Lester Cox v. City of Freeman, Missouri, and C. Kenneth Maib

321 F.2d 887, 7 Fed. R. Serv. 2d 945, 1963 U.S. App. LEXIS 4586
CourtCourt of Appeals for the Eighth Circuit
DecidedJuly 19, 1963
Docket17196
StatusPublished
Cited by31 cases

This text of 321 F.2d 887 (Lester Cox v. City of Freeman, Missouri, and C. Kenneth Maib) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lester Cox v. City of Freeman, Missouri, and C. Kenneth Maib, 321 F.2d 887, 7 Fed. R. Serv. 2d 945, 1963 U.S. App. LEXIS 4586 (8th Cir. 1963).

Opinion

YOUNG, District Judge.

This is a diversity action brought by Cox, a citizen of Kansas, against the City of Freeman, Missouri, and Maib, a citizen of Missouri.

This action arises out of an agreement between the appellant, Lester Cox, and the City of Freeman, Missouri, under which Cox contracted to build the City a waterworks. This contract was let in four parts; an agreement to build Parts I, II, and IV of the waterworks was entered into on the 28th day of April, 1959, and the contract to build Part III was dated June 10, 1959. Part I was the distribution system or water lines in the city. Part II was the earth-filled dam for the lake, Part III was for the purification plant, and Part IV was for the water storage standpipe or water tower.

There is some dispute as to whether Cox had 90 days to finish the whole contract or 90 days for each Part, but, at any rate, Cox received written notice to proceed with portions of the contract on August 5, 1959, and he then had 15 days to commence work on the job; the State Department of Health approved the waterworks on May 4, 1960, and an extension of time to paint was granted until August 5, 1960.

Sometime around the middle of June 1960 it became obvious that the parties were in disagreement about the amount of money which the City owed Cox; Cox contending that the City owed him $10,-303.34, and the City demanding that the bill be reduced because of delays in the completing of the job. On June 19, 1960, the City officials, Maib (City Engineer) , and Cox attended a meeting to negotiate a final settlement. At this meeting an “Agreement” was entered into which stipulated, inter alia, the City owed Lester Cox $73,315.20 on the contract less $68,188.05 already paid, leaving a balance due of $5,127.15 subject to certain conditions which were then set out; 1 included in this list was a qualification referring to provision No. 1.18 of *889 the original construction contract. This provision provided for a deduction from the final payment to Cox damages incurred by the City caused by the contractor’s delay in completing the waterworks. 2

On September 28, 1960, the defendant Maib wrote Cox a letter in which he said: “In keeping with the General Conditions of the Agreement and supplement agreement dated June 15, 1960, relative to the captioned project I have certified to the owner final payment to you as follows: * * Maib then went on to list the debits against the $5,127.15 mentioned in the June 15th instrument; 3 included in this list are charges against Cox for painting, minor repairs, and one unexplained entry to “Troth Plumbing Co.,” which come to a total of $468.00, but by far the largest debit is the “penalty” due for the alleged four and one-fifth months’ overtime, which amounts to $3,-956.40. The debits listed, subtracted from the $5,127.15, leave a “Net amount due Cox Trenching” of $702.75. Maib enclosed three checks 4 made out to Cox and, in two cases, other parties, which totaled the $702.75 which Maib alleged that the City owed Cox.

At the trial Cox testified that he received the checks just mentioned and *890 “cashed them or paid the indicated checks to suppliers.”

On September 29, 1960, Cox filed a complaint against the City and Maib. Cox sued the City, alleging that it still owed him on the contract, and in tort for negligently hiring Maib and for the alleged negligence of Maib under the doctrine of respondeat superior. 5 Cox sues Maib in tort contending that Maib, acting as the agent, servant, and employee of the City, was negligent in that he caused, while acting as engineer, certain “unnecessary delays to the plaintiff in completing the contract * * These alleged delays were that Maib:

