Transpac Construction Co., Inc., a California Corporation v. Clark & Groff, Engineers, Inc.

466 F.2d 823, 1972 U.S. App. LEXIS 7987
CourtCourt of Appeals for the Ninth Circuit
DecidedAugust 10, 1972
Docket25485, 26306
StatusPublished
Cited by6 cases

This text of 466 F.2d 823 (Transpac Construction Co., Inc., a California Corporation v. Clark & Groff, Engineers, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Transpac Construction Co., Inc., a California Corporation v. Clark & Groff, Engineers, Inc., 466 F.2d 823, 1972 U.S. App. LEXIS 7987 (9th Cir. 1972).

Opinion

HAMLEY, Circuit Judge:

Transpae Construction Co., Inc. (Transpae) brought this Oregon diversity action against Umpqua Basin Water Association, Inc. (Umpqua), Clark & Groff, Engineers, Inc. (Clark & Groff), and Arthur V. Faulkner, to recover damages in the sum of eight hundred and fifteen thousand dollars for negligent and intentional interference with the performance of a contract. The contract is one under which Transpae undertook to install, for Umpqua, a pipeline for a domestic water supply system in Rose-burg, Oregon. Clark & Groff engineered the water supply system and supervised its installation. Faulkner served as Umpqua’s resident engineer on the project.

A trial was had before United States District Judge Gus J. Solomon on limited issues, including the issue of whether Umpqua and Transpae compromised and settled Transpac’s claim against Ump-qua. As aresult of this trial, and on October 22, 1969, Judge Solomon entered findings of fact (amended November 17, 1969), conclusions of law, and a judgment dismissing the action as to Umpqua. 1 Transpae took a timely appeal from this judgment.

On March 13, 1970, the parties entered into a stipulation under which the action was dismissed as to Faulkner. After entry of a second pretrial order 2 pertaining to Transpac’s claims against Clark & Groff, Clark & Groff moved for summary judgment in its favor. This motion was made on the ground that, under the undisputed facts, the compromise and settlement which had operated to release Umpqua from liability to Transpae, also served to release Clark & Groff from liability to Transpae. The parties argued the motion before United States District Judge (now Circuit Judge) Alfred T. Goodwin, who thereupon granted the motion. Transpae filed a timely notice of appeal, and Transpac’s two appeals have been consolidated for argument and disposition in this court. Appellee Umpqua has made no appearance in this court.

On appeal, Transpae first argues that Judge Solomon erred in finding and concluding that Umpqua and Transpae had, by agreement of March 15, 1967, fully settled and compromised all claims which Transpae here asserts against Umpqua.

On August 29, 1966, Transpae and Umpqua entered into a contract for the installation, by Transpae, of a domestic water supply system for the agreed amount of $695,864.54. Shortly thereafter work began under the contract. Commencing in early October 1966, various disputes arose between Transpae and Umpqua concerning the performance of each party to the contract. Judging by Transpac’s contentions set forth in the original pretrial order, Transpac’s grievances which were ap *825 parently dealt with in these disputes covered a wide range, as summarized in the margin. 3

Judge Solomon found and concluded that, on March 15, 1967, Transpac and Umpqua reached an agreement by which they intended to and did settle all claims that Transpac had against Umpqua, including those arising out of tortious acts as well as from breach of contract. The reference here was to a letter dated March 15, 1967, which had been dictated by Transpac’s attorney, Dudley C. Walton, in the presence of Umpqua’s attorney, Warren A. Woodruff. The pertinent part of this letter is quoted in the margin. 4 In the other portions of the letter new contractual arrangements were specified adjusting contract price payments and deleting items of work that the contractor need not perform.

In contending that the letter of March 15, 1967 did not constitute a release of all of Transpac’s claims against Ump-qua, Transpac asserts that the letter resolved only the items concerning which Transpac had demanded arbitration, and not the additional items involved in this lawsuit. Transpac calls attention to the statement, in the second paragraph of the March 15, 1967 letter, that the “dispute . . . has been the subject of claim and demand for payment by Transpac . . . under the terms of the *826 contract providing for arbitration . . and also comments that the letter is not couched in terms of a general release.

In our opinion the March 15, 1967 letter is ambiguous insofar as the scope of the settlement is concerned. It is true that the term “release” is not used, and that the second paragraph relates the dispute to Transpac’s arbitration demand. But the first paragraph of the letter states that the dispute had arisen by reason of changes ordered by the owner “and other conditions and circumstances under which the contractor performed the work ordered by the owner.” All ' of Transpac’s grievances against Umpqua asserted in this action, as summarized in note 3, pertain to “conditions and circumstances under which the contractor performed the work ordered by the owner.”

By reason of this ambiguity it was entirely proper for the parties to produce extrinsic evidence bearing upon the scope of the settlement memorialized by the March 15, 1967 letter, and they proceeded to do so. This evidence was both documentary and oral. After considering this evidence, the trial court found that, during the negotiations, the parties considered all claims which Transpac had against Umpqua. While Transpac challenges this finding of fact, we are convinced that it is not clearly erroneous. In our opinion, save for the considerations to be explored below, this finding taken in conjunction with the wording of the letter, warranted Judge Solomon in concluding that the March 15, 1967 letter constitutes a full and final settlement of all claims which Transpac is asserting against Umpqua.

But Transpac argues that, under Oregon law, a release is not binding unless it results from a meeting of the minds and unless it is executed by the party releasing a claim with knowledge of what he is signing and with the intent to discharge the asserted liability. Transpac then refers to testimony by Transpac’s attorney, Walton, that at the time the settlement negotiations were in progress, he was aware that Transpac wanted to be in a position to assert tort claims against Umpqua after the March 15, 1967 settlement had been effectuated. Transpac also notes that, at that time, Walton did not know what Umpqua's attorney believed, “but suspected that Umpqua and its attorney thought they were settling all claims.” Judge Solomon found as to this matter:

“Although plaintiff knew that defendant Umpqua relied on the settlement agreement as a full and final settlement of all disputes between the parties, plaintiff did not disclose to defendant Umpqua that any claims were excluded from the settlement.”

It thus appears that Transpac is urging that, under Oregon law, one party to an executed settlement agreement, although knowing before execution that the other party considers that the written agreement will operate as a full release, may defeat that expectation by secretly intending that the settlement be of limited scope. We do not believe Oregon decisional law requires such an unjust result. We further observe that the argument proves too much because if there were no “meeting of minds” under this theory, it would operate to render the settlement entirely inoperative instead of merely limiting its scope. See Brown v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
466 F.2d 823, 1972 U.S. App. LEXIS 7987, Counsel Stack Legal Research, https://law.counselstack.com/opinion/transpac-construction-co-inc-a-california-corporation-v-clark-groff-ca9-1972.