Trett v. Oklahoma Gas & Electric Co.

1989 OK 54, 775 P.2d 275, 1989 Okla. LEXIS 60, 1989 WL 30168
CourtSupreme Court of Oklahoma
DecidedApril 4, 1989
Docket67352
StatusPublished
Cited by18 cases

This text of 1989 OK 54 (Trett v. Oklahoma Gas & Electric Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trett v. Oklahoma Gas & Electric Co., 1989 OK 54, 775 P.2d 275, 1989 Okla. LEXIS 60, 1989 WL 30168 (Okla. 1989).

Opinions

LAVENDER, Justice:

Appellee R. Thomas Trett was an employee of The Dolese Company and was employed at that company’s quarry operations in southern Oklahoma. One of the company’s operations was the quarrying of stone for use as railway ballast. At one of these quarry operations the stone had been exhausted and Dolese undertook plans to begin quarrying stone from an area to the east, on the other side of a county road. In order to make use of the rock crushing unit and rail loading facilities on the west side of the road, Dolese undertook plans to build an overpass bridge over the county road so that Dolese tracks could bring the stone from the east side to the facilities on the west side without worrying about traffic on the public road. Dolese began construction on this project around the middle of July in 1981.

A high voltage line owned by O.G. & E. paralleled the county road some distance to the west. Because Dolese intended to raise the grade for their road to make use of the bridge, the tracks using the completed road would be in danger of coming into contact with the electric lines. Accordingly, Dolese contacted O.G. & E. on July 17, 1981 concerning the need to relocate the line. An O.G. & E. employee met with Dolese officials at the work site shortly thereafter to assess Dolese’s needs. On August 4, 1981 O.G. & E. sent proposed estimates to Dolese on various methods of relocation. On August 11, 1981 Dolese sent a check to O.G. & E. to cover the least expensive relocation alternative accompanied by a note expressing pleasure that O.G. & E. had agreed to commence work on the relocation the week of August 24, 1981.

On August 19, 1981, Dolese was well along in the construction of the new road and the bridge. On this morning Dolese employees, including appellee Trett, were engaged in moving reinforced concrete panels for placement in the bridge construction. Some fill material had already been [277]*277placed on the new road under the O.G. & E. lines. The Dolese Superintendent who was directing the panel moving operations had had one of the ten ton panels picked up by a cable sling on a front end loader. The panel was picked up off the ground and the superintendent directed the loader to back and turn with the panel in the air. Appel-lee Trett was one of two employees who were steadying the panel as it was moved. Appellee Trett was holding on to a steel reinforcing bar on the panel when the front end loader inadvertently backed into the electric lines and contact was made between the raised loader bucket, from which the panel was slung, and one of the energized electric lines. Appellee Trett received a severe electric shock as a result of this contact.

Appellee Trett brought the present action against O.G. & E. alleging that negligence on the part of O.G. & E. had brought about his injuries. The matter was tried to a jury which returned a verdict finding Trett to be 2.5 percent contributarily negligent and finding O.G. & E. to be 34.17 percent negligent and awarding Trett $350,000 in damages.1 O.G. & E. appealed, arguing that Trett’s evidence did not support the verdict and that O.G. & E.’s motion for directed verdict should have been granted and that the trial court erred in not giving two instructions requested by O.G. & E.2 The Court of Appeals, Oklahoma City Divisions, to which this case was originally assigned, affirmed, finding no error as to the points raised by O.G. & E.

O.G. & E. petitioned for certiorari from this Court, arguing that the Court of Appeals had failed to apply the proper standards of review as to the question of whether the evidence supported the jury verdict and that the Court of Appeals had erroneously dealt with the instruction issues.

