Trans World Metals, Inc., Trans-World Metals and Co. Limited, and Trans World Metals, Limited v. Southwire Company

769 F.2d 902, 41 U.C.C. Rep. Serv. (West) 453, 19 Fed. R. Serv. 88, 1985 U.S. App. LEXIS 21880
CourtCourt of Appeals for the Second Circuit
DecidedAugust 5, 1985
DocketDocket 84-7856
StatusPublished
Cited by32 cases

This text of 769 F.2d 902 (Trans World Metals, Inc., Trans-World Metals and Co. Limited, and Trans World Metals, Limited v. Southwire Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Trans World Metals, Inc., Trans-World Metals and Co. Limited, and Trans World Metals, Limited v. Southwire Company, 769 F.2d 902, 41 U.C.C. Rep. Serv. (West) 453, 19 Fed. R. Serv. 88, 1985 U.S. App. LEXIS 21880 (2d Cir. 1985).

Opinion

JON O. NEWMAN, Circuit Judge:

This appeal requires us to resolve an expensive dispute arising out of the repudiation of a long-term commodity supply contract. Southwire Company (“Southwire”) appeals from a judgment of the District Court for the Southern District of New York (Charles E. Stewart, Jr., Judge) entered in this diversity action following a four-week jury trial. The jury awarded plaintiffs Trans World Metals, Inc., Trans-World Metals & Co., Ltd., and Trans World Metals, Ltd. (collectively “Trans World”) approximately $7.1 million in damages. Southwire challenges the finding that it is liable to Trans World under the contract, the measure of damages awarded to Trans World, and various rulings by the District Court. We affirm.

Background

On April 7, 1981, Trans World and South-wire negotiated by telephone for the purchase and delivery in 1982 of approximately $20.4 million of aluminum. The parties confirmed the contract by exchanging unsigned, standard form documents: Trans World sent Southwire both a confirming telex and a similarly worded “sales contract”; Southwire sent Trans World a “purchase contract confirmation.” The contract documents reflect an agreement for the sale and delivery of twelve thousand metric tons of primary aluminum at an average price of $.77 per pound. The “delivery time” clause of the Trans World sales contract and the “shipment schedule” clause of the Trans World telex both state that delivery shall occur “[a]t the rate of 1000 mt [metric tons] per month from January 1982 through December 1982.” The *905 Southwire purchase contract confirmation indicates that the quantity and “expected date” under the agreement is 2,205,000 lbs. (one thousand metric tons) “Per Month.” The standard printed form on the reverse side of the purchase contract confirmation indicates, in the “Delivery” clause, that “Time is hereby made of the essence, any late delivery shall be a default, and Seller shall be fully responsible for any cost occasioned Buyer thereby.”

Also pertinent to the delivery obligation is the following clause in the Trans World sales contract:

Delivered Railhead, usual midwest U.S.A. destinations as per buyer’s instructions, which are to be submitted no later than the 15th of the month of shipment. Any tonnage not released by that date is to be invoiced on the last day of month on net 30 days terms.

(Emphasis added). The purchase contract confirmation contained similar language.

The Southwire purchase contract confirmation contained a “termination” clause with the following provision regarding untimely delivery:

(a) Buyer may, by written notice of default, cancel this contract in whole or in part if:
(1) Seller fails to make timely delivery, time being of the essence; or
(2) Seller fails to comply with any provision thereof; and
Seller fails to cure such failure within ten (10) days, or such longer period as may be specified in the notice, from the date of receiving the notice.

Pursuant to the delivery terms of the contract, Southwire sent Trans World several delivery instruction “releases” during January 1982. Trans World shipped about three-fourths of the first month’s one thousand metric tons of aluminum during January. The remaining one-fourth of the first one thousand tons of metal was shipped between February 1 and February 11, 1982. On February 17, 1982, representatives of Trans World attended a meeting at Southwire’s request in Carrollton, Georgia, at which Southwire sought to extend the length of the contract to two years without altering the total quantity of aluminum to be delivered. The parties did not discuss the late delivery of the aluminum ordered in January. Southwire sent no delivery instruction releases to Trans World after January 1982.

