Flower City Painting Contractors, Inc. v. Gumina Construction Company

591 F.2d 162, 1979 U.S. App. LEXIS 17742
CourtCourt of Appeals for the Second Circuit
DecidedJanuary 9, 1979
Docket130, Docket 78-7217
StatusPublished
Cited by17 cases

This text of 591 F.2d 162 (Flower City Painting Contractors, Inc. v. Gumina Construction Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Flower City Painting Contractors, Inc. v. Gumina Construction Company, 591 F.2d 162, 1979 U.S. App. LEXIS 17742 (2d Cir. 1979).

Opinions

GURFEIN, Circuit Judge:

This is an action for breach of contract, entertained in the District Court for the Western District of New York (Hon. Harold P. Burke, Judge) by virtue of the diversity of citizenship of the parties.1 28 U.S.C. [163]*163§ 1332. Plaintiff-appellant, Flower City Painting Contractors, Inc. (“Flower”) is a newly formed painting contracting firm in Rochester, New York, owned and managed by black minority personnel. Defendantappellee, Gumina Construction Company (“Gumina”) is an Ohio company with its principal place of business in Lorain, Ohio.

Gumina entered into a prime contract with the FIGHT Village Housing Development Fund Company, Inc., for the construction of a garden type apartment project called “FIGHT Village,” on March 12, 1973. The project was federally funded and developed under the auspices of the Federal Housing Authority of the Department of Housing and Urban Development (“HUD”). Pursuant to Executive Order No. 11246, which prohibits employment discrimination by Government contractors, HUD regulations and the terms of the prime contract required the prime contractor to undertake an affirmative action program that included efforts to recruit and hire minority subcontractors. HUD Contract Compliance Handbook 8000.6 at 27 (1972). Compliance was a condition of the contract.

Part of Gumina’s affirmative action obligation was satisfied by its award of a subcontract for painting in the FIGHT Village to Flower on April 16, 1973. As indicated by the cost breakdown summary sheet attached to the prime contract, the total anticipated cost of painting and decorating the entire FIGHT project was to be $101,-000. This estimation of cost was significant, since an excess of cost in one aspect could have caused a cost overrun that would cut into the prime contractor’s profits. The subcontract executed with Flower provided that Flower was to be paid $98,499.84 for its work, a sum that was roughly only $2500 less than the maximum allotted for painting and decorating the entire project.

The terms of the Gumina-Flower subcontract included the language of Flower’s original bid on the subcontract which was incorporated in haec verba as Schedule A of the subcontract. That Schedule reads as follows:

“SCHEDULE A”
The painting of the above mentioned project in accordance with the painting specifications and plans for this project.
1. One bedroom units $*335.00 per unit $*17,420.00
2. Two bedroom units $*371.00 per unit $*28,196.00
3. Three bedroom units $*428.00 per unit $*29,960.00
4. Four bedroom units $*477.58 per unit $*22,923.84
A Total of: $*98,499.84
Please note: price given reflects no bonding requirement and a non-union job operation.

The subcontract also incorporated by reference the prime contract, drawings, addenda, and specifications, as well as modifications subsequently issued. Indeed, Schedule A made specific reference to the contract specifications and plans in defining the scope of the subcontractor’s work. The subcontract further provided that the subcontractor would “faithfully observe all requirements and conditions set forth by plans and specifications on file at the F.H.A. Office in Buffalo, N.Y. . . .,” and that these documents were to be “available for inspection by the Subcontractor upon his request.”