In affirming the judgment of the trial court the Court of Appeals stated that it did not find the contractual agreement between O.G. & E. and Dolese to totally insulate O.G. & E. from liability. The court merely stated that the question of liability was properly submitted to the jury. As pointed out by O.G. & E. in its petition for certiorari, the proper standard to be applied when the sufficiency of the evidence to support a jury verdict is raised is whether there is any evidence to support the judgment for the party against whom the motion for directed verdict is made.3 In ruling on such motion a trial court must consider as true all the evidence and all the inferences reasonably drawn therefrom favorable to the party against whom the motion is made and any conflicting evidence favorable to the movant must be disregarded.4 In reviewing the trial court’s ruling the appellate court must examine the record and make a determination as to whether there is any evidence reasonably tending to support the judgment.5 Here it does not appear from the Court of Appeals’ opinion that such an examination of the record was made. We have therefore previously granted certiorari and now undertake the appropriate review of the questions presented.

On appeal O.G. & E. argues that Trett failed to present any evidence to support a finding that O.G. & E. had breached a duty owed to Trett.6 Trett argues that a duty on O.G. & E.’s part, and a breach of that [278]*278duty, was established on two evidentiary points. The first was that O.G. & E.’s lines were allowed to hang at a dangerously low level. The second was that O.G. & E. failed to move the lines in a timely fashion following Dolese’s request.

On the issue of the height of O.G. & E.’s lines, Trett introduced the testimony of himself and several of his co-workers to the effect that, in their opinions, the lines were dangerously low. However, from this testimony it was also clear that a front end loader, with its bucket down in a normal position could drive under the lines with clearance. The only evidence of the height of the loader was submitted by O.G. & E. and established that the distance from the ground to the top of the loader’s cab was fifteen feet, ten inches. The only specific evidence regarding the height of the O.G. & E. lines was also submitted by O.G. & E. and was to the effect that the O.G. & E. line carrying the charge which was contacted by the front end loader was eighteen feet five inches above the level of the fill added by Dolese at the line’s lowest point, and from the top of the fill to the point of contact of the accident was approximately nineteen and one half feet. The testimony of O.G. & E.’s witnesses also established that the line height exceeded National Electrical Safety Code requirements as imposed on O.G. & E. by the Oklahoma Corporation Commission rules on electrical transmission lines by a minimum of three and a half feet prior to Dolese’s placement of fill underneath the lines.

On the issue of O.G. & E.’s timeliness of response to the request to move the lines the only evidence submitted by Trett was his and his wife’s testimony that on the evening of the day of the accident, two of Trett’s supervisors at the Dolese quarry stopped by and told him that they had attempted to have O.G. & E. move the lines earlier but that the O.G. & E. officials had stated that they were “too busy.” While the two supervisors from Dolese were subject to examination at trial, there was no attempt to identify the O.G. & E. officials who allegedly made the statements attributed to them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Roberson v. Wal-Mart Inc
W.D. Oklahoma, 2022
Graybeal v. Martin Sand & Gravel
2008 OK CIV APP 28 (Court of Civil Appeals of Oklahoma, 2007)
Thomason v. Pilger
2005 OK 10 (Supreme Court of Oklahoma, 2005)
Fuller v. Pacheco
2001 OK CIV APP 39 (Court of Civil Appeals of Oklahoma, 2001)
Myers v. Maxey
915 P.2d 940 (Court of Civil Appeals of Oklahoma, 1996)
Shelley v. Kiwash Electric Cooperative, Inc.
1996 OK 44 (Supreme Court of Oklahoma, 1996)
Taylor v. Payne
1994 OK CIV APP 40 (Court of Civil Appeals of Oklahoma, 1994)
Rowell v. El Reno Junior College Foundation, Inc.
1993 OK 170 (Supreme Court of Oklahoma, 1993)
McMeakin v. Roofing & Sheet Metal Supply Co. of Tulsa
1990 OK CIV APP 101 (Court of Civil Appeals of Oklahoma, 1990)
Trett v. Oklahoma Gas & Electric Co.
1989 OK 54 (Supreme Court of Oklahoma, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
1989 OK 54, 775 P.2d 275, 1989 Okla. LEXIS 60, 1989 WL 30168, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trett-v-oklahoma-gas-electric-co-okla-1989.