Towns of Wellesley, Concord, and Norwood, Massachusetts v. Federal Energy Regulatory Commission, Boston Edison Company, Intervenor

829 F.2d 275, 1987 U.S. App. LEXIS 12714
CourtCourt of Appeals for the First Circuit
DecidedSeptember 25, 1987
Docket85-1221
StatusPublished
Cited by30 cases

This text of 829 F.2d 275 (Towns of Wellesley, Concord, and Norwood, Massachusetts v. Federal Energy Regulatory Commission, Boston Edison Company, Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Towns of Wellesley, Concord, and Norwood, Massachusetts v. Federal Energy Regulatory Commission, Boston Edison Company, Intervenor, 829 F.2d 275, 1987 U.S. App. LEXIS 12714 (1st Cir. 1987).

Opinion

PER CURIAM.

The towns of Wellesley, Concord and Norwood, Massachusetts (“petitioners”) petition this court for a writ of mandamus to compel the Federal Energy Regulatory Commission (“FERC”) to comply with the mandate of the earlier decision of the court in this case, Towns of Wellesley, Concord and Norwood v. F.E.R.C., 786 F.2d 463 (1st Cir.1986).

*276 I. PRIOR PROCEEDINGS

Petitioners purchase electricity from Boston Edison Company (Boston Edison) at wholesale rates. A 1980 settlement agreement controlled, at the time this controversy arose, the method by which Boston Edison could raise these rates. Specifically, the agreement prohibited Boston Edison from increasing petitioners’ rates unless a rate increase had been made effective for Boston Edison’s retail customers.

In September, 1984, Boston Edison applied for a $2.95 million wholesale rate increase with the FERC. The application proposed that the increase go into effect in two stages. Petitioners objected to the rate filing. They claimed that it violated the 1980 agreement because retail rates had increased only once prior to the application. The FERC found that the contract did not bar the two-step rate increase and ordered the increased rates effective, subject to refund, as of November 28,1984 and April 28, 1985 respectively. 29 F.E.R.C. 161,224 (November 21, 1984). The FERC also ordered hearings on whether the rates proposed by Boston Edison were reasonable. Id. After the FERC denied their motion for rehearing, petitioners sought review in this court of the FERC's acceptance of the rate filing.

In our prior decision, we found that the settlement agreement “require[d] that effective dates for wholesale rate increases be matched with effective dates for increases in retail rates.” 786 F.2d at 465. However, the effective date of the second step of the proposed wholesale rate increase was not accompanied by a corresponding increase in retail rates. Thus, the second step of the rate filing violated the settlement agreement. Id. Because the FERC cannot accept rate filings that contravene private contracts, id. (citation omitted), we vacated the FERC’s orders accepting the rate filing in two stages. Id. at 465-66.

Originally, we also remanded the case to the FERC with instructions to order Boston Edison to refund to petitioners, with interest, all rates it had collected pursuant to the second step of the rate increase and we ordered the FERC to conduct further proceedings as deemed necessary. On May 8, 1986, the FERC petitioned for rehearing and a suggestion for rehearing in banc. The FERC argued that the determination of a proper remedy should be left up to it. It pointed out that the authorization for the rate increase had been temporary and was subject to refund, pending the outcome of the underlying rate proceeding. A better course, the FERC argued, was to permit it to fashion a remedy in the context of the final orders concerning Boston Edison’s rate increase application. We agreed and, on June 6, 1986, we limited our order to remanding the case to the FERC “to conduct further proceedings as deemed necessary and grant such remedy as is consistent herewith.” Id. at 466. Our order vacating the FERC’s acceptance of the rate filing in two stages still stood.

On June 22, 1986, the Administrative Law Judge (“AU”) issued a decision in the underlying rate proceeding. 34 F.E.R.C. U 63,023. According to the FERC, the parties have appealed the AU’s decision and it currently is in the process of formulating an order that will resolve the issues raised in the parties’ appeals and in our remand to it. However, according to petitioners, they still are paying the second step rate to Boston Edison. 1 As a result, they filed a motion, on August 27, 1986, requesting the FERC to take action pursuant to our order. 2 They claim to have received no response to this motion. The instant petition for writ of mandamus followed.