On March 18, 1974, nearly one year after Flower entered into the subcontract, it asserted in a letter to Gumina that the contract required Flower to paint interior walls of the individual apartment units only and that Flower was not obligated to paint exteriors or common buildings.2 On March 25, 1974, Flower received from Gumina a copy of Article II of the subcontract with additional explanatory language typed in as a reminder of obligations which Gumina insisted that Flower had under its subcontract. This notation stated: “It is further [164]*164understood that this contract includes all exterior work, (encompasses all work, within specs and drawings) except exterior siding. The community building is also a part of this contract.” On March 29, 1974, the president of Flower submitted to Gumina an itemization of additional costs for this “exterior work,” claiming that it was not required to do the painting of apartment laundry rooms, storage rooms, and hallways, as well as of exterior doors, trim and certain common buildings.3 On April 4, 1974 (the letter was erroneously dated March 4), Gumina responded to Flower’s demand for extra payments by reiterating that the exterior work specified by Flower as requiring additional payment, was work which had already been agreed upon. Gumina, in the same letter, though the work had not yet begun, cancelled the contract. Appellant sued Gumina for damages.

At trial, Gumina defended its removal of Flower on the ground that the latter had misinterpreted the contract, and that by insisting upon extra payment for the painting of exteriors Flower had refused to comply with the terms of — and had thereby repudiated — the existing subcontract. Flower maintained the converse position: that Gumina had unilaterally attempted to enlarge the scope of Flower’s obligation under the contract by requiring work outside the individual “unit” interiors. The trial court accepted the contract interpretation offered by Gumina. It found, despite Flower’s contentions that it had been hired to paint only the walls in the “units,” that, on the contrary, neither the subcontract nor the specifications incorporated by reference excluded common hallways, storage areas, laundry rooms, or exterior surfaces of FIGHT Village. The court determined that the specifications required the painting of “ ‘all surfaces except those specifically excluded.’ ”

The court held that Flower committed a breach of contract “by asking for extra pay for work it was obligated to do under its contract.” It found that “Flower City unequivocally declared its refusal to perform according to the contract” and that “cancellation was the proper response by Gumina Construction.” It was on that basis that the complaint was dismissed after trial.

On this appeal, the defendant contends that an alternative ground upon which to uphold dismissal of Flower’s suit is that no subcontract was actually formed between Flower and Gumina because there was no “meeting of the minds.” This issue was not expressly considered by the District Court, although the assumption that a contract existed as interpreted by Gumina is implicit in its ruling.

If we hold Flower strictly to its obligation to recognize that the specifications were part of the subcontract, then its claim for additional payment as a condition of performance was unjustified, as Judge Burke found. This, in turn, would raise the question whether a refusal to perform part of an alleged contract, except in accordance with one’s own interpretation, is a repudiation. If so, we would then have to decide whether such a repudiation by Flower was sufficiently material to be treated as a justification for unilateral rescission by Gumina.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Regional Building Systems, Inc.
273 B.R. 423 (D. Maryland, 2001)
Therma-Scan, Inc. v. Thermoscan, Inc.
217 F.3d 414 (Sixth Circuit, 2000)
State v. Nason
981 P.2d 866 (Court of Appeals of Washington, 1999)
Mohawk Mt. Ski Area v. American Home Assce., No. Cv 056905 (Jan. 30, 1995)
1995 Conn. Super. Ct. 573 (Connecticut Superior Court, 1995)
Natwest USA Credit Corp. v. Alco Standard Corp.
858 F. Supp. 401 (S.D. New York, 1994)
Property Advisory Group, Inc. v. Bevona
718 F. Supp. 209 (S.D. New York, 1989)
United States v. Laskow
688 F. Supp. 851 (E.D. New York, 1988)
Kimley-Horn Associates, Inc. v. Moskowitz
19 Fla. Supp. 2d 31 (Palm Beach County Court, 1986)
United Steelworkers v. North Bend Terminal Co.
752 F.2d 256 (Sixth Circuit, 1985)
Marion Coal Co. v. Marc Rich & Co. International, Ltd.
539 F. Supp. 903 (S.D. New York, 1982)
Doyle Dane Bernbach, Inc. v. Avis
526 F. Supp. 117 (S.D. New York, 1981)
United States Fire Insurance v. M.V. Asia Friendship
495 F. Supp. 244 (S.D. New York, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
591 F.2d 162, 1979 U.S. App. LEXIS 17742, Counsel Stack Legal Research, https://law.counselstack.com/opinion/flower-city-painting-contractors-inc-v-gumina-construction-company-ca2-1979.