Between April 1981, when the contract was negotiated, and March 1982, the price of aluminum fell dramatically. On March 4, 1982, Southwire sent Trans World a telex repudiating the entire contract, pursuant to the termination clause of the purchase contract confirmation. The telex stated:

Pursuant to [the termination clause] of our contract ... Southwire Company hereby notifies you of default in your performance of said contract and cancels the same because of your failure to make timely delivery of material called for by said contract.
Please advise us how to dispose of material you have late shipped, which we hold for your instruction.

The “failure to make timely delivery” refers to shipments to be made during the first month of the twelve-month contract. The “late shipped” material consists of the $419,232.84 worth of aluminum shipped by Trans World in early February 1982.

On May 3, 1982, Trans World brought suit in New York state court against South-wire for breach of the aluminum supply contract. 1 Southwire removed the action to federal court and unsuccessfully sought to transfer the case to Georgia. At the conclusion of the trial the jury answered special interrogatories in addition to rendering a general verdict in favor of Trans World. *906 The jury found that the parties had entered into a contract but that the “time is of essence” and “termination” clauses of Southwire’s “purchase contract confirmation” were not a part of the contract. The jury could not agree whether the aluminum shipments made in early February were timely but found that, even if the shipments were late, they were accepted by Southwire and that there was no substantial impairment of the value either of any particular shipment or of the contract as a whole. The jury awarded Trans World total damages of $7,122,141.84, consisting of $6,702,529.00 for repudiation of the remaining purchase obligations of the contract and $419,232.84 for shipments accepted without payment by Southwire in February. 2 The District Court applied the New York prejudgment interest rate and awarded Trans World $1,304,804.88 in prejudgment interest, for a total of $8,426,946.72. The District Court denied Southwire’s motions for judgment notwithstanding the verdict and for a new trial. This appeal followed.

DISCUSSION

I.

Southwire challenges the jury's finding that it is liable for repudiation of the contract, arguing that the District Court should have ruled as a matter of law that Trans World breached the contract by failing to complete the first month’s shipments in January. Southwire argues, in essence, that the deliveries made in February violated the “delivery” and “termination” clauses of its purchase contract confirmation and therefore that it was error for the District Court to permit Trans World to introduce evidence regarding trade practices in order to show that the February deliveries were timely. Even if we ignore the jury’s findings that the “time is of the essence” and “termination” clauses were not part of the contract between the parties, Southwire’s argument fails.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. P. Grimshaw
2025 MT 250 (Montana Supreme Court, 2025)
Jo v. JPMC Specialty Mortg., LLC
369 F. Supp. 3d 511 (W.D. New York, 2019)
Wilder v. World of Boxing LLC
310 F. Supp. 3d 426 (S.D. Illinois, 2018)
Nungesser v. Columbia University
169 F. Supp. 3d 353 (S.D. New York, 2016)
Arch Insurance v. Precision Stone, Inc.
584 F.3d 33 (Second Circuit, 2009)
RBFC ONE, LLC v. Zeeks, Inc.
367 F. Supp. 2d 604 (S.D. New York, 2005)
Purina Mills, L.L.C. v. Less
295 F. Supp. 2d 1017 (N.D. Iowa, 2003)
Diversified Energy v. TVA
Sixth Circuit, 2003
Jeung v. McKrow
264 F. Supp. 2d 557 (E.D. Michigan, 2003)
MATTHEWS AND FIELDS LUMBER CO. v. New England Ins. Co.
113 F. Supp. 2d 574 (W.D. New York, 2000)
In Re: Payroll Express Corporation
186 F.3d 196 (Federal Circuit, 1999)
Pereira v. Aetna Casualty & Surety Co.
186 F.3d 196 (Second Circuit, 1999)
Malek v. Federal Insurance
994 F.2d 49 (Second Circuit, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
769 F.2d 902, 41 U.C.C. Rep. Serv. (West) 453, 19 Fed. R. Serv. 88, 1985 U.S. App. LEXIS 21880, Counsel Stack Legal Research, https://law.counselstack.com/opinion/trans-world-metals-inc-trans-world-metals-and-co-limited-and-trans-ca2-1985.