Town of Norwood, Massachusetts v. Federal Energy Regulatory Commission, Yankee Atomic Electric Company, Intervenor

80 F.3d 526, 317 U.S. App. D.C. 50, 1996 U.S. App. LEXIS 6869
CourtCourt of Appeals for the D.C. Circuit
DecidedApril 9, 1996
Docket94-1710
StatusPublished
Cited by9 cases

This text of 80 F.3d 526 (Town of Norwood, Massachusetts v. Federal Energy Regulatory Commission, Yankee Atomic Electric Company, Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Norwood, Massachusetts v. Federal Energy Regulatory Commission, Yankee Atomic Electric Company, Intervenor, 80 F.3d 526, 317 U.S. App. D.C. 50, 1996 U.S. App. LEXIS 6869 (D.C. Cir. 1996).

Opinion

Opinion for the Court filed by Circuit Judge TATEL.

TATEL, Circuit Judge:

After Yankee Atomic Electric Company shut down a nuclear power plant before the plant’s license expired, the Federal Energy Regulatory Commission allowed Yankee to recover from ratepayers 100% of its remaining unamortized investment, construction-work-in-progress, decommissioning costs, and the operating expenses of the closed plant. To reflect the plant shutdown, the Commission also reduced Yankee’s rate of return. The Town of Norwood, one of Yankee’s ratepayers, now seeks review of the Commission’s order. In view of both the language of the service contract between Norwood and Yankee and the substantial savings to ratepayers from the shutdown of the plant, we find that the Commission’s decision to allow Yankee 100% recovery of its investment and other expenses was neither arbitrary nor capricious. We find, however, that in establishing a new rate of return to reflect the reduced risks facing Yankee, the Commission’s determination that it could not go below the previously established zone of reasonableness was arbitrary. We therefore set aside the order and remand for the setting of a new zone of reasonableness.

I.

Yankee Atomic Electric Company owns an electric power production facility in Rowe, Massachusetts, which began operating in 1961 under a Nuclear Regulatory Commission license that expires on July 9, 2000. All of Yankee’s stock is owned by ten Northeast utility companies. Known as “purchaser-owners,” these ten companies are parties to a “Power Contract” with Yankee that allows Yankee to charge all of its operating costs to customers. The Town of Norwood, the petitioner in this case, is a customer of New England Power Company, one of the parties to the Power Contract.

In response to Nuclear Regulatory Commission concerns about the safety of the Rowe plant’s reactor vessel, Yankee voluntarily shut down the plant in October 1991. Four months later, after conducting a study that showed that the costs of restarting the plant and operating it through the remainder of its license exceeded the value of the energy the plant could produce, Yankee’s board of directors voted to close the plant permanently. Yankee then filed with the Federal Energy Regulatory Commission an Amendment to each Power Contract authorizing Yankee to include in its rate base 100% of the $48.4 million of investment in the Rowe plant that it would have recovered if it had operated the plant through July 2000. Yankee also sought to recover its post-shutdown operating and maintenance expenses (about $68.9 million). The Amendment also allowed Yankee to maintain its 12% rate of return on equity.

When several Yankee customers, including Norwood, intervened to oppose the Amendment, the Commission suspended Yankee’s rate filing to decide whether the Amendment was just and reasonable. Yankee Atomic Elec. Co., 60 F.E.R.C. ¶ 61,104, at 61,334 (1992) (order granting intervention). The *529 Commission scheduled a hearing to determine whether the shutdown decision was prudent, and whether Opinion No. 295 — in which the Commission held that investors could not recover from ratepayers more than 50% of their investment in a plant canceled before operation — applied to the Yankee shutdown. Id. at 61,332-35 (citing New England Power Co., Opinion No. 295, 42 F.E.R.C. ¶ 61,016, reh’g denied in part and granted in part, Opinion No. 295-A, 43 F.E.R.C. ¶ 61,285 (1988)). Yankee’s subsequent offer of settlement was accepted by all intervening customers except Norwood. See Yankee Atomic Elec. Co., 65 F.E.R.C. ¶ 63,-001, at 65,002 (1993) (ALJ decision).

