Tolboe Construction Co. v. Staker Paving & Construction Co.

682 P.2d 843, 1984 Utah LEXIS 830
CourtUtah Supreme Court
DecidedApril 30, 1984
Docket18691
StatusPublished
Cited by16 cases

This text of 682 P.2d 843 (Tolboe Construction Co. v. Staker Paving & Construction Co.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tolboe Construction Co. v. Staker Paving & Construction Co., 682 P.2d 843, 1984 Utah LEXIS 830 (Utah 1984).

Opinions

SAM, District Judge:

Plaintiff appeals from a judgment for defendant in an action to recover damages resulting from defendant’s refusal to perform certain paving work according to a bid it submitted to plaintiff.

On September 7, 1979, Plaintiff Tolboe Construction Company, a licensed general contractor, submitted a bid to the Veteran’s Administration for the construction of a “Clinical and Ambulatory Care” addition to the Veteran’s Administration Hospital in Salt Lake City.

On the same day and just prior to the submission of its bid, plaintiff received bids from three subcontractors for the asphalt paving section of the project. The bids for that particular section consisted of a base bid and an alternate bid, delineated as alternate No. 4. The following are the bids submitted by the subcontractors:

Company Base Bid Alternate No. 4
Staker Bavins & Construction $ 29,081 $110,547
Geneva Rock Products 84,800 58,590
Gibbons & Reed 102,188 57,007

Upon receiving these bids and recognizing the large disparity between defendant Staker’s base bid and that of the other subcontractors, Michael Tolboe, acting on behalf of the plaintiff company and pursuant to its policy to verify a bid which is 10 to 15 percent below other bids, telephoned defendant and informed William Morris, defendant’s estimator, that the bid was low and should be reviewed. Following that conversation, Mr. Morris reexamined his calculations and determined once again that they were accurate; whereupon, he telephoned Mr. Tolboe and reconfirmed the bid. On the basis of that confirmation, plaintiff incorporated defendant’s bid into the general bid on the In addition to submitting a bid to plaintiff, defendant also submitted one on the same day to another general contractor bidding on the hospital project, namely, the Oakland Construction Company (hereinafter “Oakland”). Oakland also noted a substantial disparity between defendant’s bid and others it had received, and like plaintiff, called Staker to verify the low bid. In that telephone conversation, Ken Hutchins, Oakland’s representative, reviewed with Mr. Morris (defendant’s estimator) the items included in the bid to determine why it was so low. As a result of that conversation, Oakland determined that the Staker bid was incomplete and rejected it.

On or about November 1, 1979, a meeting was held between Mr. Tolboe and Mr. Morris, at the request of Mr. Tolboe, to [845]*845discuss details of the project. During that meeting Mr. Tolboe mentioned the paving of a certain parking lot (parking lot No. 1), and was immediately informed by Mr. Morris that defendant’s bid did not include the paving of that particular lot because it had not been specified in the plans. A meeting was then arranged and held later that same day with Gordon Staker to discuss the problem further. Mr. Staker advised Mr. Tolboe at that time that defendant would not perform the paving work for the amount of its bid if the subcontract required paving parking lot No. 1.

On November 5, 1979, plaintiff received the contract for the Veteran’s Administration Hospital project (the base bid only). Upon receiving said contract, plaintiff immediately contacted defendant to discuss the first phase of the work required under the contract. Again, Mr. Tolboe was informed that defendant would not perform until the problem regarding parking lot No. 1 was resolved and the scope of work clarified.

At a meeting held in late November, 1979, with all parties present, it was determined, by reviewing the plans and specifications available to defendant at the time the subcontract bid was prepared, that Mr. Morris had overlooked certain specifications when preparing defendant’s bid and thus had made an error in calculating. Defendant acknowledged the mistake but refused to perform the substantially greater quantity of work on the basis of the erroneous bid.

As a consequence, plaintiff had to perform some of the initial work which was to be included in the paving subcontract, and thereafter, to subcontract the balance of the work to Geneva Rock Products. According to plaintiff’s evidence, the amount ultimately expended for the asphalt paving work was $101,744, which included costs for the work done by plaintiff of $15,494 and costs for the subcontractor’s performance of $83,360. Plaintiff therefore alleges that its reliance upon defendant’s bid resulted in damages of $72,663, that being the amount the actual costs for the paving work exceeded defendant’s bid of $29,081.

