Banks Building Co. v. Malanga Family Real Estate Holding, LLC

926 A.2d 1, 102 Conn. App. 231, 2007 Conn. App. LEXIS 275
CourtConnecticut Appellate Court
DecidedJuly 3, 2007
DocketAC 27822
StatusPublished
Cited by16 cases

This text of 926 A.2d 1 (Banks Building Co. v. Malanga Family Real Estate Holding, LLC) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Banks Building Co. v. Malanga Family Real Estate Holding, LLC, 926 A.2d 1, 102 Conn. App. 231, 2007 Conn. App. LEXIS 275 (Colo. Ct. App. 2007).

Opinion

Opinion

BISHOP, J.

This case concerns a construction contract dispute. The matter was referred to an attorney fact finder, who filed a report, on the basis of which the trial court subsequently rendered judgment in favor of the plaintiff, Banks Building Company, LLC. The defendant, Malanga Family Real Estate Holding, LLC, claims on appeal that the judgment was premised on an erroneous conclusion by the court that the defendant had waived a provision of the contract. 1 We affirm the judgment of the trial court.

*233 The following facts and procedural history are relevant to our discussion of the issues on appeal. In August, 2002, the plaintiff began to construct the “outer shell” of a building for the defendant pursuant to an oral agreement. Subsequent to a dispute regarding the demolition of another building, the parties, on September 3, 2002, entered into a formal written contract with supplementary conditions, 2 pursuant to which the plaintiff agreed to construct the shell of a building 3 in the Gateway Shopping Plaza in Manchester for the defendant in exchange for $93,360. The contract imposed a deadline of September 13, 2002, for completion of construction and included a time is of the essence clause regarding this date. The defendant made one progress payment to the plaintiff in the amount of $46,680 on September 6, 2002, in satisfaction of its obligation under the contract. Final payment was due under *234 the terms of the contract “within one (1) day of completion of the [w]ork . . . .”

The construction of the building’s shell, however, was not completed by September 13, 2002. The plaintiff sent its final invoice for $46,680 on October 23, 2002, the date it claimed to have completed its performance of the contract. 4 The defendant, in turn, refused to pay the invoice on the ground that the plaintiff had not completed its performance obligation by September 13, 2002. Therefore, the defendant claimed, it was relieved of its obligation to pay the plaintiff because the project was not completed by the contract completion date.

Subsequently, as a result of the defendant’s failure to pay the remaining amount purportedly due, 5 the plaintiff filed a two count complaint, alleging breach of contract and, alternatively, unjust enrichment. 6 The defendant filed an answer, three special defenses and a counterclaim, alleging that the plaintiff had materially breached the parties’ contract, thereby excusing the defendant’s performance. In a previous appeal of this matter involving a different issue, this court set forth the matter’s procedural history as follows: “Because the amount in dispute was less than $50,000, the court referred the matter to an attorney fact finder. . . . The fact finder held a hearing on February 2 and 9, 2004, and, on April 12, 2004, filed a report outlining his findings of fact and recommended disposition. . . . The fact finder made a number of subordinate findings, including that the defendant through its actions had waived a provision *235 of the contract stating that ‘time is of the essence,’ and that the defendant was entitled to certain offsets from the amount due to the plaintiff under the contract. [He concluded that] judgment [should enter] in favor of the plaintiff in the amount of $22,336.80 [and against the defendant on its counterclaim].” (Citations omitted.) Banks Building Co., LLC v. Malanga Family Real Estate Holding, LLC, 92 Conn. App. 394, 395-96, 885 A.2d 204 (2005).

On the basis of the attorney fact finder’s report, the court, Hon. Mary R. Hennessey, judge trial referee, issued a memorandum of decision adopting the fact finder’s recommendation and rendering judgment in favor of the plaintiff. 7 The court concluded that “[sufficient evidence was presented to support the fact finder’s conclusion that the defendant waived the ‘time is of the essence’ requirement in the contract. The fact finder concluded that ‘[t]here were delays on the project, but the parties adopted a course of dealings where the defendant completed some of the construction items that were the plaintiffs responsibility under the contract. The defendant waived reliance on the time is of the essence provision of the contract by its actions.’ ” This appeal followed.

We begin our analysis of the defendant’s claim on appeal by setting forth the applicable standard of review. “Attorney fact finders are empowered to hear and decide issues of fact on contract actions pending in the Superior Court .... On appeal, [o]ur function *236 ... is not to examine the record to see if the trier of fact could have reached a contrary conclusion. . . . Rather, it is the function of this court to determine whether the decision of the trial court is clearly erroneous. . . . This involves a two part function: where the legal conclusions of the court are challenged, we must determine whether they are legally and logically correct and whether they find support in the facts set out in the memorandum of decision; where the factual basis of the court’s decision is challenged we must determine whether the facts set out in the memorandum of decision are supported by the evidence or whether, in light of the evidence and the pleadings in the whole record, those facts are clearly erroneous.” (Citation omitted; internal quotation marks omitted.) Premier Capital, Inc. v. Grossman, 68 Conn. App. 51, 57, 789 A.2d 565, cert. denied, 260 Conn. 917, 797 A.2d 514 (2002), aff'd after remand, 82 Conn. App. 390, 845 A.2d 442, cert. denied, 271 Conn. 901, 859 A.2d 564 (2004). With the foregoing in mind, we now turn to the defendant’s specific claim.

At the heart of this appeal is the defendant’s claim that the court improperly found that it had waived the time is of the essence clause in the parties’ written contract. On the basis of this determination, the court found that the plaintiff had not breached the contract and, accordingly, awarded damages to the plaintiff for the work it performed pursuant to the contract. The defendant argues that the court’s finding that the defendant implicitly waived the time is of the essence provision in the contract was not supported by the evidence at trial and, thus, was clearly erroneous. 8 We are unpersuaded.

*237 The record reveals that the plaintiff continued construction work after the original September 13, 2002 deadline on matters that were its contractual responsibility.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reserve Realty, LLC v. Windemere Reserve, LLC
Supreme Court of Connecticut, 2023
Brady v. Bickford
183 A.3d 27 (Connecticut Appellate Court, 2018)
Hornung v. Hornung
146 A.3d 912 (Supreme Court of Connecticut, 2016)
RBC Nice Bearings, Inc. v. SKF USA, Inc.
78 A.3d 195 (Connecticut Appellate Court, 2013)
State v. Reddy
42 A.3d 406 (Connecticut Appellate Court, 2012)
Town of Stratford v. A. Secondino & Son, Inc.
38 A.3d 179 (Connecticut Appellate Court, 2012)
Northland Two Pillars, LLC v. Harry Grodsky & Co.
35 A.3d 333 (Connecticut Appellate Court, 2012)
Shelton v. Olowosoyo
10 A.3d 45 (Connecticut Appellate Court, 2010)
Blackwell v. Mahmood
992 A.2d 1219 (Connecticut Appellate Court, 2010)
Dougan v. Dougan
970 A.2d 131 (Connecticut Appellate Court, 2009)
Grey v. Connecticut Indemnity Services, Inc.
964 A.2d 591 (Connecticut Appellate Court, 2009)
DARTMOOR CONDOMINIUM ASS'N, INC. v. Guarco
960 A.2d 1076 (Connecticut Appellate Court, 2008)
Mastroianni v. Fairfield County Paving, LLC
942 A.2d 418 (Connecticut Appellate Court, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
926 A.2d 1, 102 Conn. App. 231, 2007 Conn. App. LEXIS 275, Counsel Stack Legal Research, https://law.counselstack.com/opinion/banks-building-co-v-malanga-family-real-estate-holding-llc-connappct-2007.