Town of Stratford v. A. Secondino & Son, Inc.

38 A.3d 179, 133 Conn. App. 737, 2012 Conn. App. LEXIS 101
CourtConnecticut Appellate Court
DecidedFebruary 28, 2012
DocketAC 32589
StatusPublished
Cited by5 cases

This text of 38 A.3d 179 (Town of Stratford v. A. Secondino & Son, Inc.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Stratford v. A. Secondino & Son, Inc., 38 A.3d 179, 133 Conn. App. 737, 2012 Conn. App. LEXIS 101 (Colo. Ct. App. 2012).

Opinion

Opinion

MIHALAKOS, J.

This appeal arises from a contract dispute between the plaintiff, the town of Stratford, and the defendant, A. Secondino & Son, Inc., after a trial to the court in which the court found in favor of the defendant on the complaint and on the first and second counts of the defendant’s counterclaim. On appeal, the plaintiff claims that the trial court erred by ruling that the defendant was not required to comply with a condition precedent to payment as set forth in the parties’ contract. The defendant filed a cross appeal, claiming [739]*739that the court’s failure to award statutory interest pursuant to General Statutes § 37-3a was inconsistent with its finding that the plaintiffs detention of the defendant’s money was wrongful. We disagree with the claims raised by both parties and, accordingly, affirm the judgment of the trial court.

The following facts, which the trial court reasonably found, are relevant to our resolution of the claims on appeal. In its memorandum of decision, the court found that the parties had entered into a contract “for the construction of a new fire headquarters building in Stratford. . . . The final contract between the [plaintiff] and the defendant consisted of: (1) a [document titled ‘Standard Form of Agreement between Owner and Contractor’] on [the American Institute of Architects’] document A101-1997; (2) [a document titled ‘General Conditions of the Contract for Construction’] on [the American Institute of Architects’] form A-201; and . . . (3) plans and specifications prepared by the architects. . . . The contract originally provided for a contract price of $4,837,000 and for completion of construction within 400 calendar days. As the result of approved change orders, the final price was increased to $5,561,120.08. Under the provisions of the contract, the [plaintiff] was the ‘Owner,’ the defendant was the ‘[Contractor’ and Antinozzi Associates, P.C., was the ‘Architect.’ Leonard Bucher was designated as the ‘Owner’s representative,’ and David Secondino was designated as the ‘Contractor’s representative. . . .’ [The architect,] Paul Lisi, acted on behalf of Antinozzi Associates, P.C. . . .

“Under the provisions of article 5 of the contract, the defendant was required to make monthly applications for payment as work on the project progressed. Paragraph 5.1.3 states: ‘Provided that an Application for Payment is received by the Architect not later than the first day of a month, the Owner shall make payment [740]*740to the Contractor not later than the 15th day of the following month. If an Application for Payment is received by the Architect after the application date fixed above, payment shall be made by the Owner not later than 30 days after the Architect approves the Application for Payment in the amount so approved.' . . .

“Although not contemplated by the terms of the contract, the parties handled monthly applications for payment in the following manner. The defendant would prepare a ‘pencil copy’ of each monthly application for payment and forward it to Lisi. After discussions between David Secondino and Lisi, the defendant would prepare five copies of a final application for payment, each of which would be signed on behalf of the defendant, notarized and delivered to Lisi. Lisi would sign each copy of the application, retain one copy for his files and forward the remaining copies to Bucher so that payments could be made to the defendant.

“The defendant was aware that Bucher was independently reviewing and approving each application for payment prior to authorizing payment. However, despite the provisions of the contract, the defendant was unaware that Lisi was approving and signing the final applications for payment before forwarding them to Bucher. The defendant believed that after orally approving the ‘pencil copy’ of each application, Lisi did not take any further action to evidence his approval of the final application. This mistaken belief was engendered, to some extent, by the [plaintiff], which retained all copies of the applications for payment forwarded to Bucher by Lisi rather than furnishing the defendant with copies of each fully approved application for payments. . . .

“After substantial completion of the project as originally contemplated, there remained certain ‘punch list’ items which needed to be addressed. These items were [741]*741listed on a list prepared by Lisi and sent to the defendant on August 22, 2005 .... On February 22, 2006 . . . Lisi prepared a revised punch list, which also included items related to the dispatch center construction. A final punch fist was prepared by Lisi on June 9, 2006, and sent to Bucher. . . . Lisi prepared an estimate of the cost of completion of the punch list on June 5, 2006 — $60,950. In accordance with the provisions of paragraph 5.2.2 of the contract, Lisi proposed to withhold twice that amount from the payment due the defendant.

“On June 29, 2006, Lisi sent a letter to Bucher reminding him that certain items on the punch list had not yet been addressed and that the one year warranty period on the project would expire on August 23, 2006.1

“On July 19, 2006, the defendant sent a letter to Bucher, with a copy to Lisi, addressing, at length, the items on Lisi’s June 9, 2006 punch list. In the letter, the defendant claimed that only $3675 worth of punch work remained to be done and proposed reducing the retainage to twice that amount ($7350) in accordance with paragraph 5.2.2 of the agreement. In that same letter, the defendant offered to promptly complete the punch work when the amount being withheld from the defendant (claimed to be $137,659) was reduced to $7350. The letter threatened litigation ‘[i]f these issues are not resolved and our payment is not received by August 15, 2006 . . . .’

“On August 4, 2006, the defendant again wrote to Bucher, informing him that [it] had not heard from Lisi [742]*742concerning [its] request that the retainage be reduced. In the letter, the defendant characterized the amount of work remaining to be done as ‘minuscule’ but refused to return to the job until the [plaintiff] reduced the retainage. The letter also claimed that the [plaintiff] had hired an attorney to seek to attach the defendant’s surety bond and informed Bucher that the surety company intended to deny the claim. On August 22, 2006 the [plaintiff] commenced this litigation against the defendant, claiming breach of contract because of the defendant’s failure to correct unspecified portions of its work, which did not conform to contract specifications. . . .

“After the suit was filed, the [plaintiff] and the defendant and their respective attorneys met on several occasions in attempts to resolve their differences. Lisi did not participate in these meetings. David Secondino, vice president of the defendant, testified that he was told by [the plaintiffs] officials, including the [plaintiffs] attorney that all outstanding issues would be handled directly between the parties without regard to any participation by Lisi. This claim was essentially verified by Lisi who testified that he was not involved with the project for approximately two years, beginning shortly after he prepared his June 9, 2006 punch list . . . and lasting until 2008, when Lisi was asked to participate in the preparation of [a] new punch list following a ‘commissioning’ of the [heating, ventilating and air conditioning] system ordered by the [plaintiff].

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pressman v. Purcell
D. Connecticut, 2019
Bruno v. Whipple
Connecticut Appellate Court, 2015
Design Tech, LLC v. Moriniere
76 A.3d 712 (Connecticut Appellate Court, 2013)
Carrillo v. Goldberg
61 A.3d 1164 (Connecticut Appellate Court, 2013)
Alarmax Distributors, Inc. v. New Canaan Alarm Co.
61 A.3d 1142 (Connecticut Appellate Court, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
38 A.3d 179, 133 Conn. App. 737, 2012 Conn. App. LEXIS 101, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-stratford-v-a-secondino-son-inc-connappct-2012.