Shelton v. Olowosoyo

10 A.3d 45, 125 Conn. App. 286, 2010 Conn. App. LEXIS 539
CourtConnecticut Appellate Court
DecidedNovember 30, 2010
DocketAC 31413
StatusPublished
Cited by2 cases

This text of 10 A.3d 45 (Shelton v. Olowosoyo) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shelton v. Olowosoyo, 10 A.3d 45, 125 Conn. App. 286, 2010 Conn. App. LEXIS 539 (Colo. Ct. App. 2010).

Opinion

Opinion

PELLEGRINO, J.

The defendants, Femi Olowosoyo 1 and Starlight Construction Company, Inc., appeal from the judgment rendered after a court trial, arising from a home construction contract with the plaintiffs, Stephen Shelton and Elizabeth Shelton, denying relief on all claims and counterclaims. On appeal, the defendants claim that the court improperly found that the payment terms of the contract had been modified based on the parties’ actions and that it failed to award damages. On cross appeal, the plaintiffs claim that the court improperly found that (1) they could not enforce the third amended completion date, (2) they were not entitled to damages and (3) the defendants had not been unjustly enriched. We affirm the judgment of the trial court.

The court found the following facts. In approximately 2003, the plaintiffs met with John Mastera, an architect, to consider renovating their house located at 16 Compo Road North in Westport. After a series of meetings with Mastera, the plaintiffs decided to demolish their home at the property and build a new house. By June, 2004, *288 Mastera had prepared drawings and had given the plaintiffs an estimated project cost of $580,000, including fees. Because the plaintiffs intended to utilize a construction loan in the amount of $580,000, they could not afford a bid of $580,000 that did not include the kitchen and architectural fees. Eventually, they decided to alter the initial plans to reduce costs and, on September 4, 2004, entered into a contract with the defendants to build the home for a fixed price of $450,000. They executed the contract again on April 1, 2005. The contract was an “at cost” contract, meaning that the defendants would not realize a profit. The price negotiated included all labor and materials but did not include costs for the kitchen, driveway and architectural fees. 2

The contract initially provided for an estimated completion four months from the start date, and it included a payment schedule that obligated the plaintiffs to make the following payments: one third, or $150,000, as a retainer; one third, or $150,000, at the “commencement of the framing”; one sixth, or $75,000, at the “completion of the drywall”; and the remaining balance of $75,000 upon the completion of the project. Prior to signing the contract, the plaintiffs informed the defendants that a construction loan would be the source of their payments. After the contract had been signed, the plaintiffs learned of the draw schedule on their construction loan and, subsequently, informed the defendants as to the schedule, effectively putting the defendants on notice that the plaintiffs might not be able to follow the payment terms of the contract insofar as they failed to coincide with the terms of the draw schedule.

Although the contract stipulated that the first payment would be for $150,000, the first draw was for *289 $112,000 and, on September 22, 2004, the plaintiffs paid $90,000 to the defendants. The defendants accepted the plaintiffs’ nonconforming payment and began working two months later, in November, 2004. 3 In December, 2004, the town of Westport issued a cease and desist order because the defendants had begun work without obtaining the necessary permit authorizing demolition of the house. It was not until January 28, 2005, that the town finally issued a building permit authorizing the demolition of the house.

In March, 2005, the plaintiffs paid to the defendants $25,265 for additional change orders to remove trees, to install a new water meter, to clean the “ ‘old septic’ ” tank, to reinforce the foundation wall by increasing its thickness, to comply with framing notes and to provide a fireplace vent kit. In April, 2005, the parties met after both the stipulated payment and completion dates had not been met. The defendants provided the plaintiffs with an amended completion date of August 2, 2005. In May, 2005, as the foundation was nearing completion, the plaintiffs received another draw on their bank loan and paid $53,800 to the defendants. At that point, including the aforementioned paid change order, a total of $166,065 had been paid to the defendants.

In July, 2005, Olowosoyo contacted the plaintiffs and stated that the defendants did not have the necessary financial resources to continue with the construction. In order to attain additional funds, the plaintiffs refinanced their home at 9 Cedar Road in Westport. On August 25, 2005, the plaintiffs paid to the defendants an additional $86,000. By that time, the foundation had been completed, work on the basement had commenced, and the plaintiffs had paid a total of $252,065. In August, 2005, the defendants provided the plaintiffs with a schedule *290 with a second amended completion date of December 31, 2005. On March 29, 2006, after the second amended completion date had not been met, the parties agreed to a third amended completion date of May 31, 2006.

On May 16, 2006, Olowosoyo e-mailed the plaintiffs and acknowledged that the defendants’ mistakes, the town’s cease and desist order and financial issues had contributed to the failure to meet the agreed on completion dates. On June 5, 2006, the plaintiffs e-mailed the defendants, “insisting . . . that the exterior structure (framing, sheeting, windows) be completed by June 30, 2006.” (Internal quotation marks omitted.) On July 12, 2006, after the deadline was not met, the plaintiffs unilaterally terminated the contract. In July, 2006, the plaintiffs hired Shoreline Builders, Inc. (Shoreline), to weatherproof the house. Shoreline was paid a total of $101,000 to complete the framing, to install the roof and additional sheathing and to replace rotted or weather-damaged wood. After Shoreline finished that work, the plaintiffs sold the property for $700,000. 4

On December 11, 2006, the plaintiffs commenced this action against the defendants in a five count complaint alleging breach of contract; violation of the Connecticut Unfair Trade Practices Act (CUTPA), General Statutes § 42-110a et seq.; piercing of the corporate veil; conversion; and unjust enrichment. 5 6In response, the defendants filed an amended answer, special defenses and a five count counterclaim alleging breach of contract, promissory estoppel, fraud, unjust enrichment and a claim for a setoff pursuant to Practice Book § 10-54. *291 The case was tried before the court over six days in December, 2008. The court found that the parties voluntarily had modified or waived the terms of the contract and that none of the parties were entitled to recover on any of their claims or counterclaims. This appeal and cross appeal followed. Additional facts will be set forth as necessary.

I

The defendants claim that the court improperly interpreted the contract when it found that the payment provisions of the contract had been modified based on the parties’ actions. We disagree.

We begin by setting forth our standard of review.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Loch View, LLC v. Windham
Connecticut Appellate Court, 2026
Mason v. Ford
168 A.3d 525 (Connecticut Appellate Court, 2017)
HOUSING AUTHORITY OF NORWALK v. Brown
19 A.3d 252 (Connecticut Appellate Court, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
10 A.3d 45, 125 Conn. App. 286, 2010 Conn. App. LEXIS 539, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shelton-v-olowosoyo-connappct-2010.