Tull v. Gundersons, Inc.

709 P.2d 940, 52 A.L.R. 4th 699, 1985 Colo. LEXIS 537
CourtSupreme Court of Colorado
DecidedDecember 2, 1985
Docket84SC57
StatusPublished
Cited by88 cases

This text of 709 P.2d 940 (Tull v. Gundersons, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tull v. Gundersons, Inc., 709 P.2d 940, 52 A.L.R. 4th 699, 1985 Colo. LEXIS 537 (Colo. 1985).

Opinion

DUBOFSKY, Justice.

We granted certiorari to review the court of appeals’ decision in Gundersons, Inc. v. Tull, 678 P.2d 1061 (1983) concerning the amount of proof necessary to prove lost profits in an action for breach of contract to construct a golf course. The court of appeals directed the Larimer County District Court to enter an award of damages based on lost profits, equipment leasing costs, and mitigation expenses. We affirm that decision in part, reverse in part, and remand the case for the district court to make further factual determinations.

The plaintiff, Gundersons, Inc., is a golf course construction company authorized to do business in Colorado. The defendants are Ptarmigan Investment Company (Ptarmigan) and its partners. On July 26, 1979, Ptarmigan accepted Gundersons’ bid for construction of a golf course in Larimer County. Gundersons began work on the *943 project without a contract on August 6, 1979. On August 30, Ptarmigan and Gun-dersons executed a construction agreement. Under the agreement, Ptarmigan was responsible for obtaining financing for the construction.

Gundersons continued to work on the project until the end of November when bad weather forced it to suspend operations. Prior to the shutdown, Gundersons had received, in accordance with the construction agreement, monthly payments for work completed, less a 10% retainage withheld by Ptarmigan. Because Ptarmigan was unable to obtain financing to complete the project, Gundersons never resumed work; instead, Gundersons filed this breach of contract action against Ptarmigan.

After trial, the district court concluded that the August 30 agreement between the parties was a valid and enforceable contract that had been breached by Ptarmigan. The district court entered in Gundersons’ favor a judgment of $43,504, the amount withheld from payment by Ptarmigan as retainage, plus interest. However, the district court denied Gundersons’ damages based on lost profits because the court concluded that the evidence of lost profits presented by Gundersons did “not meet the burden of proof required.” The court further concluded that Gundersons was not entitled to damages for the costs of leasing equipment used in the project and for costs involved in Gundersons’ efforts to mitigate damages by finding other work.

Gundersons appealed the judgment of the district court on the damages issues. The court of appeals held that as a matter of law Gundersons had established lost profits with sufficient certainty and that the district court erred in refusing to award damages based on this item. The court of appeals also held that Gundersons was entitled to damages for equipment leasing costs and mitigation expenses.

I.

We agree with the court of appeals that Gundersons met its burden of proving that it was entitled to an award of damages. Although an award of damages cannot be based on mere speculation or conjecture, once the fact of damage has been established with the requisite degree of certainty, uncertainty as to the amount of damages will not bar recovery. Peterson v. Colorado Potato Flake and Mfg. Co., 164 Colo. 304, 309, 435 P.2d 237, 239 (1967); Donahue v. Pikes Peak Auto Co., 150 Colo. 281, 287-88, 372 P.2d 443, 446-47 (1962).

Here Gundersons was only required to establish the fact of damage with reasonable certainty. 1 And while there are conflicting views of the meaning of the reasonable certainty standard, 2 we think the standard should be interpreted as imposing on a plaintiff the burden of proving the fact of damage by a preponderance of the evidence. As we stated in Riggs v. McMurty, 157 Colo. 33, 39, 400 P.2d 916, 919 (1965):

It is of course true that monetary reparation cannot be based upon mere speculation, but on the other hand such need not be proven with mathematical certainty. It is sufficient if the plaintiff establishes by a preponderance of the evidence that he has in fact suffered damage or *944 that his rights have been infringed and that his evidence in this regard provides a reasonable basis for a computation of the damage so sustained. 3

The parties agree that the applicable measure of damages is the amount of profit lost by Gundersons as a result of Ptarmigan’s breach of contract. The formula for determining lost profits in actions involving breach of a construction contract was set out in Comfort Homes v. Peterson, 37 Colo.App. 516, 518-19, 549 P.2d 1087, 1089-90 (1976):

The amount of ... damages has been described as ... the contract price less (1) any payments made ... on the contract, and (2) what it would have cost the builder if it had completed the [project] in accordance with the contract.

At trial, Gundersons presented estimates of lost profits ranging from $292,662 to $302,585. 4 These estimates were derived in accordance with the Comfort Homes formula.

The defendants assert that Gundersons’ estimates of completion costs do not provide a sufficiently certain foundation for an award of damages. In support of their assertion, they refer to McCormick on Damages, Ch. 26 § 165 at 644 (1935) for the proposition that

The difficulties of proving the prospective cost, that is, the further amount that it would cost to finish the job, cannot be adequately met in the case of a substantial building contract by merely placing the builder or his superintendent on the stand to give his lump sum opinion or estimate. This may be admissible, but, to warrant a finding, the estimate should include detailed figures as to the cost of the different materials and operations, based, if possible, on “percentage of completion” reports. (Footnotes omitted.)

Whatever the force of this rule might be under other circumstances, we do not think that in this case it should totally preclude an award of damages in Gundersons’ favor.

Here, as the court of appeals noted, Gun-dersons did not rely solely on Wallace Gun-derson’s lump sum estimate of lost profits. Gundersons’ estimate was broken down into excavation, greens construction, drainage, bridges, irrigation, grassing, cart paths, abutments, and bunker sand, and the costs of completing each of these operations were listed and admitted into evidence. The defendants rebutted Gunder-sons’ cost-of-completion estimates as to excavation and greens construction. The defendants presented evidence that the cost to complete the excavation work would amount to $180,000 rather than the $55,000 claimed by Wallace Gunderson.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peo v. Rodriguez
Colorado Court of Appeals, 2025
Sanchez v. Rains Precision Motorsports, Inc.
2025 COA 40 (Colorado Court of Appeals, 2025)
Smart v. Stropas
Colorado Court of Appeals, 2025
KND Holdings LLC v. Manis
D. Colorado, 2025
& 23CA0663 Duran v. Montoya
Colorado Court of Appeals, 2024
Mayotte v. U.S. Bank
985 F.3d 1248 (Tenth Circuit, 2021)
Lehouillier v. Gallegos
2019 CO 8 (Supreme Court of Colorado, 2019)
Boxer F2 v. Bronchick
Tenth Circuit, 2018
Olivero v. Trek Bicycle Corp.
291 F. Supp. 3d 1209 (D. Colorado, 2017)
Rice's Lucky Clover Honey, LLC. v. Hawley
700 F. App'x 852 (Tenth Circuit, 2017)
Xtreme Coil Drilling Corp. v. Encana Oil & Gas, Inc.
958 F. Supp. 2d 1238 (D. Colorado, 2013)
Banning v. Prester
2012 COA 215 (Colorado Court of Appeals, 2012)
Sterenbuch v. Goss
266 P.3d 428 (Colorado Court of Appeals, 2011)
Club Matrix, LLC v. Nassi
284 P.3d 93 (Colorado Court of Appeals, 2011)
Ner Tamid Congregation of N. Town v. Krivoruchko
660 F. Supp. 2d 927 (N.D. Illinois, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
709 P.2d 940, 52 A.L.R. 4th 699, 1985 Colo. LEXIS 537, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tull-v-gundersons-inc-colo-1985.