Town of Boylston v. Federal Energy Regulatory Commission

21 F.3d 1130, 305 U.S. App. D.C. 382, 1994 U.S. App. LEXIS 8333
CourtCourt of Appeals for the D.C. Circuit
DecidedApril 22, 1994
DocketNo. 92-1261
StatusPublished
Cited by8 cases

This text of 21 F.3d 1130 (Town of Boylston v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Town of Boylston v. Federal Energy Regulatory Commission, 21 F.3d 1130, 305 U.S. App. D.C. 382, 1994 U.S. App. LEXIS 8333 (D.C. Cir. 1994).

Opinion

Opinion for the Court filed by Circuit Judge STEPHEN F. WILLIAMS.

STEPHEN F. WILLIAMS, Circuit Judge:

Boston Edison Company has estimated that the decommissioning of its “Pilgrim 1” nuclear plant (operating under a license that will expire in 2008) will cost $121.9 million in 1986 dollars. Believing that current customers should meet this expense as they use the power, Boston Edison in 1986 filed rates with the Federal Energy Regulatory Commission to impose such a charge on 13 municipal purchasers (which FERC collectively calls the “Municipals”). See Federal Power Act § 205, 16 U.S.C. § 824d (1988). In the aggregate the Municipals held entitlements to about 3% of the power from Pilgrim; the remaining sales are evidently either non-jurisdictional or to customers that agreed to the charge. See Boston Edison Letter to FERC, August 8, 1986, at 4. In making the filing Boston Edison argued that the charge was authorized by its contracts with the Municipals (which are identical except as to identity of the purchaser and the percent of output purchased). The Commission agreed. Boston Edison Company, 52 FERC ¶ 61,010 (1990) (“Opinion No. 350”); see also Boston Edison Company, 59 FERC ¶ 61,062 (1992) (“Opinion No. 350-A”) (denying Boston Edison’s petition for rehearing). Because we find the Commission’s reading of the contract unsustainable, even with the deference we owe its interpretation, see National Fuel Gas Supply Corp. v. FERC, 811 F.2d [1132]*11321563, 1569 (D.C.Cir.1987), we reverse and remand for further consideration.

* * # * * *

There is no dispute over whether the Municipals are ultimately liable for their share of decommissioning costs. Indeed, to support their view that the costs are payable to Boston Edison only when they are incurred, the Municipals rely in part on the section that establishes a right to reimbursement, Paragraph 7.0, entitled “Shutdown or Permanent Retirement”:

Buyer agrees to reimburse seller for [a specified percentage] of any dismantlement or removal costs or expenses incurred by Seller in the shutdown, or permanent retirement, or both, of the Unit, including but not limited to any cost of removal commenced within three years after the end of the term or the date of cancellation.

The Municipals suggest that the term “reimburse” and the use of the past tense — “incurred” — imply that the expenditure at issue will have already occurred.

The Commission, however, relied on the contract’s provision for a monthly capacity charge, and, more particularly, on the paragraph explaining the computation of its depreciation component, Par. C-6.3.1:

Depreciation applicable to the facilities shall be computed on a straight line basis using Gross Investment and a service life of twenty-eight (28) years or until such time as the depreciation reserve equals the gross investment as defined below, at which time depreciation shall cease. For depreciation purposes, Gross Investment as defined in C-4.0 shall be adjusted to exclude associated land costs, nuclear fuel investment, prepaid and working capital items, materials and supplies. Plant retirements, both normal and extraordinary, including salvage values and cost of removal, shall also be reflected through this subparagraph in a manner consistent with the method of handling on the Seller’s books of account.

(Emphasis added.) The Commission reads the last sentence to permit collection of estimated decommissioning costs on a current basis. In support of its reading, it makes two main arguments. First, this interpretation accords with the general ratemaking principle that costs should be “collected currently from the customers benefitting from the service provided by the facility.” Opinion No. 350, 52 FERC at 61,075. Indeed, the Municipals themselves acknowledge the principle, though not the contractual obligation, arguing that it should be fulfilled by their paying estimated decommissioning costs on a current basis into a special trust fund, which would be better for them from a tax perspective than paying Boston Edison currently. See Boston Edison Company, 42 FERC ¶ 63,033, 65,220, 65,223 (1988) (“Initial Decision”).1

Second, the Commission offers an interpretation that, it says, embodies the contract principle of reconciling apparently contradictory clauses “by affording each provision the fullest meaning possible.” Opinion No. 350, 52 FERC at 61,075. Specifically, FERC fits Par. 7.0 together with C-6.3.1 in the following way: While C-6.3.1 provides for periodic collection of estimated costs, Par. 7.0 serves a clean-up function,

imposing an obligation upon the Municipals, which continues after termination of service pursuant to the contract, to reimburse Boston Edison for their share of costs incurred in decommissioning the plant to the extent such costs have not been recovered during the period of operation of the plant.

Id. (emphasis added). In the absence of Par. 7.0, the Commission explains, “Boston Edison would not be able to recover such costs from purchasers who are no longer taking service at the time of plant retirement.” Id.

The Municipals, however, claim that the contract’s specific terms for calculating depreciation undercut the Commission’s view. According to Par. C-6.3.1, when “the depre[1133]*1133ciation reserve [i.e., aggregate amount charged as depreciation] equals the gross investment as defined below, ... depreciation shall cease.” If depreciation includes amounts for decommissioning, the Municipals argue, the depreciation reserve will reach the level of gross investment, and depreciation will therefore terminate, well before Boston Edison has fully recouped its original investment.

The force of the Municipals’ argument would seem to turn on how gross investment is computed. If the decommissioning costs go into gross investment, then the argument disintegrates; the costs are on both sides of the process and exhaustion of depreciable gross investment occurs when it should, not prematurely.

At this point, rather than turning to the contract provisions on gross investment, the Commission took what to us is an incomprehensible leap. It declared that the last sentence of C-6.3.1, rather than authorizing an additional element of depreciation, “provide[d] for recovery of decommissioning expenses as a separate cost component of the formula rate.” Opinion No. 350, 52 FERC at 61,076. This interpretation appeared to disregard the phrase in the last sentence of C-6.3.1 that requires that plant retirements, etc., “shall also be reflected through this subparagraph ”. The Commission dealt with the phrase by saying it required only that decommissioning costs would be “recoverable as a discrete cost component through the monthly capacity charge”. Opinion No. 350-A, 59 FERC at 61,259.

But the contract takes a fairly orderly outline form, with C-6.1 defining the annual capacity charge as the sum of two items, demand charges' (covered in C-6.2 and its subparts) and investment expenses (covered in C-6.3 and its subparts). Evidently the Commission reads “subparagraph” in the depreciation clause, C-6.3.1, as referring to some much broader concept, perhaps the capacity charge that C-6.1 defines.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
21 F.3d 1130, 305 U.S. App. D.C. 382, 1994 U.S. App. LEXIS 8333, Counsel Stack Legal Research, https://law.counselstack.com/opinion/town-of-boylston-v-federal-energy-regulatory-commission-cadc-1994.