Town of Kearny v. Brandt

67 A.3d 601, 214 N.J. 76, 2013 WL 3064600, 2013 N.J. LEXIS 589
CourtSupreme Court of New Jersey
DecidedJune 20, 2013
StatusPublished
Cited by165 cases

This text of 67 A.3d 601 (Town of Kearny v. Brandt) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Kearny v. Brandt, 67 A.3d 601, 214 N.J. 76, 2013 WL 3064600, 2013 N.J. LEXIS 589 (N.J. 2013).

Opinion

Justice PATTERSON

delivered the opinion of the Court.

This construction dispute requires the Court to consider two issues: 1) when a building can be considered substantially complete for purposes of calculating the ten-year period of the statute of repose, N.J.S.A. 2A: 14-1.1(a), and 2) whether the Comparative Negligence Act, N.J.S.A. 2A:15-5.2, and the Joint Tortfeasors Contribution Law, N.J.S.A. 2A:53A-2, authorize allocation of fault at trial to defendants who have obtained dismissals pursuant to the statute of repose, N.J.S.A. 2A:14-l.l(a).

Following structural failures in its public safety facility, plaintiff Town of Kearny (Town) sued the project’s architectural firm, Brandt-Kuybida Architects (Brandt-Kuybida), and three of its individual architects, alleging that Brandh-Kuybida was liable for defects in the facility that rendered it unusable. The Town and Brandt-Kuybida filed claims against the project’s soil engineering firm, Soils Engineering Services, Inc. (SESI), and one of its individual engineers, and structural engineering firm, HarrisonHamnett, P.C. (Harrison-Hamnett), and its principal. The trial court granted summary judgment motions filed by SESI and Harrison-Hamnett on the ground that the Town’s complaint was filed more than ten years after the engineers completed their work on the construction project, ruling that the claims against these defendants were barred by the statute of repose and the statute of limitations. The trial court, however, denied a similar motion filed by the defendant architect, holding that the ten-year [83]*83periods prescribed by the statutes of repose and limitations were triggered by the issuance of the first Temporary Certificate of Occupancy, and, accordingly, the Town’s claims against the architect were timely filed. The trial court also denied BrandtKuybida’s application for an apportionment of fault at trial to SESI and Harrison-Hamnett, pursuant to the Comparative Negligence Act and the Joint Tortfeasors Contribution Law.

The Town appealed. The Appellate Division affirmed the trial court’s application of the statutes of repose and limitations to Brandt-Kuybida but reversed the trial court’s denial of the architect’s application for an apportionment of fault to the dismissed codefendants.

We affirm. We hold that the trial court properly denied Brandt-Kuybida’s motion for summary judgment on the statute of repose issue. We concur with the trial court’s finding that the ten-year period prescribed in N.J.S.A. 2A:14-l.l(a) commenced when the first Temporary Certificate of Occupancy was issued for the Town’s public safety facility. We further hold that, when the claims against a defendant are dismissed on statute of repose grounds, fault may be apportioned to the dismissed defendant under the Comparative Negligence Act and the Joint Tortfeasors Contribution Law.

I.

The South Kearny Improvement Projects Corporation (SKIP) was charged by the Town with the responsibility to oversee the design and construction of a new public safety facility, including police and fire stations. In October 1989, BrandWKuybida submitted a proposal to SKIP to design and plan the new facility. SKIP selected BrandWKuybida to perform the work. A principal of the firm, Louis Brandt, was initially designated as the lead architect. The Town and Brandt-Kuybida executed a contract on April 9, 1990. After Brandt-Kuybida dissolved in 1994, Michael Kuybida became the primary architect for the project.

[84]*84Other professionals were hired for the Town’s project. SKIP directly retained SESI to conduct a soil investigation. SESI completed and reported on its soil investigation in July 1990, and had no further involvement with the facility. Brandt-Kuybida hired Harrison-Hamnett to serve as the structural engineer, with responsibility to design the facility’s foundations, piles, roof structure and wall reinforcement. Harrison-Hamnett completed its work on October 30,1995.

