R. A. Weaver & Associates, Inc. v. Haas & Haynie Corp.

663 F.2d 168, 213 U.S. App. D.C. 404
CourtCourt of Appeals for the D.C. Circuit
DecidedDecember 4, 1980
DocketNos. 78-1205, 78-1283
StatusPublished
Cited by7 cases

This text of 663 F.2d 168 (R. A. Weaver & Associates, Inc. v. Haas & Haynie Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
R. A. Weaver & Associates, Inc. v. Haas & Haynie Corp., 663 F.2d 168, 213 U.S. App. D.C. 404 (D.C. Cir. 1980).

Opinion

Opinion PER CURIAM.

PER CURIAM:

At issue are judgments in favor of two plaintiffs, R. A. Weaver & Associates, Inc. (Weaver) and International Stone & Erectors, Inc. (ISE), against two defendants, Blake Construction Company, Inc. (Blake) and Haas & Haynie Corporation,1 for damages for breach of contract and tortious conversion of property.2 The District Court predicated the judgments on jury verdicts which, save in one respect, the court refused to set aside. We sustain the award for the conversion found. We reverse, however, the judgments for breach of contract and remand that aspect of the litigation for further proceeding.

I. BACKGROUND

In 1971, the General Services Administration (GSA) invited bids for the construction of a federal office building in the District of Columbia designated as the “South Portal” [406]*406site project.3 The architectural plans for the project specified black slate from Maine or Virginia as the material to be used in paving the plaza and driveways.4 Blake submitted a lump-sum bid incorporating the price quoted to it for a Virginia black slate meeting the specifications.5

GSA awarded the construction contract to Blake in 1972, whereupon Blake commenced negotiations with suppliers for the purchase of the slate required for the plaza and driveways.6 Weaver and ISE were among those interested in supplying slate for the project. Weaver quoted to ISE a price for Nor Cashire slate — a blue-black slate to be quarried in England and fabricated in the United States7 — and ISE in turn proposed its use to Blake.8 As a result, on March 19, 1972, Blake and ISE entered into a purchase-order contract,9 the terms of which are vital in this litigation. The contract evidenced ISE’s agreement to furnish, for a stated price, Nor Cashire slate and domestic granite 10 “in full and complete accord with the Specifications and Drawings prepared by the Architect and forming a part of the Contract, for subject project, between the Contractor and the Owner.”11 More finely, the parties stipulated that “[t]his contract ... is subject to the approval by the Owner of imported but domestically fabricated ‘Nor Cashire’ Blue Black Slate meeting the requirements of the ‘Buy America [American] Act;’ ”12 still later, they reiterated that “[t]he items to be provided herein are subject to approval by the Owner.”13 The contract was silent, however, on the time within which approval was to be secured. To boot, a nearly con-, temporaneous letter from ISE to Blake amending the purchase order stated:

The contract is based upon the approval of Nor Cashire Slate by the Owner. [We are] to prepare the necessary documents showing how [we] propose[] to meet the requirements of the “BUY AMERICA [American] ACT.” This also [may be] subject to the Owner’s approval if requested. Should we not secure approval of the above, it is understood that the contract will be void without recourse [407]*407to either party. We stand ready to assist to secure approval.14

A bit later, ISE contracted with Weaver for the purchase of Nor Cashire on terms similar to those in the Blake-ISE agreement.15

In June, 1973, in accordance with the specifications governing construction; test data, certifications and samples of Nor Ca-shire slate were furnished to supervising architects for approval. On July 17, 1973, however, the architects disapproved the proposed slate for three reasons.16 The modulus of elasticity, they stated, was substantially lower than the value required;17 the appearance of the slate, they added, was unsatisfactory;18 furthermore, they pointed out, the slate was a foreign rather than a domestic product.19

Promptly, on July 20, Blake objected, and on August 19, transmitted a Weaver-prepared letter with attachments protesting the architects’ decision.20 About November 1, Blake augmented these submissions with a formal petition for approval of the slate under the Buy American Act.21 Meanwhile, the architects modified their July 17 position. In a letter to GSA’s contracting officer dated September 11, 1973, they expressed the opinion that the Nor Cashire slate “substantially meets the requirements of” the specifications;22 “[pjrovided that the test data submitted applies to the Grade ‘A’ and to the Select Stock, both samples would have the physical properties required for paving stones.”23

Walter E. Huber, however, the GSA contracting officer who alone had authority to substitute Nor Cashire slate for the slate originally designated,24 did not act immediately to approve the slate. Though perhaps prepared to authorize the change if need be,25 he desired instead to investigate with Blake the possibility of substituting granite for slate with an equitable adjustment making the substitution economically feasible for GSA.26 For this reason, three months went by without any decision by the contracting officer as to whether Nor Cashire slate would be accepted. On December 14, 1973, after unfruitful discussion of the matter with ISE, Blake gave formal notice that it was cancelling its contract with ISE for nonsatisfaction of the contractual requirement of GSA approval of the Nor Cashire slate.27 Some months later, after negotiations with Blake, GSA substituted charcoal black granite for slate as the paving material for the plaza and driveways.28

One more episode completes the factual background. Weaver had prepared a 13-page set of shop drawings showing the size and placement of slate and granite to be [408]*408used in the South Portal site project.29 Weaver had submitted these drawings to ISE, and ISE had delivered them to Blake. After cancellation of the Blake-ISE contract, Blake turned the drawings over to Cold Spring Granite Company (Cold Spring), the supplier of the granite ultimately employed in the project, a step by which Blake benefited to the tune of a $13,000 credit on Cold Spring’s contract price to Blake.30 Later, Blake offered ISE and Weaver $10,000 for the drawings, but only on condition that they execute a full release of all claims against Blake arising out of the contract cancellation.31 Not surprisingly, ISE and Blake declined this proposition.32

In 1975, ISE, Weaver and another33 instituted an action in the District Court against Blake and others,34 and the case reached trial before a jury. Claims of breach of contract and tortious conversion of the shop drawings survived a defense motion for a directed verdict,35 the court reserving decision on the motion.36

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
663 F.2d 168, 213 U.S. App. D.C. 404, Counsel Stack Legal Research, https://law.counselstack.com/opinion/r-a-weaver-associates-inc-v-haas-haynie-corp-cadc-1980.