third-party complaint with a proposed amended count III which alleged that Correct Piping breached a contractual duty to perform the work in a safe manner. The parties have disputed whether or not the trial court’s previous dismissal with prejudice of original count I of the original third-party complaint which made substantially similar claims and allegations bars the proposed amendment. However, we need not and do not decide the issue because we would affirm the trial court’s denial of leave to amend even if we were to assume, arguendo, that the dismissal with prejudice of original count I did not act as a bar to the addition of proposed amended count III.

The decision as to whether to allow or deny an amendment rests within the sound discretion of the trial court (Montgomery Ward & Co. v. Wetzel (1981), 98 Ill. App. 3d 243, 423 N.E.2d 1170, appeal denied (1981), 85 Ill. 2d 567; Banks v. United Insurance Co. of America (1975), 28 Ill. App. 3d 60, 328 N.E.2d 167), and its decision will not be disturbed on review absent an abuse of that discretion (United Air Lines, Inc. v. Conductron Corp. (1979), 69 Ill. App. 3d 847,

Related

Chicago Land and Trust Company v, United Structural Systems of Illinois, Inc
2022 IL App (2d) 210299-U (Appellate Court of Illinois, 2022)
People Ex Rel. Ulrich v. Bosmann
664 N.E.2d 119 (Appellate Court of Illinois, 1996)
M. Ecker & Co. v. La Salle National Bank
645 N.E.2d 335 (Appellate Court of Illinois, 1994)
Sigma Companies, Inc. v. Regas
627 N.E.2d 256 (Appellate Court of Illinois, 1993)
Metzger v. New Century Oil & Gas Supply Corp. Income & Development Program
594 N.E.2d 1218 (Appellate Court of Illinois, 1992)
Bank of Northern Illinois v. Nugent
584 N.E.2d 948 (Appellate Court of Illinois, 1991)
Martin v. Yellow Cab Co.
567 N.E.2d 461 (Appellate Court of Illinois, 1990)
BC v. JC Penney Co., Inc.
562 N.E.2d 533 (Appellate Court of Illinois, 1990)
Starnes v. International Harvester Co.
539 N.E.2d 1372 (Appellate Court of Illinois, 1989)
Russ v. Pension Consultants Co.
538 N.E.2d 693 (Appellate Court of Illinois, 1989)
Century Universal Enterprises, Inc. v. Triana Development Corp.
510 N.E.2d 1260 (Appellate Court of Illinois, 1987)
Schwaner v. Belvidere Medical Building Partnership
508 N.E.2d 522 (Appellate Court of Illinois, 1987)
Harrington v. Chicago Sun-Times
502 N.E.2d 332 (Appellate Court of Illinois, 1986)
Berutti v. Dierks Foods, Inc.
496 N.E.2d 350 (Appellate Court of Illinois, 1986)
Lakeside Villas Homeowners Ass'n, Inc. v. Zale Const. Co., Inc.
495 N.E.2d 1100 (Appellate Court of Illinois, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
479 N.E.2d 1052, 134 Ill. App. 3d 103, 89 Ill. Dec. 46, 1985 Ill. App. LEXIS 2081, Counsel Stack Legal Research, https://law.counselstack.com/opinion/talas-v-youngstown-sheet-tube-co-illappct-1985.