Relying on Yankee’s study which showed that ceasing plant operations would save ratepayers at least $116 million, the ALJ assigned to hear Norwood’s challenges concluded that Yankee’s decision to shut down the plant was prudent. Id. at 65,005. The ALJ also found that extending the license beyond 2000 rather than closing the plant would require Yankee to spend $23 million to obtain a license extension and another $50 to $100 million to purchase a new reactor vessel, and that these costs exceeded other power supply alternatives. Id. at 65,004. Determining that Yankee was not entitled to recover 100% of its costs, the ALJ developed an “equitable sharing” formula under which Yankee could recover 82.3% of its unamor-tized investments and post-shutdown operating and maintenance expenses and 50% of construction-work-in-progress. Id. at 65,-011-13. The ALJ also rejected Norwood’s request that Yankee lower its rate of return on equity, finding no evidence that Yankee’s business and financial risks had decreased because of the shutdown. Id. at 65,016.

The Commission rejected the ALJ’s “equitable sharing” formula. It found that the original Power Contract — as interpreted in Opinion No. 285, a prior Commission opinion — guaranteed Yankee 100% recovery of its unamortized investments and operating and maintenance expenses in the event of premature termination. Yankee Atomic Elec. Co., Opinion No. 390, 67 F.E.R.C. ¶ 61,318, at 62,112-13 (1994) (affirming ALJ decision) (citing Yankee Atomic Elec. Co., Opinion No. 285, 40 F.E.R.C. ¶ 61,372 (1987), aff'd in part, modified in part, and rev’d in part, Opinion No. 285-A, 43 F.E.R.C. ¶ 61,232, 1988 WL 412405 (1988)). Noting that utility investors are “generally entitled to recoup from consumers the full amount of their investment,” Democratic Cent. Comm. v. Washington Metro. Area Transit Comm’n, 485 F.2d 786, 808 (D.C.Cir.1973), cert. denied, 415 U.S. 935, 94 S.Ct. 1451, 39 L.Ed.2d 493 (1974), the Commission concluded that 100% recovery for Yankee was “just and reasonable.” 67 F.E.R.C. at 62,113. Denying Yankee full recovery, the Commission reasoned, would give utilities perverse incentives to operate power plants until they recouped their investment, even though retiring the plant might be more cost-effective. Id. at 62,114. The Commission also granted Yankee 100% recovery of its construction-work-in-progress. Noting that limiting eon-struction-work-in-progress to 50% was logical for plants under construction that had never provided service to customers, the Commission approved full recovery for Yankee because its investments “were made in an attempt to assure that an already used and useful plant could continue to remain used and useful.” Id. at 62,115.

As to the rate of return, the Commission disagreed with the ALJ, finding instead that the shutdown had decreased Yankee’s risk and that Yankee’s rate should therefore be reduced. Id. at 62,120-21. Rejecting the rates proposed by its own staff and by Nor-wood, the Commission proposed instead 9.86%. However, because the Commission concluded that the zone of reasonableness established in its prior order, Opinion No. 285, remained binding, it reduced Yankee’s rate only to 10.75%, the lower end of the zone. Id. at 62,122. Following denial of its petition for rehearing, Norwood filed the petition for review thát is before us now.

II.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cupp v. County of Lycoming
M.D. Pennsylvania, 2022
Sierra Club v. FERC
38 F.4th 220 (D.C. Circuit, 2022)
Maine v. Federal Energy Regulatory Commission
854 F.3d 9 (D.C. Circuit, 2017)
ENGIE Gas & LNG LLC v. Department of Public Utilities
475 Mass. 191 (Massachusetts Supreme Judicial Court, 2016)
Yankee Atomic Electric Co. v. United States
73 Fed. Cl. 249 (Federal Claims, 2006)
LA Pub Svc Cmsn v. FERC
174 F.3d 218 (D.C. Circuit, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
80 F.3d 526, 317 U.S. App. D.C. 50, 1996 U.S. App. LEXIS 6869, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-norwood-massachusetts-v-federal-energy-regulatory-commission-cadc-1996.