Stevens v. Howard D. Johnson Co.

181 F.2d 390, 1950 U.S. App. LEXIS 2619
CourtCourt of Appeals for the Fourth Circuit
DecidedApril 11, 1950
Docket6038_1
StatusPublished
Cited by327 cases

This text of 181 F.2d 390 (Stevens v. Howard D. Johnson Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Stevens v. Howard D. Johnson Co., 181 F.2d 390, 1950 U.S. App. LEXIS 2619 (4th Cir. 1950).

Opinion

PARKER, Chief Judge.

This is an appeal by the plaintiffs from a summary judgment for the defendant in an action to recover damages for breach of a rental contract. Plaintiffs were the owners of a lot which they had purchased and leased to defendant under an agreement to erect a building thereon for which the defendant was to pay the cost of construction above a certain amount. Plaintiffs alleged that defendants had breached the contract by failure to approve contracts for the construction of the building or to take action looking to contracts for construction which it would approve. Defendant denied any obligation to proceed under the contract on the ground that it had not approved the cost of construction of the building and was not liable in the absence of such approval. Plaintiffs demanded a jury trial and defendant moved for summary judgment on affidavits. From the granting of the motion for summary judgment this appeal is taken.

The pleadings and affidavits disclose that plaintiffs had an option to purchase a lot of land near Staunton, Virginia, upon which defendant desired to operate a restaurant, and that they leased it to defendant and, relying upon the lease, proceeded to purchase ít so as to comply with the lease. The lease was not an executory contract to take effect in the future, but an out *392 and out lease of the property for a term of ten years with privilege of renewal at the same rental for two additional five year periods. The rental provided was $1,000 per year, plus 10% of the total cost of the new building to be erected on the property, plus 6% of the gross sales of the restaurant to be conducted therein. Other provisions of the contract showing that it' was something more than a mere provisional or executory agreement were sections relating to taxes, improvements, trade fixtures, public liability, plate glass insurance, remedies for breach, etc. The section relating to the construction of the new building, which is the section of importance here, is as follows:

■ “Section II. New Building.
“Lessors agree to construct on the demised premises, a building for the use and occupancy of the lessee, such building to be erected in accordance with approved plans and specifications, which are to be identified by the initialing thereof by the parties to this agreement.
“The total cost of construction, including materials, fees, supervision and all other necessary and incidental expenses, shall be borne by the lessors, up to, but not exceeding forty thousand dollars ($40,000.00). All expenses of construction in excess of said sum of forty thousand dollars ($40,-000) shall be borne by the lessee, but payment by lessee of such additional construction cost shall not operate, expressly or impliedly to create any equity for the lessee in the demised premises. And the lessee expressly covenants, to indemnify and save the lessors harmless from the payment of any of the costs of such construction in excess of the sum of forty thousand dollars ($40,000.00). It is agreed, however, that all contracts and expenditures relating to the construction in excess of forty thousand dollars ($40,000) shall be submitted to and approved in writing by the lessee, before the same become effective.
“Construction shall be commenced as soon as practicable after the execution of this lease, and lessors and lessees agree to diligently prosecute such construction to completion.” ■ •

Defendant admits in its answer that it was to prepare the plans for the building; and it appears from the affidavits offered in connection with the motion for summary judgment that such plans were prepared and were approved and initialed by the parties as the contract provided. Contractors had indicated that the cost of constructing the building completed would be around $35,000 or $40,000; but, when bids were called for on the plans and specifications, the lowest bid submitted was $54,-000, and this did not include certain items which it was estimated would aggregate around $15,000. An affidavit submitted by plaintiffs shows that upon receipt of these bids, defendant refused to approve them and, notwithstanding the request of plaintiffs that the plans and specifications be revised so as to provide a building at a cost which would be approved, refused to take any action along this line or any other action looking to the carrying out of the contract, but on ■ the contrary indicated that it would not proceed further thereunder because a change in the location of a highway had made the property undesirable as a site for a restaurant. In this connection, there was attached to the affidavit a letter of defendant clearly indicating that his change in the highway, and not the matter of cost, was the basis of the refusal to go forward. The letter was as follows:

