Tuxedo Contractors, Incorporated v. Swindell-Dressler Company, a Division of Pullman, Incorporated

613 F.2d 1159, 198 U.S. App. D.C. 426, 1979 U.S. App. LEXIS 9421
CourtCourt of Appeals for the D.C. Circuit
DecidedDecember 26, 1979
Docket77-2114
StatusPublished
Cited by25 cases

This text of 613 F.2d 1159 (Tuxedo Contractors, Incorporated v. Swindell-Dressler Company, a Division of Pullman, Incorporated) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tuxedo Contractors, Incorporated v. Swindell-Dressler Company, a Division of Pullman, Incorporated, 613 F.2d 1159, 198 U.S. App. D.C. 426, 1979 U.S. App. LEXIS 9421 (D.C. Cir. 1979).

Opinion

SPOTTSWOOD W. ROBINSON, III, Circuit Judge:

Appellant, Tuxedo Contractors, Incorporated, brought suit in the District Court against appellees, Swindell-Dressler Company and Paul R. Jackson Construction Company, Incorporated, alleging tortious interference with a contract between appellant and Hartwick Construction Company (Hart-wick). After a bench trial, the court held that appellant had failed to establish sever *1161 al essential elements of its cause of action, entered judgment for appellees and dismissed the case with prejudice. 1 This appeal challenges the court’s factual and legal conclusions on two principal grounds. 2 We find the arguments advanced by appellant unpersuasive, and therefore affirm.

I

The undisputed facts may be briefly stated. Appellant and Hartwick negotiated an agreement 3 pursuant to which appellant prepared a bid for an asphalt repair contract with the District of Columbia, and Hartwick then submitted the bid as potential prime contractor. The agreement stated that Hartwick, if successful, would subcontract with appellant for all work to be performed, thus confining Hartwick’s obligation to provision of a performance bond and payment to appellant of a specified percentage of the receipts from the District. 4

Appellees, as a joint venture, also tendered a bid, 5 which proved to be lowest, and received notice that they had been awarded the repair contract. 6 After discovering these facts, appellant, which through Hart-wick had presented the second lowest proposal, 7 entered in Hartwick’s name a formal protest of the award on the ground that appellees’ bid was nonresponsive. 8 The protest was ultimately upheld, and thereupon the contract went to Hartwick. 9

In the interim, however, Hartwick had chosen to withdraw from its agreement with appellant and to give the subcontract to appellees. 10 Appellant contends that appellees induced Hartwick to make this decision, and that in doing so they wrongfully interfered with appellant’s contract with Hartwick. 11 Appellees, on the other hand, assert that they did not cause Hartwick’s repudiation and, moreover, that they had insufficient knowledge of the Tuxedo-Hart-wick agreement to be charged with any tort respecting it. 12

II

The District Court’s jurisdiction in this case rested solely on diversity of the parties’ citizenship. 13 Normally, then, we would first ascertain just whose local law is properly to be applied. 14 But the parties have not briefed the choice-of-law issue, and have not questioned the District Court’s apparent assumption that District of Columbia law controls. 15 In similar situations *1162 in the past we have sustained that court’s utilization of District law. 16 We do so here as well.

To recover under District of Columbia law on a theory of wrongful inducement of a breach of contract, the plaintiff “must show (1) a contract; (2) knowledge of the contract; (3) intentional procurement of its breach by the defendant; and (4) damages resulting from the breach.” 17 The District Court held that appellant had failed to prove the second and third elements and thus had not made out a prima facie case. 18 Appellant challenges these rulings, claiming that the court misapprehended the law and that its factual conclusions are without sufficient evidentiary support. 19 Our review of the record satisfies us that the District Court correctly interpreted the applicable substantive law 20 and that its findings of facts were not clearly erroneous. 21

The District Court found, first, that appellant had not proven “intentional pro-curement of [the] breach” 22 because it had failed to demonstrate that appellees’ actions substantially contributed to Hartwick’s decision to dishonor the agreement with appellant. 23 This pertains to the issue of causation, and is a determination of fact 24 which we may reverse only if the resolution is clearly erroneous. 25 The record affords no basis for such a conclusion.

Prior to any contacts with appellees, Hartwick had begun to have second thoughts about undertaking the repair contract with appellant. Jack Y. Matthews, the chief executive officer of Hartwick, testified that he was concerned about appellant’s ability to perform the construction work 26 and about Hartwick’s ability to obtain a performance bond in compliance with its side of the agreement with appellant. 27 Moreover, when appellees later approached Matthews, he felt that Hartwick was no longer bound by its promise to subcontract to appellant. 28 As a consequence of his *1163 misgivings, Matthews had even attempted to withdraw from the bid protest, though he was subsequently persuaded to continue it, 29 and he further avowed that at that time he probably did not intend to enter into a subcontract with appellant. 30 It was some three weeks after these events that appellees contacted Hartwick for the first time and sought to negotiate an agreement under which they, and not appellant, would execute the subcontract. 31

On the other hand, there was also evidence tending to show that, despite Matthews’ apprehensions, Hartwick would have kept its bargain with appellant had appellees not sown further doubts in Matthews’ already receptive mind 32 and at the same time offered him a more advantageous arrangement, under which Hartwick would not even have to provide a performance bond for the work. 33

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Legal Technology Group, Inc. v. Mukerji
District of Columbia, 2019
National Railroad Passenger v. Veolia Transportation Services, Inc.
791 F. Supp. 2d 33 (District of Columbia, 2011)
Pagonis v. Donnelly
929 F. Supp. 459 (District of Columbia, 1995)
Johns v. Rozet
141 F.R.D. 211 (District of Columbia, 1992)
Connors, Fiscina, Swartz & Zimmerly v. Rees
599 A.2d 47 (District of Columbia Court of Appeals, 1991)
Kaempfer v. Brown
109 B.R. 527 (District of Columbia, 1990)
Kenneth I. Brown v. Herman Miller, Inc.
890 F.2d 443 (D.C. Circuit, 1989)
Lewis v. Leo Buk Lhu
696 F. Supp. 723 (District of Columbia, 1988)
Woodward v. Dipalermo
686 F. Supp. 1 (District of Columbia, 1986)
Nancy H. Steorts v. American Airlines, Inc
647 F.2d 194 (D.C. Circuit, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
613 F.2d 1159, 198 U.S. App. D.C. 426, 1979 U.S. App. LEXIS 9421, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tuxedo-contractors-incorporated-v-swindell-dressler-company-a-division-cadc-1979.