II. MANDAMUS

The All Writs Act, 28 U.S.C. § 1651(a), provides, in relevant part, that “all courts established by Act of Congress may issue all writs necessary or appropri *277 ate in aid of their respective jurisdictions and agreeable to the usages and principles of law.” There is no doubt that we have inherent power to determine whether the FERC has complied with our earlier mandate, and that section 1651(a) is an aid to this power. Potomac Elec. Power Co. v. I.C.C., 702 F.2d 1026, 1032 (D.C.Cir.1983) (citing United States v. New York Telephone Co., 434 U.S. 159, 172-73, 98 S.Ct. 364, 372-73, 54 L.Ed.2d 376 (1977)). However, mandamus is a drastic remedy, suitable only in “extraordinary situations.” Kerr v. United States District Court, 426 U.S. 394, 402, 96 S.Ct. 2119, 2123, 48 L.Ed.2d 725 (1976) (citations omitted); Acton Corp. v. Borden, Inc., 670 F.2d 377, 382 (1st Cir.1982). One of the conditions for its issuance is that petitioners have “no other adequate means to attain the relief [they] desire____” Kerr, supra, 426 U.S. at 403, 96 S.Ct. at 2124 (citation omitted).

Petitioners claim that they are entitled to the issuance of a writ because the FERC has unreasonably delayed in complying with this court’s mandate. Specifically, petitioners complain that the FERC has not issued a final order in the underlying rate proceeding and that petitioners still are paying the second step of the wholesale rate increase.

In Telecommunications Research & Action Center v. F.C.C., 750 F.2d 70 (D.C.Cir. 1984) (“T.R.A.C.”), the Court of Appeals for the District of Columbia Circuit set out guidelines which are relevant to our determination whether the FERC’s delay in issuing a final order is so “egregious” as to warrant mandamus. In pertinent part, they provide that 1) a “rule of reason” governs the time agencies take to make decisions; 2) delays where human health and welfare are at stake are less tolerable than delays in the economic sphere; 3) consideration should be given to the effect of ordering agency action on agency activities of a competing or higher priority; 4) the court should consider the nature of the interests prejudiced by delay; and 5) the agency need not act improperly to hold that agency action has been unreasonably delayed. Id. at 80 (citations omitted).

Applying these standards to petitioners’ claims of unreasonable delay, we find that the timing of the FERC’s actions in fashioning a final order is not so “egregious” as to warrant mandamus.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ghannad-Rezaie v. Laitinen
D. Massachusetts, 2024
Durrani v. Bitter
D. Massachusetts, 2024
Aya Raouf v. P U.S. Department of State, et al.
2023 DNH 042 (D. New Hampshire, 2023)
Raouf v. US Department of State
D. New Hampshire, 2023
Roe v. Mayorkas
D. Massachusetts, 2023
Am. Acad. of Pediatrics v. U.S. Food & Drug Admin.
330 F. Supp. 3d 657 (District of Columbia, 2018)
Martin v. O'Rourke
891 F.3d 1338 (Federal Circuit, 2018)
Cent. Sierra Envtl. Res. Ctr. v. Stanislaus Nat'l Forest
304 F. Supp. 3d 916 (E.D. California, 2018)
Center for Biological Diversity v. Bureau of Land Management
35 F. Supp. 3d 1137 (N.D. California, 2014)
Families for Freedom v. Napolitano
628 F. Supp. 2d 535 (S.D. New York, 2009)
Aronov v. Napolitano
562 F.3d 84 (First Circuit, 2009)
Aronov v. Chertoff
536 F.3d 30 (First Circuit, 2008)
LeBeau v. TOWN OF SPENCER
190 F. Supp. 2d 131 (D. Massachusetts, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
829 F.2d 275, 1987 U.S. App. LEXIS 12714, Counsel Stack Legal Research, https://law.counselstack.com/opinion/towns-of-wellesley-concord-and-norwood-massachusetts-v-federal-energy-ca1-1987.