Plaintiff prosecuted this action at trial on the theory of promissory estoppel, which has been defined in the Restatement (Second) of Contracts § 90 as follows:

A promise which the promisor should reasonably expect to induce action or for-ebearance on the part of the promisee or a third person and which does induce such action or forebearance is binding if injustice can be avoided only by enforcement of the promise. The remedy granted for breach may be limited as justice requires.

Staker’s defense against the aforesaid theory was that plaintiff could not produce the necessary evidence to establish an essential element of the doctrine of promissory estoppel, namely, that the promisee’s reliance was reasonable or justifiable under the circumstances. At the conclusion of the presentation of evidence, the question of the reasonableness of plaintiff’s reliance was submitted to an advisory jury, which returned a verdict as follows: “We, the jurors, impaneled in the above case, find that the plaintiff Tolboe Construction Company did not reasonably rely on the bid given to them by Staker Paving & Construction Company.” This verdict was adopted by the trial court and judgment was entered accordingly, in defendant’s favor. Plaintiff appealed.

The principal contention raised by plaintiff on appeal is that the undisputed facts of this case warrant the application of the doctrine of promissory estoppel and that the trial court’s ruling to the contrary was therefore erroneous.

The doctrine of promissory estoppel and the prerequisites for an action based thereupon have been described by this Court as follows:

[Promissory estoppel] is a doctrine of equity which the plaintiff could claim the benefit of only by showing the facts required to justify its application. These would include that the defendants were aware of all the material facts; that in such awareness they made the promise [846]*846when they knew that the plaintiff was acting in reliance on it; that the latter, observing reasonable care and prudence, acted in reliance on the promise and got into a position where it suffered a loss. Under such circumstances, equity recognizes the unfairness of permitting withdrawal of the promise and will enforce it.[1] [Emphasis added.]

The focus of this appeal is limited to the underscored prerequisite regarding the reasonableness of the plaintiffs reliance.

Plaintiff asserts that it took every reasonable precaution to ensure the accuracy and validity of defendant’s bid before relying upon it. Specifically, plaintiff refers to its telephone call to defendant’s estimator after discovering the disparity between defendant’s bid and the others, wherein plaintiff informed the estimator that his bid was substantially low and suggested that he review it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S6 v. Wing Enterprises
2024 UT App 105 (Court of Appeals of Utah, 2024)
In re Estate of Berrey
2024 UT App 21 (Court of Appeals of Utah, 2024)
Anderson v. Larry H. Miller Communications Corp.
2015 UT App 134 (Court of Appeals of Utah, 2015)
Henshaw v. Estate of King
2007 UT App 378 (Court of Appeals of Utah, 2007)
UTCO Associates, Ltd. Ex Rel. Kent v. Zimmerman
2001 UT App 117 (Court of Appeals of Utah, 2001)
Nunley v. Westates Casing Services, Inc.
1999 UT 100 (Utah Supreme Court, 1999)
Skanchy v. Calcados Ortope SA
952 P.2d 1071 (Utah Supreme Court, 1998)
FC STANGL, III v. Ernst Home Center
948 P.2d 356 (Court of Appeals of Utah, 1997)
Triax Pacific, Inc. v. American Ins. Co.
69 F.3d 548 (Tenth Circuit, 1995)
King v. Nevada Elec. Inv. Co.
59 F.3d 178 (Third Circuit, 1995)
Brown v. Weis
871 P.2d 552 (Court of Appeals of Utah, 1994)
Atiya v. Salt Lake County
852 P.2d 1007 (Court of Appeals of Utah, 1993)
Andreason v. Aetna Casualty & Surety Co.
848 P.2d 171 (Court of Appeals of Utah, 1993)
Guardian State Bank v. Stangl
778 P.2d 1 (Utah Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
682 P.2d 843, 1984 Utah LEXIS 830, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tolboe-construction-co-v-staker-paving-construction-co-utah-1984.