Daidone v. Buterick Bulkheading

924 A.2d 1193, 191 N.J. 557, 2007 N.J. LEXIS 706
CourtSupreme Court of New Jersey
DecidedJune 26, 2007
StatusPublished
Cited by91 cases

This text of 924 A.2d 1193 (Daidone v. Buterick Bulkheading) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Daidone v. Buterick Bulkheading, 924 A.2d 1193, 191 N.J. 557, 2007 N.J. LEXIS 706 (N.J. 2007).

Opinion

Justice RIVERA-SOTO

delivered the opinion of the Court.

This appeal addresses a discrete issue: whether, under the circumstances present in this matter, the Statute of Repose, N.J.S.A. 2A:14-1.1, should not commence until the issuance of a certificate of occupancy notwithstanding the completion of work by subcontractors at an earlier date. In this case, plaintiffs John and Laura Daidone acted as their own general contractor and sub *560 contracted with several contractors to perform specific portions of the work in respect of the design and construction of their home. Among those, defendants Scott Lepley, Lepley Design Group, and Lepley-McCorry Architects ALA, P.C. (collectively, Lepley) designed plaintiffs’ home, and defendant Buterick Bulkheading, Inc. installed the pilings for the home’s foundation. More than ten years after both Lepley and Buterick completed their respective portions of the work, but less than ten years after a certificate of occupancy was issued for plaintiffs’ home, plaintiffs sued Lepley and Buterick alleging negligence and other claims. Plaintiffs claim that the relevant start date for Statute of Repose purposes must be the date on which the certificate of occupancy issues; Lepley and Buterick assert that the start date must be when they completed their work.

The plain language of N.J.S.A. 2A:14-l.l(a) is clear: no action for deficient design or construction of an improvement to real property may be brought “more than 10 years after the performance or furnishing of such services and construction.” (Emphasis supplied). If the design or construction services provided continue up to and including the date the certificate of occupancy is issued for the improvements made, then the start date for Statute of Repose purposes is the date of the certificate of occupancy. However, if the design or construction services are completed before a certificate of occupancy is issued and the designer or contractor has no further functions to perform in respect of that construction project, then the start date for Statute of Repose purposes is the date on which the designer or contractor has completed his or her portion of the work.

I.

Commencing sometime prior to February 1993, plaintiffs took steps to build their home in Forked River, Lacey Township. Although plaintiffs acted as their own general contractor, 1 plain *561 tiffs hired Lepley to provide the architectural design for that home, which design includéd a piling system to support the structure. Lepley prepared and, on February 19, 1993, certified those plans. The Lacey Township Construction Official approved those plans on June 23, 1993. Once the plans were approved, Lepley’s retention as an architect was completed, and Lepley had no continuing role or responsibilities in respect of the design or construction of plaintiffs’ home. Significantly, plaintiffs did not retain Lepley to perform any construction supervisory services or the like.

After the plans were completed by Lepley and approved by Lacey Township, plaintiffs contracted with Buterick to install the foundation pilings as designed by Lepley. Buterick did so, had the completion of its work in accordance with the plans certified by a professional engineer, and invoiced plaintiffs for all work Buterick performed. On May 24, 1994, plaintiffs paid Buterick’s bill in full with a check issued on the account of “DRN Contracting.” Once its piling services were completed, Buterick performed no further work on plaintiffs’ home. A certificate of occupancy for *562 the home was issued on June 14, 1994 and, thereafter, plaintiffs occupied it.

Starting in 1999, five years after plaintiffs had moved into their home, plaintiffs experienced a number of problems resulting from the home settling on its foundations. According to plaintiffs, their “home settled as a result of the improper installation of the pilings supporting that home and the improper design of the ground level slab[.]” In his deposition, plaintiff John Daidone described the “settling” as follows:

Something was not either designed right or installed right. Slabs should not settle as they settled.
Q. What do you mean slabs should not settle as they settled?
A..... Because the utilities, the boiler and the hot water heater are on a platform that sits on the slab..... But what’s happening, as the slab was settling all the pipes and everything else are ripping out of the ceiling. The natural gas pipe coming in from the meter was being stressed. You could still see the marks in the ceiling..... We had to shim up basically the platform two inches to relieve that stress, all right.
The sewerage waste pipe which goes through the floor out, that was ripping through. That was just coming down too because of the settlement. So we had to cut that and put a rubber gasket. The rubber gasket is still there. We had to do that in two places. The electrical panel had to be lifted up because it was being stressed.
Q.....You said if you didn’t take these precautions that you could not live in the house. The house would have been uninhabitable?
A. Yeah, ‘cause the furnace wouldn’t have worked, the boiler, the hot water, everything was ripping out of the ceilings, the pipe, the heating. It’s all hot water baseboard. They were all ripping out of the ceiling and bending.
Q. You said natural gas was pulling too?
A. The natural gas pipe. You could see it till today. When it was put in it was horizontal. Now it’s pitched down because it was being dragged down.

Although plaintiffs noticed these changes as early as 1999, they did not seek any expert assistance until late 2001, when they retained an expert to perform a subsurface investigation and geotechnical evaluation of their home. In a report dated January 2, 2002, the expert opined that “the basement structure has settled due to the underlying soft soils and organics present.” Significantly, after describing the length of the pilings installed, plaintiffs’ expert did not conclude that the design or installation of the *563 pilings was deficient. The most the expert would say is that “[t]he length of these timber pilings below the ground surface may not be enough based on the information available from the soil borings.” (Emphasis supplied).

Based on their expert’s advice, plaintiffs undertook repairs to their home, which repairs cost approximately $90,000 and were completed by July 2002. Plaintiffs, however, did not file their complaint against either Lepley or Buterick until June 2, 2004. Although that date was within ten years after plaintiffs secured a certificate of occupancy for their home, it was more than ten years after both Lepley and Buterick had performed and completed their services.

Lepley and Buterick moved to dismiss plaintiffs’ complaint as barred by the Statute of Repose, which the trial court granted.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
924 A.2d 1193, 191 N.J. 557, 2007 N.J. LEXIS 706, Counsel Stack Legal Research, https://law.counselstack.com/opinion/daidone-v-buterick-bulkheading-nj-2007.