SKIP chose Beleor Construction (Belcor) to build the facility in accordance with Brandt-Kuybida’s design, and, on July 11, 1994, SKIP and Belcor entered into a construction contract. Among other provisions, the construction contract required Belcor to achieve substantial completion of the project within 360 days of the issuance of a Notice to Proceed. That notice was issued on September 12, 1994. The contract between SKIP and Belcor defined substantial completion to be the date upon which the project architect, Brandt-Kuybida, certified that the facility is “sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work for its intended use.”

Construction of the facility began in the fall of 1994. On November 15,1995, Beleor signed a document entitled “Certificate of Substantial Completion” (Certificate). On November 24, 1995, Brandt-Kuybida and SKIP signed that same document. In language similar to that of the July 11, 1994 contract, the Certificate defined the date of substantial completion as “the Date certified by the Architect when construction is sufficiently complete, in accordance with the Contract Documents, so the Owner can occupy or utilize the Work or designated portion thereof for the use for which it is intended, as expressed in the Contract Documents.” The signatories to the Certificate, however, failed to complete it. For reasons that the record does not disclose, the “date of issuance” and the “date of completion” of the project were left blank on the form.

[85]*85According to a December 7, 1995 memorandum from Brandi Kuybida, a November 28,1995 inspection revealed that open items had to be completed and that, while municipal construction, fire and electrical approval had been obtained, approval for the facility’s plumbing was still pending. A December 4, 1995 punch list identified eleven outstanding items requiring additional work. On January 18, 1996, BrandWiuybida wrote to Belcor confirming the continued existence of open items and a pending plumbing inspection of the facility’s showers. It was not until April 5, 1996, that the Kearny Police Department requested permission to occupy its portion of the building. On April 9, 1996, the Town’s Construction Official issued the first Temporary Certificate of Occupancy, limited to the police section of the building and subject to completion of the items in a March 28, 1996 punch list. On May 23, 1996, the Construction Official issued the second Temporary Certificate of Occupancy, permitting the Kearny Fire Department to use its section of the building.

Structural defects in the facility surfaced shortly after the Kearny Police Department took occupancy. The building settled differentially, causing gaps between the ceiling and a wall, as well as leaks, buckled tiles and cracks in the walls. The Kearny Police Department reported leaks in various parts of the building and doors that could not close because they did not fit in their frames. Although the Town continued to use the facility, there were further complaints about structural flaws in the building. In 2003, the Town’s Construction Official received an emergency call that the ceiling in the police dispatch area of the building was about to collapse. By 2007, ceilings in the facility had fallen, pipes had separated and pulled, and glass had broken, all of which were attributed to uneven settlement. The Town never issued a final certificate of occupancy. The Town’s Construction Official ordered all occupants to evacuate the building on February 8, 2007.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

David Timpanaro v. Jenkinson's Pavilion, Inc.
New Jersey Superior Court App Division, 2025
Jacqueline Mhrez v. First National Collection Bureau, Inc.
New Jersey Superior Court App Division, 2025
Jessica Hoffer Kaylor v. Teresa Bacallao
New Jersey Superior Court App Division, 2025
Estate of Victor Gaza, Jr. v. Joseph Popovich, M.D.
New Jersey Superior Court App Division, 2025
Michael P. Ryan v. Hammonton Town Board of Education
New Jersey Superior Court App Division, 2025
Kenneth S. Javerbaum, Etc. v. State of New Jersey
New Jersey Superior Court App Division, 2025
922 Rvd, LLC v. Bc International Group, Inc.
New Jersey Superior Court App Division, 2024
Robert J. Triffin v. Travelers
New Jersey Superior Court App Division, 2024
Kenneth Hagel v. Kevin Davenport
New Jersey Superior Court App Division, 2024
Yecheskel "Charlie" Schwab v. Joyce Blay and Hershel Herskowitz
New Jersey Superior Court App Division, 2023
Glen J. Heuman v. Wayne Heuman
New Jersey Superior Court App Division, 2023
Morris Properties, Inc. v. Jonathan Wheeler
New Jersey Superior Court App Division, 2023

Cite This Page — Counsel Stack

Bluebook (online)
67 A.3d 601, 214 N.J. 76, 2013 WL 3064600, 2013 N.J. LEXIS 589, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-kearny-v-brandt-nj-2013.