“ (a) Caused an unnecessary delay on the completion of the line to the lake by his failure to have the necessary engineering completed before the City gave the written notice to start work and damaged the plaintiff in the amount of Six Thousand Four Hundred ($6,400.00) Dollars;
"(b) Caused an unnecessary delay on the location of the tower site by his failure to have the necessary engineering completed before the City gave the written notice to start work, and damaged the plaintiff in the amount of Two Thousand ($2,-000.00) Dollars;
“(c) Caused an unnecessary delay on the location of the plant site by his failure to have the necessary engineering completed before the City gave the written notice to start work, and damaged the plaintiff in the amount of One Thousand Three Hundred Thirty-two ($1,332.00) Dollars;
“(d) Caused an unnecessary delay on the trenching of rock near Highway 2 by his failure to have the necessary engineering completed before the City gave the written notice to start work, and damaged the plaintiff in the amount of One Thousand Seven Hundred Four ($1,704.-00) Dollars;
“(e) Caused an unnecessary delay on the completion of the contract by his negligence and carelessness in over-pressuring the water lines, in. rupturing the lines by putting pressure in the lines exceeding the amount specified in testing, in failing to engineer a surge chamber for the high service pump and damaged the plaintiff in the amount of Two-Thousand ($2,000.00) Dollars;
“(f) Caused an unnecessary delay on the completion of the contract by failing to appoint qualified resident engineers or inspectors and by failing to be present on the project or to. be located, the numerous discrepancies in the contract, drawings and. specifications could not be resolved: and the plaintiff was damaged thereby.”

It is apparent that almost~the entire dispute between the parties concerns, whether or not Maib or the City, through Maib, acted with such negligence that. Cox was delayed in his work and was-thereby damaged. It is true that if there was negligence on the part of Maib,. both he and the City would be liable except for the possibility of an accord and' satisfaction, Maib as a tort-feasor and: the City under the doctrine of respondeat, superior.

On March 8,1962, the defendants separately moved for summary judgment, alleging that the June 15th agreement and: the September 28, 1960 letter, with, cheeks attached, from Maib to Cox amounted to an accord and satisfaction. Judge Gibson overruled the motions for summary judgment primarily because-the June 15th document was without, “sufficient specificity” to be capable of enforcement. The Court went on to hold *891

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BLB Aviation South Carolina, LLC v. Jet Linx Aviation LLC
900 F. Supp. 2d 972 (D. Nebraska, 2012)
Ford v. Rodriguez
680 S.E.2d 904 (Court of Appeals of North Carolina, 2009)
LORREN v. Agan
960 So. 2d 685 (Court of Civil Appeals of Alabama, 2006)
Funderburk v. Johnson
935 So. 2d 1084 (Court of Appeals of Mississippi, 2006)
United States v. O'Connor
58 M.J. 450 (Court of Appeals for the Armed Forces, 2003)
McKeny Const. Co., Inc. v. Town of Rowlesburg
420 S.E.2d 281 (West Virginia Supreme Court, 1992)
Transpower Constructors v. Grand River Dam Authority
905 F.2d 1413 (Tenth Circuit, 1990)
Daigle v. City of Portsmouth
534 A.2d 689 (Supreme Court of New Hampshire, 1987)
Orthokinetics, Inc. v. Safety Travel Chairs, Inc.
806 F.2d 1565 (Federal Circuit, 1986)
Goldstein Oil Co. v. Sun Oil Trading Co.
624 F. Supp. 730 (E.D. Missouri, 1985)
Olson Motor Co. v. General Motors Corp.
703 F.2d 284 (Eighth Circuit, 1983)
Hill Ex Rel. Greer v. McDonald
442 A.2d 133 (District of Columbia Court of Appeals, 1982)
Soares v. Lakeville Baseball Camp, Inc.
343 N.E.2d 840 (Massachusetts Supreme Judicial Court, 1976)
United States v. William F. Ray
488 F.2d 15 (Tenth Circuit, 1973)
Enos v. WT Grant Company
294 A.2d 201 (Supreme Court of Rhode Island, 1972)
Pergerson v. Williams
176 S.E.2d 885 (Court of Appeals of North Carolina, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
321 F.2d 887, 7 Fed. R. Serv. 2d 945, 1963 U.S. App. LEXIS 4586, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lester-cox-v-city-of-freeman-missouri-and-c-kenneth-maib-ca8-1963.