“I received your letter regarding the Staunton location and can fully appreciate your position. On the other hand, I hope you appreciate our position in that when we signed the lease, we had a rough estimate from Valley Construction of $35,000 and as I have pointed out before, it is economically unwise for us'to invest money in the actual building, because that increases our rent by just that much.
“However, there is one aspect which is more serious than that of the cost of the building and that is recent information which has come to me of the change in the highway. I understand from information which our Mr. O’Keefe received from thé city manager of Staunton, that the road change is not only contemplated but actual contracts have been let. This by-pass will *393 start half a mile above our location and will divert all traffic away from our location. In view of this, I question whether or not it would be wise to go ahead with this investment until this matter has been thoroughly cleared up. It might he a great deal better if we postponed this particular location until we knew exactly what was going to happen, and at that time, if it did not look favorable, — to invest the same amount of money elsewhere. It would not do we nor you any good to have a location where we could not make any money.”

The judge below was of opinion that ■there was no issue of fact in the case on the theory that defendant had an absolute right not to approve a construction cost for the new building in excess of $40,000.00, and that it appearing that the construction cost of the building upon which the parties had agreed was in excess of that amount, and the defendant having refused to approve it, no basis of liability under the contract remained. In this we think there was error.

We quite agree that the provision of the contract upon which defendant relies, viz., that “all contracts and expenditures relating to the construction in excess of $40,000 shall be submitted to and approved in writing by the lessee before the same become effective”, reserves to defendant the right not to approve expenditures in excess of that amount; but this does not authorize summary judgment for defendant on the theory that it may absolutely repudiate the contract and refuse to proceed with it further merely because the cost of constructing a building in accordance with plans that it has furnished are greater than anticipated, and certainly not because a change in the location of a highway has rendered the location less desirable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moore v. Life Insurance Co. of North America
708 F. Supp. 2d 597 (N.D. West Virginia, 2010)
Walker v. National RR Passenger Corp.
703 F. Supp. 2d 495 (D. Maryland, 2010)
Ramseur v. United States
587 F. Supp. 2d 672 (D. Maryland, 2007)
Thornhill, Inc. v. Nvr, Inc.
422 F. Supp. 2d 646 (N.D. West Virginia, 2006)
Westfield Insurance v. Paugh
390 F. Supp. 2d 511 (N.D. West Virginia, 2005)
Haught v. the Louis Berkman, LLC
377 F. Supp. 2d 543 (N.D. West Virginia, 2005)
Parramore v. Tru-Pak Moving Systems, Inc.
286 F. Supp. 2d 643 (M.D. North Carolina, 2003)
Kress v. Food Employers Labor Relations Ass'n
285 F. Supp. 2d 678 (D. Maryland, 2003)
Odyssey Travel Center, Inc. v. RO Cruises, Inc.
262 F. Supp. 2d 618 (D. Maryland, 2003)
Medlock v. Rumsfeld
336 F. Supp. 2d 452 (D. Maryland, 2003)
havePower, LLC v. General Electric Co.
256 F. Supp. 2d 402 (D. Maryland, 2003)
Mikeron, Inc. v. Exxon Co., U.S.A.
264 F. Supp. 2d 268 (D. Maryland, 2003)
Rachel-Smith v. FTData, Inc.
247 F. Supp. 2d 734 (D. Maryland, 2003)
Paukstis v. Kenwood Golf & Country Club, Inc.
241 F. Supp. 2d 551 (D. Maryland, 2003)
Lurie v. Meserve
214 F. Supp. 2d 546 (D. Maryland, 2002)
Gaus v. Consol, Inc.
294 F. Supp. 2d 815 (N.D. West Virginia, 2002)
Maynard v. Westport Ins. Corp.
208 F. Supp. 2d 568 (D. Maryland, 2002)
Gray v. Metts
203 F. Supp. 2d 426 (D. Maryland, 2002)
Curtis v. Pracht
202 F. Supp. 2d 406 (D. Maryland, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
181 F.2d 390, 1950 U.S. App. LEXIS 2619, Counsel Stack Legal Research, https://law.counselstack.com/opinion/stevens-v-howard-d-johnson-co-ca4-1950.